Kasus / Komersial dan kontrak
Komersial dan kontrak

Menyusun kontrak berdasarkan AS 4000 atau AS 2124

Pilih general conditions dan catat Annexure yang melengkapinya, tetapkan jaminan dan pengurangannya, tunjuk Superintendent dan apa yang boleh diputuskannya, muat tanggal yang menjadi gantungan liquidated damages, alokasikan risiko sesuai yang dialokasikan Annexure, dan tandatangani dokumen yang akan menjadi acuan semua orang.

6 langkah16 mntKontraktor umumPengembang / klienBiro manajemen proyek / konstruksiKonsultansi biaya / QS

Cara kerjanya, langkah demi langkah

6 langkah di seluruh platform - apa yang Anda lakukan di setiap langkah dan mengapa itu penting.

1

Record which form it is and what the Annexure says

Kontrak

Create the contract record naming the form, AS 4000-1997 or AS 2124-1992, the contract sum and whether it is lump sum or schedule of rates, and enter the Annexure values that the rest of the job runs on. Record the principal's amendments as amendments rather than folding them into the printed clause, so anyone reading later can see what was changed from the standard.

Tangkapan layar, langkah 1: Record which form it is and what the Annexure says (Kontrak, Menyusun kontrak berdasarkan AS 4000 atau AS 2124)
Kontrak: Record which form it is and what the Annexure says

Mengapa: The commonest cause of an argument on an Australian Standard contract is two people reading two different documents, one the printed form and one the amended version. A contract record that names the form, carries the Annexure and lists the departures is what makes a clause reference a fact rather than an opinion.

MasukanAward decisionPrincipal's amendmentsHasilGeneral conditions chosenAnnexure recorded
2

Settle the security and the day it reduces

Kontrak

Record what security the contract takes, cash retention held from each progress payment or unconditional undertakings from a bank, the percentage and the limit, and the two events that release it: the reduction at practical completion and the release at the end of the defects liability period. Note who holds the guarantees and where.

Tangkapan layar, langkah 2: Settle the security and the day it reduces (Kontrak, Menyusun kontrak berdasarkan AS 4000 atau AS 2124)
Kontrak: Settle the security and the day it reduces

Mengapa: Security is the cheapest money on the job to lose track of, because nobody chases it until long after the site has closed and the people who knew the arrangement have moved on. A reduction that should have happened at practical completion and did not is working capital sitting in somebody else's account for a year.

MasukanAnnexure recordedBank guarantees offeredHasilSecurity terms on recordWhen each half is released
3

Name the Superintendent and map what they may decide

Rute persetujuan

Name the Superintendent and the Superintendent's Representative, and build the approval route that says which decisions they make alone, which need the principal, and what value threshold moves a direction from one to the other. Certificates, directions to vary and extensions of time all sit on that map.

Tangkapan layar, langkah 3: Name the Superintendent and map what they may decide (Rute persetujuan, Menyusun kontrak berdasarkan AS 4000 atau AS 2124)
Rute persetujuan: Name the Superintendent and map what they may decide

Mengapa: Both forms require the Superintendent to act honestly and, for the functions where they are certifying rather than acting as the principal's agent, reasonably and independently. A route that records who decided what and on what authority protects the certifier as much as the contractor, because a direction given by someone without the authority to give it is an argument waiting for the final account.

MasukanGeneral conditions chosenDelegations from the principalHasilSuperintendent namedWhat each decision needs
4

Load the dates the damages hang on

Tenggat Waktu

Put the date for practical completion, the separable portions if the contract has them, the liquidated damages rate and any limit on it, and the length of the defects liability period under watch, together with the time the Annexure allows for a claim to be made. Let each one warn before it lands.

Mengapa: Liquidated damages run per day from a date, and the defects liability period ends on a date, and both are worked out from Annexure entries that nobody rereads once the job starts. A claim window that closed while the site was busy is an entitlement gone, and no notice is served on you when it happens.

MasukanAnnexure recordedConstruction programmeHasilContract dates under watchLiquidated damages rate on record
5

Write down who carries what

Daftar Risiko

Take the allocations out of the conditions and the Annexure and put them on the risk register in words a site manager can act on: latent conditions and what counts as one, who effects the works insurance and the public liability cover and for how much, the excepted risks, and where the contract has been amended to move a risk from the standard position.

Tangkapan layar, langkah 5: Write down who carries what (Daftar Risiko, Menyusun kontrak berdasarkan AS 4000 atau AS 2124)
Daftar Risiko: Write down who carries what

Mengapa: Latent conditions are the clause most often amended away in Australian practice, and a contractor who assumed the standard position and priced accordingly finds out the day the excavator hits rock. A risk that lives only in clause 25 of a document in a drawer is a risk nobody manages.

MasukanAnnexure recordedSite information providedHasilRisks allocated on the registerInsurances and who effects them
6

Execute it and make it the version everyone reads

Tanda Tangan Elektronik

Send the complete set for execution, conditions, Annexure, amendments, drawings and specification listed as contract documents in the order of precedence the contract sets, and keep the executed version as the one the site, the estimator and the accounts all work from.

Mengapa: Work starting before execution is normal in Australia and it is also how a job runs for six months on a draft nobody signed. The order of precedence matters as much as the signature, because it decides which document wins when the drawing and the specification disagree, and they always disagree eventually.

MasukanFinal contract documentsAuthorised signatoriesHasilExecuted contractOne version everyone reads
Modul

Modul dalam playbook ini

5 / 190 modul platform

The market this case is written for

Australia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.