Casos prácticos / Comercial y contratos
Comercial y contratos

Set the contract up on AS 4000 or AS 2124

Pick the general conditions and record the Annexure that fills them in, settle the security and its reduction, name the Superintendent and what they may decide, load the dates the liquidated damages hang on, allocate the risks the Annexure allocates and execute the thing everyone will be working from.

6 pasos16 minContratista generalDesarrollador / clienteGestora de proyectos / construcciónConsultoría de costos / QS

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Record which form it is and what the Annexure says

Contratos

Create the contract record naming the form, AS 4000-1997 or AS 2124-1992, the contract sum and whether it is lump sum or schedule of rates, and enter the Annexure values that the rest of the job runs on. Record the principal's amendments as amendments rather than folding them into the printed clause, so anyone reading later can see what was changed from the standard.

Por que: The commonest cause of an argument on an Australian Standard contract is two people reading two different documents, one the printed form and one the amended version. A contract record that names the form, carries the Annexure and lists the departures is what makes a clause reference a fact rather than an opinion.

EntradaAward decisionPrincipal's amendmentsResultadoGeneral conditions chosenAnnexure recorded
2

Settle the security and the day it reduces

Contratos

Record what security the contract takes, cash retention held from each progress payment or unconditional undertakings from a bank, the percentage and the limit, and the two events that release it: the reduction at practical completion and the release at the end of the defects liability period. Note who holds the guarantees and where.

Por que: Security is the cheapest money on the job to lose track of, because nobody chases it until long after the site has closed and the people who knew the arrangement have moved on. A reduction that should have happened at practical completion and did not is working capital sitting in somebody else's account for a year.

EntradaAnnexure recordedBank guarantees offeredResultadoSecurity terms on recordWhen each half is released
3

Name the Superintendent and map what they may decide

Rutas de aprobación

Name the Superintendent and the Superintendent's Representative, and build the approval route that says which decisions they make alone, which need the principal, and what value threshold moves a direction from one to the other. Certificates, directions to vary and extensions of time all sit on that map.

Por que: Both forms require the Superintendent to act honestly and, for the functions where they are certifying rather than acting as the principal's agent, reasonably and independently. A route that records who decided what and on what authority protects the certifier as much as the contractor, because a direction given by someone without the authority to give it is an argument waiting for the final account.

EntradaGeneral conditions chosenDelegations from the principalResultadoSuperintendent namedWhat each decision needs
4

Load the dates the damages hang on

Plazos

Put the date for practical completion, the separable portions if the contract has them, the liquidated damages rate and any limit on it, and the length of the defects liability period under watch, together with the time the Annexure allows for a claim to be made. Let each one warn before it lands.

Por que: Liquidated damages run per day from a date, and the defects liability period ends on a date, and both are worked out from Annexure entries that nobody rereads once the job starts. A claim window that closed while the site was busy is an entitlement gone, and no notice is served on you when it happens.

EntradaAnnexure recordedConstruction programmeResultadoContract dates under watchLiquidated damages rate on record
5

Write down who carries what

Registro de riesgos

Take the allocations out of the conditions and the Annexure and put them on the risk register in words a site manager can act on: latent conditions and what counts as one, who effects the works insurance and the public liability cover and for how much, the excepted risks, and where the contract has been amended to move a risk from the standard position.

Por que: Latent conditions are the clause most often amended away in Australian practice, and a contractor who assumed the standard position and priced accordingly finds out the day the excavator hits rock. A risk that lives only in clause 25 of a document in a drawer is a risk nobody manages.

EntradaAnnexure recordedSite information providedResultadoRisks allocated on the registerInsurances and who effects them
6

Execute it and make it the version everyone reads

Firmas Electrónicas

Send the complete set for execution, conditions, Annexure, amendments, drawings and specification listed as contract documents in the order of precedence the contract sets, and keep the executed version as the one the site, the estimator and the accounts all work from.

Por que: Work starting before execution is normal in Australia and it is also how a job runs for six months on a draft nobody signed. The order of precedence matters as much as the signature, because it decides which document wins when the drawing and the specification disagree, and they always disagree eventually.

EntradaFinal contract documentsAuthorised signatoriesResultadoExecuted contractOne version everyone reads
Módulos

Módulos de este playbook

5 / 190 módulos de la plataforma

The market this case is written for

Australia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Más en Comercial y contratos

Comercial y contratos

Estimación de pago y conciliación

Valúa el trabajo ejecutado en el periodo contra el contrato, presenta la estimación con la e…

3 pasos12 minAbrir