案例 / 估算与成本
估算与成本

按ASMM 6计算工程量清单

在计算前先厘清preambles,从图纸取得尺寸,保持工程量净值、损耗计入单价,把条目写入标准规定的专业分部,把provisional和prime cost金额置于单价之外,并在投标前验证工程量清单。

6 个步骤20 分钟造价咨询 / 工料测量顾问总承包商项目/施工管理公司

运作方式,逐步说明

贯穿平台的 6 个步骤 - 每一步做什么,以及为什么重要。

1

Settle the preambles before you take a dimension

估算依据

Write the basis down first: that the bill is measured to the Australian Standard Method of Measurement of Building Works, sixth edition, which departures from it the job needs and why, what the rates are deemed to include, and what the bill does not cover. Record the drawing revisions the measurement is being taken from in the same place.

原因: The preambles are the part of the bill that is read only when there is a dispute, which is exactly why they have to be written when there is not. A tenderer who priced a rate on the assumption it excluded something the measurer assumed it included has not made an arithmetic mistake, and no amount of levelling afterwards recovers the difference.

输入Method of measurement adoptedScope and exclusions成果Preambles recordedWhat each rate is deemed to include
2

Take the dimensions off the drawings

PDF 测量

Open the drawings on the measurement canvas, calibrate the scale against a figured dimension rather than a printed scale bar, and take the areas in square metres, the lengths in metres and the counts each trade section needs. Every measurement keeps the sheet number and the revision it came off.

原因: A drawing is reissued on every live job, and the only measurements that survive a reissue are the ones you can find again. A quantity with no sheet behind it cannot be rechecked, so it has to be re-taken from scratch, and the second take-off never agrees with the first.

输入Tender drawingsPreambles recorded成果Dimensions taken offEvery measurement tied to a sheet
3

Keep the quantity net and the waste in the rate

损耗系数

Set the waste allowance for each material on its own register, so the bill quantity stays the net quantity of finished work the standard asks for and the cutting, laps, returns and breakage are priced where they belong. Reinforcement laps, tile cutting and plasterboard offcuts all live here rather than in the measured area.

原因: A quantity quietly grossed up for waste reads as a measurement and behaves as a rate, and nobody downstream can tell which it is. It also breaks the one thing a bill is for, because the next valuation measures the finished work on site and finds less of it than the bill said there would be.

输入Dimensions taken offHow the trade is actually built成果Net quantities of finished workWaste carried in the rate
4

Write each item the way the standard describes it

工程量清单

Write each item with the description, the unit and the quantity the standard calls for, and group the items into the trade sections it organises the work by. Price them from the cost database or from your own rates. An Australian bill is measured by trade, and the elemental view of the same money is produced alongside it rather than instead of it.

原因: The description is the contract between the measurer and the estimator. An item written loosely gets priced six different ways by six tenderers, and the levelling that follows is an argument about your own words rather than about their offers.

输入Net quantities of finished workUnit rates成果Priced bill of quantitiesItems in their trade sections
5

Hold the provisional and prime cost sums out of the rates

暂列金额与应急费

Put each provisional sum and each prime cost sum on the register as its own entry, with the amount, what it is meant to cover and the allowance for the builder's profit and attendance on it. Draw against them as the work is instructed and watch what is left.

原因: A sum folded into a rate is a sum nobody can release and nobody can adjust, so the contract sum adjustment at the end becomes archaeology. Held openly, both sides read the same figure and the final account is arithmetic.

输入Priced bill of quantitiesWork not yet designed成果Provisional sums heldPrime cost sums on the register
6

Validate the bill before it goes to tender

校验

Run the bill through validation for the item left at zero, the unit that contradicts its own description, the quantity that no longer agrees with the take-off it came from and the trade section that was never measured at all. Fix what it reports and run it again until it comes back clean.

原因: One bill goes to every tenderer at once, so one mistake is priced by all of them. Catching it while the document is still yours costs an hour; catching it after the tenders are in costs a re-tender or a variation on day one.

输入Priced bill of quantitiesSums on the register成果Validation reportBill cleared for tender
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

澳大利亚

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 估算与成本 案例

估算与成本

发出估算前进行核查

让已计价的清单通过核查规则,清除所有警告和错误,再导出一份可以直接交给客户的干净报告。

3 个步骤8 分钟打开
估算与成本

根据成本数据库进行估算

从真实的成本数据库中提取已计价项目,据此构建清单,把常用的组合做法打包成组合定额,提交投标数字前先做校核。

4 个步骤12 分钟打开
估算与成本

根据成本风险设定应急费

把单点估算转化为区间估算,对真正存在不确定性的项目运行蒙特卡洛模拟,读取P50到P90的分布区间,设定一个可以逐项说清楚的应急费。

3 个步骤11 分钟打开