프로젝트 설정 및 인도
프로젝트를 최초 설정부터 최종 인도까지 처리한다. 프로젝트를 생성하고, 공사비를 산정하며, 공정을 계획하고, 현장에서 진척을 관리한 후 깔끔하게 마무리한다. 전체 생…
가격이 매겨진 orçamento를 출처로 삼고, work의 순서를 정하고, 각 항목을 그것을 벌어들이는 활동에 연결하고, 금액을 각 기간에 분산하고, 각 기간의 합이 계약 총액과 일치함을 증명하고, 그 곡선을 제안서와 함께 공개한다.
플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.
Open the priced bill and confirm that every item carries a quantity, a unit and a value, and that the group structure is the one the cronograma will report against. Fix the structure here rather than inventing a second grouping for the schedule.
이유: Lei 14.133 of 2021 requires the works package to carry a detailed budget grounded in measured quantities, so the bill is the legal source of the figures and the cronograma is a view of it. A curve built from a summary sheet quietly becomes a third document with a total of its own, and the first medicao is where the three are discovered to disagree.
Build the activities the work is actually done in, give each one a duration that comes from the quantity and the crew rather than from the calendar you would like, and set the dependencies between them. Name the milestones the contract will be measured against.
이유: The physical half of the cronograma is the half that gets skipped, because the financial half can be produced by dividing the total into equal months and nobody notices for a quarter. A programme built from quantities and crews is the only version that answers the question the client will ask in month three, which is whether the plan was ever achievable.
Attach each bill item to the activity that will earn it, splitting an item across two activities where the work really is done in two places. Then look at what is left over on both sides: items no activity earns, and activities that earn nothing.
이유: The leftovers are the finding. An item nothing earns is usually work that was priced and then left out of the plan, and an activity earning nothing is usually work that will be done and was never priced. Both are cheap to fix now and expensive to discover during a medicao, when one of them is already built.
Let the linked values fall into the periods the contract measures in, and read the cumulative curve as well as the monthly bars. Note the month of peak funding and what the advance, if there is one, does to it.
이유: The client reads the cronograma as a budget commitment and the contractor reads it as working capital, and the two readings meet at the peak. Named in advance it is a financing decision. Discovered in month five it is a conversation about slowing the work down, which costs both parties more than the finance would have.
Run the check that the sum of the periods equals the total of the priced bill, and that no period is negative or empty in the middle of continuous work. Chase any difference back to the item that caused it rather than adjusting the last month to close it.
이유: A cronograma that does not total to the contract sum will be rejected on sight, and closing the gap by editing the final month hides whatever caused it, usually an item linked twice or linked to nothing. The check takes seconds and the diagnosis it gives is the part worth having.
Export the physical and the financial halves as one document with the same period headings, and keep the version that went with the proposal as the baseline. Later revisions are compared against it rather than replacing it silently.
이유: Every medicao is read against the cronograma, and the whole conversation about delay depends on which version of it both sides are holding. A baseline kept as issued makes the comparison a fact. A cronograma quietly updated each month makes the job look on programme until the last month, when the remaining work no longer fits in it.
플랫폼 190개 모듈 중 6개
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.
프로젝트를 최초 설정부터 최종 인도까지 처리한다. 프로젝트를 생성하고, 공사비를 산정하며, 공정을 계획하고, 현장에서 진척을 관리한 후 깔끔하게 마무리한다. 전체 생…
공정표를 계획하고, 비교 기준이 될 베이스라인을 확정하고, 현장의 실제 진척을 반영한 뒤 편차를 확인하여 지연을 조기에 발견합니다.
현장이 계획과 예산 대비 실제로 어디에 있는지 파악합니다. 공정표를 최신화하고, CPI와 SPI를 확인한 뒤, 준공 예상 비용과 예상 완료일에 신뢰할 수 있는 값을…