Meça um bill of quantities pelo ASMM 6

Fixe os preambles antes de medir, retire as dimensões dos desenhos, mantenha as quantidades líquidas e o desperdício na taxa, escreva os itens nas secções de especialidade que a norma fixa, mantenha as somas provisional e prime cost fora das taxas e valide o mapa antes de ir a concurso.

6 etapas20 minConsultoria de custos / QSEmpreiteiro geralGabinete de gestão de projetos / obras

Como funciona, passo a passo

6 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Settle the preambles before you take a dimension

Base da estimativa

Write the basis down first: that the bill is measured to the Australian Standard Method of Measurement of Building Works, sixth edition, which departures from it the job needs and why, what the rates are deemed to include, and what the bill does not cover. Record the drawing revisions the measurement is being taken from in the same place.

Por quê: The preambles are the part of the bill that is read only when there is a dispute, which is exactly why they have to be written when there is not. A tenderer who priced a rate on the assumption it excluded something the measurer assumed it included has not made an arithmetic mistake, and no amount of levelling afterwards recovers the difference.

EntradaMethod of measurement adoptedScope and exclusionsResultadoPreambles recordedWhat each rate is deemed to include
2

Take the dimensions off the drawings

Medições PDF

Open the drawings on the measurement canvas, calibrate the scale against a figured dimension rather than a printed scale bar, and take the areas in square metres, the lengths in metres and the counts each trade section needs. Every measurement keeps the sheet number and the revision it came off.

Por quê: A drawing is reissued on every live job, and the only measurements that survive a reissue are the ones you can find again. A quantity with no sheet behind it cannot be rechecked, so it has to be re-taken from scratch, and the second take-off never agrees with the first.

EntradaTender drawingsPreambles recordedResultadoDimensions taken offEvery measurement tied to a sheet
3

Keep the quantity net and the waste in the rate

Fatores de desperdício

Set the waste allowance for each material on its own register, so the bill quantity stays the net quantity of finished work the standard asks for and the cutting, laps, returns and breakage are priced where they belong. Reinforcement laps, tile cutting and plasterboard offcuts all live here rather than in the measured area.

Por quê: A quantity quietly grossed up for waste reads as a measurement and behaves as a rate, and nobody downstream can tell which it is. It also breaks the one thing a bill is for, because the next valuation measures the finished work on site and finds less of it than the bill said there would be.

EntradaDimensions taken offHow the trade is actually builtResultadoNet quantities of finished workWaste carried in the rate
4

Write each item the way the standard describes it

Planilha Orçamentária

Write each item with the description, the unit and the quantity the standard calls for, and group the items into the trade sections it organises the work by. Price them from the cost database or from your own rates. An Australian bill is measured by trade, and the elemental view of the same money is produced alongside it rather than instead of it.

Por quê: The description is the contract between the measurer and the estimator. An item written loosely gets priced six different ways by six tenderers, and the levelling that follows is an argument about your own words rather than about their offers.

EntradaNet quantities of finished workUnit ratesResultadoPriced bill of quantitiesItems in their trade sections
5

Hold the provisional and prime cost sums out of the rates

Provisões e contingências

Put each provisional sum and each prime cost sum on the register as its own entry, with the amount, what it is meant to cover and the allowance for the builder's profit and attendance on it. Draw against them as the work is instructed and watch what is left.

Por quê: A sum folded into a rate is a sum nobody can release and nobody can adjust, so the contract sum adjustment at the end becomes archaeology. Held openly, both sides read the same figure and the final account is arithmetic.

EntradaPriced bill of quantitiesWork not yet designedResultadoProvisional sums heldPrime cost sums on the register
6

Validate the bill before it goes to tender

Validação

Run the bill through validation for the item left at zero, the unit that contradicts its own description, the quantity that no longer agrees with the take-off it came from and the trade section that was never measured at all. Fix what it reports and run it again until it comes back clean.

Por quê: One bill goes to every tenderer at once, so one mistake is priced by all of them. Catching it while the document is still yours costs an hour; catching it after the tenders are in costs a re-tender or a variation on day one.

EntradaPriced bill of quantitiesSums on the registerResultadoValidation reportBill cleared for tender
Módulos

Módulos deste playbook

6 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Austrália

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • AS 4000
  • Security of Payment Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Orçamentação e custos