orçamento から cronograma físico-financeiro を組み立てる

積算済みの orçamento を出発点とし、work を順序立て、各項目をそれを稼ぐ活動に結び付け、金額を各期間に配分し、各期間の合計が契約総額に一致することを証明し、そのカーブを提案書とともに公表する。

6ステップ16 分総合建設会社デベロッパー / 発注者プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で6ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Start from the priced orcamento, not from a summary

内訳書

Open the priced bill and confirm that every item carries a quantity, a unit and a value, and that the group structure is the one the cronograma will report against. Fix the structure here rather than inventing a second grouping for the schedule.

理由: Lei 14.133 of 2021 requires the works package to carry a detailed budget grounded in measured quantities, so the bill is the legal source of the figures and the cronograma is a view of it. A curve built from a summary sheet quietly becomes a third document with a total of its own, and the first medicao is where the three are discovered to disagree.

入力Priced bill positionsItem groups of the orcamento出力Contract total to be spreadQuantities behind every figure
2

Sequence the work into a programme

4Dスケジュール

Build the activities the work is actually done in, give each one a duration that comes from the quantity and the crew rather than from the calendar you would like, and set the dependencies between them. Name the milestones the contract will be measured against.

理由: The physical half of the cronograma is the half that gets skipped, because the financial half can be produced by dividing the total into equal months and nobody notices for a quarter. A programme built from quantities and crews is the only version that answers the question the client will ask in month three, which is whether the plan was ever achievable.

入力Method and crew sizesQuantities behind every figure出力Baseline programmeMilestone dates named
3

Link every item to the activity that earns it

5Dコストモデル

Attach each bill item to the activity that will earn it, splitting an item across two activities where the work really is done in two places. Then look at what is left over on both sides: items no activity earns, and activities that earn nothing.

理由: The leftovers are the finding. An item nothing earns is usually work that was priced and then left out of the plan, and an activity earning nothing is usually work that will be done and was never priced. Both are cheap to fix now and expensive to discover during a medicao, when one of them is already built.

入力Baseline programmePriced bill positions出力Every item linked to an activityItems no activity earns
4

Spread the money over the measurement periods

財務

Let the linked values fall into the periods the contract measures in, and read the cumulative curve as well as the monthly bars. Note the month of peak funding and what the advance, if there is one, does to it.

理由: The client reads the cronograma as a budget commitment and the contractor reads it as working capital, and the two readings meet at the peak. Named in advance it is a financing decision. Discovered in month five it is a conversation about slowing the work down, which costs both parties more than the finance would have.

入力Every item linked to an activityMeasurement periods of the contract出力Cash forecast per periodPeak funding named
5

Prove the periods add up to the contract sum

検証

Run the check that the sum of the periods equals the total of the priced bill, and that no period is negative or empty in the middle of continuous work. Chase any difference back to the item that caused it rather than adjusting the last month to close it.

理由: A cronograma that does not total to the contract sum will be rejected on sight, and closing the gap by editing the final month hides whatever caused it, usually an item linked twice or linked to nothing. The check takes seconds and the diagnosis it gives is the part worth having.

入力Cash forecast per periodContract total to be spread出力Validation report on the totalsDifference to explain
6

Publish it as the baseline the medicoes report against

レポート

Export the physical and the financial halves as one document with the same period headings, and keep the version that went with the proposal as the baseline. Later revisions are compared against it rather than replacing it silently.

理由: Every medicao is read against the cronograma, and the whole conversation about delay depends on which version of it both sides are holding. A baseline kept as issued makes the comparison a fact. A cronograma quietly updated each month makes the job look on programme until the last month, when the remaining work no longer fits in it.

入力Cash forecast per periodBaseline programme出力Cronograma export for the proposalBaseline the medicoes report against
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 6

The market this case is written for

ブラジル

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

計画と管理の他のケース

計画と管理

プロジェクトを立ち上げ、引き渡す

最初の立ち上げから引き渡しまで、プロジェクトを一気通貫で進める。作成し、工事を価格付けし、工程を計画し、現場で追跡し、きれいに完了させる。ライフサイクル全体を5ステップで。

5ステップ20 分開く
計画と管理

ベースラインを構築し進捗を追跡する

工程を計画し、比較の基準となるベースラインを固定し、現場の実績をフィードバックし、差異を読み取ることで遅延を早期に把握する。

4ステップ12 分開く
計画と管理

アーンドバリューと実績予測

計画と予算に対して案件が本当にどこに立っているかを把握する。工程を最新化し、CPIとSPIを読み取り、実績コストと完了予定日について信頼できる数値を出す。

3ステップ13 分開く