Score a tender on price and preference under the PPPFA

Choose the points ratio the value of the tender dictates, state the specific goals in the tender document, level the priced bills so the price you score is comparable, then score price by formula and preference on what you published.

7 алхам13 минХөгжүүлэгч / захиалагчТөслийн / барилгын менежментийн компаниӨртгийн зөвлөгөө / QS

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 7 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Set the ratio and publish the specific goals

Тендер

Take the ratio from your own estimate of the value: 80 points for price and 20 for preference up to R50 million, 90 and 10 above it. Then write into the tender document the specific goals that will earn the preference points and the number of points each is worth, together with the proof a bidder must submit to claim them.

Дэлгэцийн зураг, 1-р алхам: Set the ratio and publish the specific goals (Тендер, Score a tender on price and preference under the PPPFA)
Тендер: Set the ratio and publish the specific goals

Яагаад: Under the Preferential Procurement Policy Framework Act 5 of 2000 the goals are the organ of state's to choose, but only in the tender document and only in advance. Goals that commonly appear include the bidder's B-BBEE contributor status level, but nothing is scored by default: an evaluation committee that awards points for a goal the advertisement never mentioned has given every unsuccessful bidder a review, and one that ignores a goal it did publish has done the same.

ОролтPre-tender estimateProcurement policyҮр дүнPoints ratioPublished specific goals
2

Register the bids and test them for responsiveness

Тендерийн удирдлага

Log every bid received with its price and the returnable schedules it came with, then run the responsiveness check before any scoring: CIDB registration current and of the right designation, tax status, the goal claims supported by the proof the tender asked for.

Дэлгэцийн зураг, 2-р алхам: Register the bids and test them for responsiveness (Тендерийн удирдлага, Score a tender on price and preference under the PPPFA)
Тендерийн удирдлага: Register the bids and test them for responsiveness

Яагаад: Responsiveness is a gate and not a score. A bid that fails it never reaches the points table, and mixing the two up is how a committee ends up defending why it gave a non-responsive bid 78 points instead of why it set the bid aside. Doing the check first, in writing, is what makes the rest of the evaluation short.

ОролтSubmitted bidsReturnable schedulesҮр дүнBid registerResponsiveness check
3

Level the priced bills item by item

Ажил материалын жагсаалт

Put the priced bills side by side at item level, find the arithmetic errors, the items priced at nil and the qualifications written into a covering letter, and raise a query on each before the price goes into the formula.

Дэлгэцийн зураг, 3-р алхам: Level the priced bills item by item (Ажил материалын жагсаалт, Score a tender on price and preference under the PPPFA)
Ажил материалын жагсаалт: Level the priced bills item by item

Яагаад: The price points formula measures every bid against the lowest one, so an arithmetic slip in the cheapest bid does not just misprice that bid, it moves the score of every other bidder. Levelling is the only step that makes the number going into the formula mean the same thing for everyone.

ОролтPriced billsBidder qualificationsҮр дүнComparable pricesTender queries
4

Score price by the formula and preference by the goals

Тендерийн удирдлага

Score price with the formula the regulations give: the lowest acceptable bid takes the full weighting, and every other bid loses the proportion by which it exceeds that lowest bid. Then add the preference points, goal by goal, against the proof each bidder submitted, and total the two.

Яагаад: The formula is what makes preference points decisive rather than decorative. A bid five per cent above the lowest gives up only a small part of its price points, so full preference points can and often do outweigh that gap, and a committee that quietly awards on price alone has ignored the Act. Writing the arithmetic down per bidder is what makes the award defensible.

ОролтLevelled pricesGoal claimsҮр дүнPoints per bidderRanking
5

Take the recommendation through the approval route

Зөвшөөрлийн маршрутууд

Send the evaluation report and the points table through the delegation of authority the organ of state works to, so the adjudication decision and the person who took it are both on the record with a date.

Дэлгэцийн зураг, 5-р алхам: Take the recommendation through the approval route (Зөвшөөрлийн маршрутууд, Score a tender on price and preference under the PPPFA)
Зөвшөөрлийн маршрутууд: Take the recommendation through the approval route

Яагаад: A tender award is reviewable, and the first thing a review asks is who decided and on what. An approval trail that shows the points table the decision was taken on, unchanged, answers that in one page. Note also that the Public Procurement Act 28 of 2024 has been passed and is being brought into operation in stages, so record which regime the tender was advertised under.

ОролтPoints tableEvaluation reportҮр дүнAward decisionApproval trail
6

Turn the award into a contract with its data filled in

Гэрээ

Draw up the contract on the form the tender was advertised on and complete the contract data: the accepted priced document, the dates, the securities, the penalty, and the goals the bidder committed to that now become contractual obligations.

Дэлгэцийн зураг, 6-р алхам: Turn the award into a contract with its data filled in (Гэрээ, Score a tender on price and preference under the PPPFA)
Гэрээ: Turn the award into a contract with its data filled in

Яагаад: A goal that earned preference points and was never written into the contract is a promise nobody can enforce. Carrying the commitments across at signature is what makes the preference part of the score mean something on site rather than only on the scoresheet.

ОролтAward decisionAccepted billҮр дүнSigned contractContract data
7

Notify every bidder and close the tender file

Харилцаа холбоо

Write to the successful and the unsuccessful bidders, publish the award as the organ of state is required to, and close the file with the advertisement, the bids, the responsiveness check, the points table and the approval in it.

Дэлгэцийн зураг, 7-р алхам: Notify every bidder and close the tender file (Харилцаа холбоо, Score a tender on price and preference under the PPPFA)
Харилцаа холбоо: Notify every bidder and close the tender file

Яагаад: An unsuccessful bidder is entitled to know it lost and to ask why, and the answer is the points table. A tender file assembled after a challenge arrives always looks assembled after a challenge arrives; one closed on the day of the award is simply the record.

ОролтFinal rankingBidder listҮр дүнNotification lettersTender file
Модулиуд

Энэ тоглолтын модулиуд

Платформын 190 модулиас 6

The market this case is written for

Өмнөд Африк

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • JBCC 6.2
  • SANS 1921

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Тендер ба худалдан авалт дахь бусад