Keep the e-epitesi naplo as the legal record it is

Have the naplo opened before anyone goes on site, write the day while it is happening, hang each contractor's alnaplo off the fonaplo, record measurement and concealed work as they occur, and close the record so it can be read years later.

7 steps13 minGeneral contractorSpecialist subcontractorProject / construction management firm

How it works, step by step

7 steps across the platform - what you do at each one, and why it matters.

1

Have the naplo open before the site is handed over

Site Mobilisation

Before mobilisation, confirm that the epitteto has put the naplo and the first fonaplo into readiness, that the contractor has accepted the site handover through it, and that the handover is entered as an event. Record the same milestone on the project so the site does not start on somebody's assurance that it is done.

Why: The Epkiv. lets the work begin only once that entry exists, so a crew that starts a week early is not ahead of programme, it is carrying out construction work outside the record. Building supervision treats that as a defect of the works and not as a filing lapse, and the contractor is the party standing in front of it.

InPermit or notification recordEpitteto and contractorOutNaplo open and acceptedSite handover entered
2

Write the day while the day is happening

Daily Diary

Record what the site actually did: which crews and which subcontractors were there, what each area got done, the weather and ground conditions, deliveries, visitors, and anything that stopped the work, with the hour it started and who was told.

Daily Diary screen in OpenConstructionERP: Write the day while the day is happening (Keep the e-epitesi naplo as the legal record it is)
Daily Diary: Write the day while the day is happening

Why: The naplo is where a Hungarian dispute is decided, because it is the one record both sides signed up to in advance. An entry made on the day is evidence; the same words typed in November are a claim about what somebody remembers, and the other side gets to say so. The cost of the discipline is ten minutes a day and the cost of skipping it lands all at once.

InCrews and plant on siteWeather and conditionsOutDiary entry for the dayEvents logged with their hour
3

Hang every contractor off the fonaplo

Subcontractor Directory

Keep the register of who is working under whom in step with the naplo: each contractor in the chain keeps its own alnaplo under the fonaplo above it, and a firm that turns up on site without one is a firm working outside the record.

Subcontractor Directory screen in OpenConstructionERP: Hang every contractor off the fonaplo (Keep the e-epitesi naplo as the legal record it is)
Subcontractor Directory: Hang every contractor off the fonaplo

Why: The chain of alnaplok is how an inspection reads a site, and it is also how a payment chain is reconstructed when somebody in the middle stops paying. A subcontractor with no alnaplo has no record of its own work on the job it is owed for, which is a much larger problem for them than the administrative one it looks like on the day.

InSubcontractors on the packageOpen fonaploOutContractor chain on recordAlnaplo open per contractor
4

Record the measurement where the money will look for it

Progress

Where the contract settles on measured quantities, record the measurement tetel by tetel as the work is done, and keep it agreed with the muszaki ellenor rather than presented to them at the end of the month. The felmeresi naplo is the sub-log this belongs in, and the valuation should be readable straight out of it.

Progress screen in OpenConstructionERP: Record the measurement where the money will look for it (Keep the e-epitesi naplo as the legal record it is)
Progress: Record the measurement where the money will look for it

Why: Measurement agreed while the work is visible takes minutes and measurement argued after it is buried takes a meeting, sometimes a survey, and occasionally a court. It is also the difference between a valuation the certifier can approve line by line and one they can only accept or refuse whole.

InWork executed this periodTetel and contract quantityOutMeasured quantities per tetelBasis for the valuation
5

Inspect the concealed work before it is concealed

Inspections

Before reinforcement is poured over, insulation is boarded, or a service run is buried, call the inspection, photograph the work as built, record the result and only then release the cover. Keep the notice, the inspection and the photographs on the same record.

Inspections screen in OpenConstructionERP: Inspect the concealed work before it is concealed (Keep the e-epitesi naplo as the legal record it is)
Inspections: Inspect the concealed work before it is concealed

Why: The Epkiv. puts the checking of eltakart szerkezetek on the felelos muszaki vezeto, and once the work is covered the record is the only thing anybody can look at. A dispute about concealed work is decided on the entry and the photograph, and opening it up again to find out is a cost somebody pays whether or not they were wrong.

InStructure about to be coveredNotice to the muszaki ellenorOutInspection record with photosRelease to cover
6

Keep the muszaki ellenor inside the record

Site Supervision

Route what the supervising engineer has to see through the naplo rather than by message: the inspections, the measurements, the instructions they give and the written notice that a performance is complete. Record the date the notice went in.

Site Supervision screen in OpenConstructionERP: Keep the muszaki ellenor inside the record (Keep the e-epitesi naplo as the legal record it is)
Site Supervision: Keep the muszaki ellenor inside the record

Why: The Epkiv. makes a muszaki ellenor mandatory on several kinds of work, public procurement among them, and gives them at most fifteen working days from the contractor's written notice of completion to issue the teljesitesigazolas or refuse it with reasons. That clock only exists if the notice has a date, and the naplo is where the date is beyond argument.

InEntries awaiting the ellenorMuszaki ellenor appointmentOutCountersigned entriesNotice of completion sent
7

Close the record so it can be read later

Documents

At the end of the works, pull the diary days, the inspections, the measurements and the photographs into one pack on the project, indexed by date, and hand it to close-out with the rest of the completion documentation.

Documents screen in OpenConstructionERP: Close the record so it can be read later (Keep the e-epitesi naplo as the legal record it is)
Documents: Close the record so it can be read later

Why: The people who will need this record are not the people who wrote it. A defect claim arrives years after the site manager has moved on, and the question is always the same: what was done here, when, and who checked it. A pack assembled at the end while everyone is still on the job answers that; a pack assembled from a defect notice does not.

InClosed diary daysInspections and measurementsOutSite record packRecord handed to close-out
Modules

Modules in this playbook

7 / 190 platform modules

The market this case is written for

Hungary

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Kbt.
  • TSZSZ

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

More in Site & field

Site & field

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 steps9 minOpen
Site & field

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 steps9 minOpen