Build the cronograma fisico-financeiro from the orcamento

Take the priced orcamento as the source, sequence the work, link every item to the activity that earns it, spread the money over the periods, prove the periods sum to the contract total and publish the curve with the proposal.

6 алхам16 минЕрөнхий гүйцэтгэгчХөгжүүлэгч / захиалагчТөслийн / барилгын менежментийн компани

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 6 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Start from the priced orcamento, not from a summary

Ажил материалын жагсаалт

Open the priced bill and confirm that every item carries a quantity, a unit and a value, and that the group structure is the one the cronograma will report against. Fix the structure here rather than inventing a second grouping for the schedule.

Яагаад: Lei 14.133 of 2021 requires the works package to carry a detailed budget grounded in measured quantities, so the bill is the legal source of the figures and the cronograma is a view of it. A curve built from a summary sheet quietly becomes a third document with a total of its own, and the first medicao is where the three are discovered to disagree.

ОролтPriced bill positionsItem groups of the orcamentoҮр дүнContract total to be spreadQuantities behind every figure
2

Sequence the work into a programme

4D хуваарь

Build the activities the work is actually done in, give each one a duration that comes from the quantity and the crew rather than from the calendar you would like, and set the dependencies between them. Name the milestones the contract will be measured against.

Яагаад: The physical half of the cronograma is the half that gets skipped, because the financial half can be produced by dividing the total into equal months and nobody notices for a quarter. A programme built from quantities and crews is the only version that answers the question the client will ask in month three, which is whether the plan was ever achievable.

ОролтMethod and crew sizesQuantities behind every figureҮр дүнBaseline programmeMilestone dates named
3

Link every item to the activity that earns it

5D өртөгийн загвар

Attach each bill item to the activity that will earn it, splitting an item across two activities where the work really is done in two places. Then look at what is left over on both sides: items no activity earns, and activities that earn nothing.

Яагаад: The leftovers are the finding. An item nothing earns is usually work that was priced and then left out of the plan, and an activity earning nothing is usually work that will be done and was never priced. Both are cheap to fix now and expensive to discover during a medicao, when one of them is already built.

ОролтBaseline programmePriced bill positionsҮр дүнEvery item linked to an activityItems no activity earns
4

Spread the money over the measurement periods

Санхүү

Let the linked values fall into the periods the contract measures in, and read the cumulative curve as well as the monthly bars. Note the month of peak funding and what the advance, if there is one, does to it.

Яагаад: The client reads the cronograma as a budget commitment and the contractor reads it as working capital, and the two readings meet at the peak. Named in advance it is a financing decision. Discovered in month five it is a conversation about slowing the work down, which costs both parties more than the finance would have.

ОролтEvery item linked to an activityMeasurement periods of the contractҮр дүнCash forecast per periodPeak funding named
5

Prove the periods add up to the contract sum

Шалгалт

Run the check that the sum of the periods equals the total of the priced bill, and that no period is negative or empty in the middle of continuous work. Chase any difference back to the item that caused it rather than adjusting the last month to close it.

Яагаад: A cronograma that does not total to the contract sum will be rejected on sight, and closing the gap by editing the final month hides whatever caused it, usually an item linked twice or linked to nothing. The check takes seconds and the diagnosis it gives is the part worth having.

ОролтCash forecast per periodContract total to be spreadҮр дүнValidation report on the totalsDifference to explain
6

Publish it as the baseline the medicoes report against

Тайлан

Export the physical and the financial halves as one document with the same period headings, and keep the version that went with the proposal as the baseline. Later revisions are compared against it rather than replacing it silently.

Яагаад: Every medicao is read against the cronograma, and the whole conversation about delay depends on which version of it both sides are holding. A baseline kept as issued makes the comparison a fact. A cronograma quietly updated each month makes the job look on programme until the last month, when the remaining work no longer fits in it.

ОролтCash forecast per periodBaseline programmeҮр дүнCronograma export for the proposalBaseline the medicoes report against
Модулиуд

Энэ тоглолтын модулиуд

Платформын 190 модулиас 6

The market this case is written for

Бразил

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Төлөвлөлт ба хяналт дахь бусад

Төлөвлөлт ба хяналт

Төсөл байгуулж, шилжүүлэн өгөх

Ажлыг хамгийн эхний тохиргооноос эхлээд шилжүүлэн өгөх хүртэл авч яв. Үүнийг үүсгэ, ажлыг үн…

5 алхам20 минНээх
Төлөвлөлт ба хяналт

Earned value ба гарцын тооцоо

Ажил төлөвлөгөө, төсвийн эсрэг яг хаана байгааг харах: хуваарийг шинэчилж, CPI, SPI-г уншиж,…

3 алхам13 минНээх