ASMM 6에 따라 내역서 산출하기

측정하기 전에 preambles를 정리하고, 도면에서 치수를 뽑고, 수량은 순수치로 유지하고 손실은 단가에 포함하고, 규격이 정한 공종 구분에 항목을 작성하고, provisional과 prime cost sums는 단가에서 제외하고, 내역서가 입찰에 나가기 전에 검증한다.

6단계20 분원가 컨설팅 / 적산 업체종합건설사PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Settle the preambles before you take a dimension

견적 근거

Write the basis down first: that the bill is measured to the Australian Standard Method of Measurement of Building Works, sixth edition, which departures from it the job needs and why, what the rates are deemed to include, and what the bill does not cover. Record the drawing revisions the measurement is being taken from in the same place.

이유: The preambles are the part of the bill that is read only when there is a dispute, which is exactly why they have to be written when there is not. A tenderer who priced a rate on the assumption it excluded something the measurer assumed it included has not made an arithmetic mistake, and no amount of levelling afterwards recovers the difference.

입력Method of measurement adoptedScope and exclusions결과Preambles recordedWhat each rate is deemed to include
2

Take the dimensions off the drawings

PDF 측정

Open the drawings on the measurement canvas, calibrate the scale against a figured dimension rather than a printed scale bar, and take the areas in square metres, the lengths in metres and the counts each trade section needs. Every measurement keeps the sheet number and the revision it came off.

이유: A drawing is reissued on every live job, and the only measurements that survive a reissue are the ones you can find again. A quantity with no sheet behind it cannot be rechecked, so it has to be re-taken from scratch, and the second take-off never agrees with the first.

입력Tender drawingsPreambles recorded결과Dimensions taken offEvery measurement tied to a sheet
3

Keep the quantity net and the waste in the rate

할증률

Set the waste allowance for each material on its own register, so the bill quantity stays the net quantity of finished work the standard asks for and the cutting, laps, returns and breakage are priced where they belong. Reinforcement laps, tile cutting and plasterboard offcuts all live here rather than in the measured area.

이유: A quantity quietly grossed up for waste reads as a measurement and behaves as a rate, and nobody downstream can tell which it is. It also breaks the one thing a bill is for, because the next valuation measures the finished work on site and finds less of it than the bill said there would be.

입력Dimensions taken offHow the trade is actually built결과Net quantities of finished workWaste carried in the rate
4

Write each item the way the standard describes it

내역서

Write each item with the description, the unit and the quantity the standard calls for, and group the items into the trade sections it organises the work by. Price them from the cost database or from your own rates. An Australian bill is measured by trade, and the elemental view of the same money is produced alongside it rather than instead of it.

이유: The description is the contract between the measurer and the estimator. An item written loosely gets priced six different ways by six tenderers, and the levelling that follows is an argument about your own words rather than about their offers.

입력Net quantities of finished workUnit rates결과Priced bill of quantitiesItems in their trade sections
5

Hold the provisional and prime cost sums out of the rates

충당금 및 예비비

Put each provisional sum and each prime cost sum on the register as its own entry, with the amount, what it is meant to cover and the allowance for the builder's profit and attendance on it. Draw against them as the work is instructed and watch what is left.

이유: A sum folded into a rate is a sum nobody can release and nobody can adjust, so the contract sum adjustment at the end becomes archaeology. Held openly, both sides read the same figure and the final account is arithmetic.

입력Priced bill of quantitiesWork not yet designed결과Provisional sums heldPrime cost sums on the register
6

Validate the bill before it goes to tender

검증

Run the bill through validation for the item left at zero, the unit that contradicts its own description, the quantity that no longer agrees with the take-off it came from and the trade section that was never measured at all. Fix what it reports and run it again until it comes back clean.

이유: One bill goes to every tenderer at once, so one mistake is priced by all of them. Catching it while the document is still yours costs an hour; catching it after the tenders are in costs a re-tender or a variation on day one.

입력Priced bill of quantitiesSums on the register결과Validation reportBill cleared for tender
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6

The market this case is written for

오스트레일리아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

적산 및 원가 카테고리의 더 보기

적산 및 원가

발송 전 견적 점검

산출된 내역서를 검증 규칙에 통과시켜 모든 경고와 오류를 해결한 뒤, 발주자에게 바로 전달할 수 있는 깨끗한 보고서를 내보냅니다.

3단계8 분열기
적산 및 원가

원가 데이터베이스로 견적 산정하기

실제 원가 데이터베이스에서 가격 항목을 가져와 내역서를 작성하고, 반복되는 조합을 어셈블리로 묶은 뒤, 입찰 금액을 확정하기 전에 검토를 실행합니다.

4단계12 분열기
적산 및 원가

비용 리스크로 예비비 산정하기

단일 값 견적을 범위로 바꾸고, 실제로 불확실한 항목에 대해 몬테카를로 시뮬레이션을 실행하여 P50~P90 분포를 읽고, 항목별로 근거를 설명할 수 있는 예비비를 설…

3단계11 분열기