把电子施工日志当成它本来就是的法定记录

在任何人进场之前就把 e-építési napló 开好,当天的事当天写,把每家承包商的 alnapló 挂在 főnapló 下面,计量和隐蔽工程随做随记,并把记录收尾成多年以后还能读懂的样子。

7 个步骤13 分钟总承包商专业分包商项目/施工管理公司

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Have the naplo open before the site is handed over

现场动员

Before mobilisation, confirm that the epitteto has put the naplo and the first fonaplo into readiness, that the contractor has accepted the site handover through it, and that the handover is entered as an event. Record the same milestone on the project so the site does not start on somebody's assurance that it is done.

原因: The Epkiv. lets the work begin only once that entry exists, so a crew that starts a week early is not ahead of programme, it is carrying out construction work outside the record. Building supervision treats that as a defect of the works and not as a filing lapse, and the contractor is the party standing in front of it.

输入Permit or notification recordEpitteto and contractor成果Naplo open and acceptedSite handover entered
2

Write the day while the day is happening

施工日志

Record what the site actually did: which crews and which subcontractors were there, what each area got done, the weather and ground conditions, deliveries, visitors, and anything that stopped the work, with the hour it started and who was told.

原因: The naplo is where a Hungarian dispute is decided, because it is the one record both sides signed up to in advance. An entry made on the day is evidence; the same words typed in November are a claim about what somebody remembers, and the other side gets to say so. The cost of the discipline is ten minutes a day and the cost of skipping it lands all at once.

输入Crews and plant on siteWeather and conditions成果Diary entry for the dayEvents logged with their hour
3

Hang every contractor off the fonaplo

分包商目录

Keep the register of who is working under whom in step with the naplo: each contractor in the chain keeps its own alnaplo under the fonaplo above it, and a firm that turns up on site without one is a firm working outside the record.

原因: The chain of alnaplok is how an inspection reads a site, and it is also how a payment chain is reconstructed when somebody in the middle stops paying. A subcontractor with no alnaplo has no record of its own work on the job it is owed for, which is a much larger problem for them than the administrative one it looks like on the day.

输入Subcontractors on the packageOpen fonaplo成果Contractor chain on recordAlnaplo open per contractor
4

Record the measurement where the money will look for it

进度

Where the contract settles on measured quantities, record the measurement tetel by tetel as the work is done, and keep it agreed with the muszaki ellenor rather than presented to them at the end of the month. The felmeresi naplo is the sub-log this belongs in, and the valuation should be readable straight out of it.

原因: Measurement agreed while the work is visible takes minutes and measurement argued after it is buried takes a meeting, sometimes a survey, and occasionally a court. It is also the difference between a valuation the certifier can approve line by line and one they can only accept or refuse whole.

输入Work executed this periodTetel and contract quantity成果Measured quantities per tetelBasis for the valuation
5

Inspect the concealed work before it is concealed

检查

Before reinforcement is poured over, insulation is boarded, or a service run is buried, call the inspection, photograph the work as built, record the result and only then release the cover. Keep the notice, the inspection and the photographs on the same record.

原因: The Epkiv. puts the checking of eltakart szerkezetek on the felelos muszaki vezeto, and once the work is covered the record is the only thing anybody can look at. A dispute about concealed work is decided on the entry and the photograph, and opening it up again to find out is a cost somebody pays whether or not they were wrong.

输入Structure about to be coveredNotice to the muszaki ellenor成果Inspection record with photosRelease to cover
6

Keep the muszaki ellenor inside the record

现场监督

Route what the supervising engineer has to see through the naplo rather than by message: the inspections, the measurements, the instructions they give and the written notice that a performance is complete. Record the date the notice went in.

原因: The Epkiv. makes a muszaki ellenor mandatory on several kinds of work, public procurement among them, and gives them at most fifteen working days from the contractor's written notice of completion to issue the teljesitesigazolas or refuse it with reasons. That clock only exists if the notice has a date, and the naplo is where the date is beyond argument.

输入Entries awaiting the ellenorMuszaki ellenor appointment成果Countersigned entriesNotice of completion sent
7

Close the record so it can be read later

文档

At the end of the works, pull the diary days, the inspections, the measurements and the photographs into one pack on the project, indexed by date, and hand it to close-out with the rest of the completion documentation.

原因: The people who will need this record are not the people who wrote it. A defect claim arrives years after the site manager has moved on, and the question is always the same: what was done here, when, and who checked it. A pack assembled at the end while everyone is still on the job answers that; a pack assembled from a defect notice does not.

输入Closed diary daysInspections and measurements成果Site record packRecord handed to close-out
模块

此方案使用的模块

190 个平台模块中的 7

The market this case is written for

匈牙利

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Kbt.
  • TSZSZ

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 现场与作业 案例

现场与作业

收尾现场一天的工作

妥善收尾一天的工作:记录日志、登记人工和机械工时、上传照片并记录安全观察,让这一天以可依赖的证据形式留存下来。

4 个步骤9 分钟打开
现场与作业

答复一份RFI

将现场提出的问题转化为可跟踪的请求,推动到负责给出答复的一方,并将回复归档,使其成为项目记录的一部分。

3 个步骤9 分钟打开
现场与作业

记录计工计料与时间材料

把已下达指令的额外工作转化为能获得赔付的索赔:施工发生的同时记录人工、机械和材料,当天就取得签认,再依据合同提交。

3 个步骤9 分钟打开