إعداد العقد على AS 4000 أو AS 2124

اختر الشروط العامة ووثّق ملحقا Annexure مكتملا، سوّ الضمان securities وتخفيضها، سمِّ Superintendent وما يمكنه قراره، حمّل التواريخ التي تعتمد عليها liquidated damages، وزّع المخاطر كما يحددها الملحق، ونفّذ الشيء الذي سيعمل به الجميع.

6 خطوة16 دقيقةمقاول عاممطوّر / عميلمكتب إدارة المشاريع / الإنشاءاستشارات التكاليف / قياس الكميات

كيف يعمل، خطوة بخطوة

6 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Record which form it is and what the Annexure says

العقود

Create the contract record naming the form, AS 4000-1997 or AS 2124-1992, the contract sum and whether it is lump sum or schedule of rates, and enter the Annexure values that the rest of the job runs on. Record the principal's amendments as amendments rather than folding them into the printed clause, so anyone reading later can see what was changed from the standard.

لقطة شاشة، الخطوة 1: Record which form it is and what the Annexure says (العقود, إعداد العقد على AS 4000 أو AS 2124)
العقود: Record which form it is and what the Annexure says

لماذا: The commonest cause of an argument on an Australian Standard contract is two people reading two different documents, one the printed form and one the amended version. A contract record that names the form, carries the Annexure and lists the departures is what makes a clause reference a fact rather than an opinion.

المدخلاتAward decisionPrincipal's amendmentsالمخرجاتGeneral conditions chosenAnnexure recorded
2

Settle the security and the day it reduces

العقود

Record what security the contract takes, cash retention held from each progress payment or unconditional undertakings from a bank, the percentage and the limit, and the two events that release it: the reduction at practical completion and the release at the end of the defects liability period. Note who holds the guarantees and where.

لقطة شاشة، الخطوة 2: Settle the security and the day it reduces (العقود, إعداد العقد على AS 4000 أو AS 2124)
العقود: Settle the security and the day it reduces

لماذا: Security is the cheapest money on the job to lose track of, because nobody chases it until long after the site has closed and the people who knew the arrangement have moved on. A reduction that should have happened at practical completion and did not is working capital sitting in somebody else's account for a year.

المدخلاتAnnexure recordedBank guarantees offeredالمخرجاتSecurity terms on recordWhen each half is released
3

Name the Superintendent and map what they may decide

مسارات الاعتماد

Name the Superintendent and the Superintendent's Representative, and build the approval route that says which decisions they make alone, which need the principal, and what value threshold moves a direction from one to the other. Certificates, directions to vary and extensions of time all sit on that map.

لقطة شاشة، الخطوة 3: Name the Superintendent and map what they may decide (مسارات الاعتماد, إعداد العقد على AS 4000 أو AS 2124)
مسارات الاعتماد: Name the Superintendent and map what they may decide

لماذا: Both forms require the Superintendent to act honestly and, for the functions where they are certifying rather than acting as the principal's agent, reasonably and independently. A route that records who decided what and on what authority protects the certifier as much as the contractor, because a direction given by someone without the authority to give it is an argument waiting for the final account.

المدخلاتGeneral conditions chosenDelegations from the principalالمخرجاتSuperintendent namedWhat each decision needs
4

Load the dates the damages hang on

المواعيد النهائية

Put the date for practical completion, the separable portions if the contract has them, the liquidated damages rate and any limit on it, and the length of the defects liability period under watch, together with the time the Annexure allows for a claim to be made. Let each one warn before it lands.

لماذا: Liquidated damages run per day from a date, and the defects liability period ends on a date, and both are worked out from Annexure entries that nobody rereads once the job starts. A claim window that closed while the site was busy is an entitlement gone, and no notice is served on you when it happens.

المدخلاتAnnexure recordedConstruction programmeالمخرجاتContract dates under watchLiquidated damages rate on record
5

Write down who carries what

سجل المخاطر

Take the allocations out of the conditions and the Annexure and put them on the risk register in words a site manager can act on: latent conditions and what counts as one, who effects the works insurance and the public liability cover and for how much, the excepted risks, and where the contract has been amended to move a risk from the standard position.

لقطة شاشة، الخطوة 5: Write down who carries what (سجل المخاطر, إعداد العقد على AS 4000 أو AS 2124)
سجل المخاطر: Write down who carries what

لماذا: Latent conditions are the clause most often amended away in Australian practice, and a contractor who assumed the standard position and priced accordingly finds out the day the excavator hits rock. A risk that lives only in clause 25 of a document in a drawer is a risk nobody manages.

المدخلاتAnnexure recordedSite information providedالمخرجاتRisks allocated on the registerInsurances and who effects them
6

Execute it and make it the version everyone reads

التوقيعات الإلكترونية

Send the complete set for execution, conditions, Annexure, amendments, drawings and specification listed as contract documents in the order of precedence the contract sets, and keep the executed version as the one the site, the estimator and the accounts all work from.

لماذا: Work starting before execution is normal in Australia and it is also how a job runs for six months on a draft nobody signed. The order of precedence matters as much as the signature, because it decides which document wins when the drawing and the specification disagree, and they always disagree eventually.

المدخلاتFinal contract documentsAuthorised signatoriesالمخرجاتExecuted contractOne version everyone reads
الوحدات

وحدات هذا الدليل

5 / 190 من وحدات المنصة

The market this case is written for

أستراليا

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

المزيد في التجاري والعقود

التجاري والعقود

تحويل تغيير إلى أمر تغيير مدفوع

التقط تغيير النطاق وهو طازج، وسعّره كأمر تغيير تعاقدي على أسعارك المتفق عليها، وحاسب عليه في…

3 خطوة11 دقيقةفتح
التجاري والعقود

إدارة حزمة مقاول باطن

أرسِ حزمة تخصص على مقاول باطن، وضعها في عقد باطن بجدول قيم ومحتجزات، ثم اسددها مستخلصاً بعد…

3 خطوة11 دقيقةفتح
التجاري والعقود

مطالبة الدفع ومطابقتها

قيّم العمل المنفَّذ خلال هذه الفترة مقابل العقد، وقدّم المطالبة مدعومة بأدلّتها، وطابِق ما ا…

3 خطوة12 دقيقةفتح