Run a concrete pour from request to record

Run the pour card loop end to end: raise the request, clear the pre-pour hold point, release and pour with the delivery tickets and cube samples, then record the test results and the as-built against the element.

4 pași11 minAntreprenor generalSubantreprenor specializatManager de proiect / de construcție

Cum funcționează, pas cu pas

4 pași în cadrul platformei - ce faceți la fiecare și de ce contează.

1

Raise the pour request

Formulare și liste de verificare

Raise the pour request with the element, the location, the specified mix and the volume, giving enough notice for the inspection and the concrete order to line up.

De ce: A pour called at short notice is a pour that skips checks. Requesting it properly gives the inspection its window and the batching plant its lead time, so nothing is rushed on the day.

IntrareElement to pourSpecified mixRezultatPour request
2

Clear the pre-pour hold point

Inspecții

Inspect against the checklist before the pour: reinforcement size and spacing, cover, ties, formwork line and cleanliness, and any cast-in items in the right place.

De ce: This is the last moment the steel and the formwork are visible. A hold point cleared here catches the error that would otherwise be entombed and only found when the cover meter comes out.

IntrarePour requestInspection checklistRezultatHold point cleared
3

Release and pour

Construction Control

Release the hold point and pour, logging each delivery ticket, the mix and slump on arrival, and taking the cube samples for testing as the concrete goes in.

De ce: The tickets and samples captured during the pour are the proof the right concrete went in. Reconstructed afterwards they are worthless, so they have to be taken as it happens.

IntrareCleared hold pointDelivery ticketsRezultatPour completedCube samples taken
4

Record tests and as-built

Construction Control

Record the cube test results at seven and twenty-eight days against the pour, and close the as-built record for the element, so the concrete has a verified strength on file.

De ce: A pour is not finished when the concrete sets, it is finished when it is proven to strength on record. That record is what the structural sign-off and the eventual handover depend on.

IntrareCube samplesTest resultsRezultatAs-built pour record