Scenariji / Gradilište i teren
Gradilište i teren

Vodite e-építési napló kao pravni zapis koji jest

Neka napló bude otvoren prije nego itko stupi na gradilište, zapisujte dan dok traje, objesite alnapló svakog izvođača na fonapló, bilježite izmjeru i skrivene radove čim nastanu i zatvorite zapis tako da se može čitati i godinama poslije.

7 koraka13 minGlavni izvođačSpecijalizirani podizvođačUred za upravljanje projektima / gradnjom

Kako funkcionira, korak po korak

7 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Have the naplo open before the site is handed over

Mobilizacija gradilišta

Before mobilisation, confirm that the epitteto has put the naplo and the first fonaplo into readiness, that the contractor has accepted the site handover through it, and that the handover is entered as an event. Record the same milestone on the project so the site does not start on somebody's assurance that it is done.

Zašto: The Epkiv. lets the work begin only once that entry exists, so a crew that starts a week early is not ahead of programme, it is carrying out construction work outside the record. Building supervision treats that as a defect of the works and not as a filing lapse, and the contractor is the party standing in front of it.

UlazPermit or notification recordEpitteto and contractorRezultatNaplo open and acceptedSite handover entered
2

Write the day while the day is happening

Dnevnik gradilišta

Record what the site actually did: which crews and which subcontractors were there, what each area got done, the weather and ground conditions, deliveries, visitors, and anything that stopped the work, with the hour it started and who was told.

Zašto: The naplo is where a Hungarian dispute is decided, because it is the one record both sides signed up to in advance. An entry made on the day is evidence; the same words typed in November are a claim about what somebody remembers, and the other side gets to say so. The cost of the discipline is ten minutes a day and the cost of skipping it lands all at once.

UlazCrews and plant on siteWeather and conditionsRezultatDiary entry for the dayEvents logged with their hour
3

Hang every contractor off the fonaplo

Imenik podizvođača

Keep the register of who is working under whom in step with the naplo: each contractor in the chain keeps its own alnaplo under the fonaplo above it, and a firm that turns up on site without one is a firm working outside the record.

Zašto: The chain of alnaplok is how an inspection reads a site, and it is also how a payment chain is reconstructed when somebody in the middle stops paying. A subcontractor with no alnaplo has no record of its own work on the job it is owed for, which is a much larger problem for them than the administrative one it looks like on the day.

UlazSubcontractors on the packageOpen fonaploRezultatContractor chain on recordAlnaplo open per contractor
4

Record the measurement where the money will look for it

Napredak

Where the contract settles on measured quantities, record the measurement tetel by tetel as the work is done, and keep it agreed with the muszaki ellenor rather than presented to them at the end of the month. The felmeresi naplo is the sub-log this belongs in, and the valuation should be readable straight out of it.

Zašto: Measurement agreed while the work is visible takes minutes and measurement argued after it is buried takes a meeting, sometimes a survey, and occasionally a court. It is also the difference between a valuation the certifier can approve line by line and one they can only accept or refuse whole.

UlazWork executed this periodTetel and contract quantityRezultatMeasured quantities per tetelBasis for the valuation
5

Inspect the concealed work before it is concealed

Inspekcije

Before reinforcement is poured over, insulation is boarded, or a service run is buried, call the inspection, photograph the work as built, record the result and only then release the cover. Keep the notice, the inspection and the photographs on the same record.

Zašto: The Epkiv. puts the checking of eltakart szerkezetek on the felelos muszaki vezeto, and once the work is covered the record is the only thing anybody can look at. A dispute about concealed work is decided on the entry and the photograph, and opening it up again to find out is a cost somebody pays whether or not they were wrong.

UlazStructure about to be coveredNotice to the muszaki ellenorRezultatInspection record with photosRelease to cover
6

Keep the muszaki ellenor inside the record

Nadzor gradilišta

Route what the supervising engineer has to see through the naplo rather than by message: the inspections, the measurements, the instructions they give and the written notice that a performance is complete. Record the date the notice went in.

Zašto: The Epkiv. makes a muszaki ellenor mandatory on several kinds of work, public procurement among them, and gives them at most fifteen working days from the contractor's written notice of completion to issue the teljesitesigazolas or refuse it with reasons. That clock only exists if the notice has a date, and the naplo is where the date is beyond argument.

UlazEntries awaiting the ellenorMuszaki ellenor appointmentRezultatCountersigned entriesNotice of completion sent
7

Close the record so it can be read later

Dokumenti

At the end of the works, pull the diary days, the inspections, the measurements and the photographs into one pack on the project, indexed by date, and hand it to close-out with the rest of the completion documentation.

Zašto: The people who will need this record are not the people who wrote it. A defect claim arrives years after the site manager has moved on, and the question is always the same: what was done here, when, and who checked it. A pack assembled at the end while everyone is still on the job answers that; a pack assembled from a defect notice does not.

UlazClosed diary daysInspections and measurementsRezultatSite record packRecord handed to close-out
Moduli

Moduli u ovom playbooku

7 / 190 modula platforme

The market this case is written for

Mađarska

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Kbt.
  • TSZSZ

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Gradilište i teren

Gradilište i teren

Provedite dan na gradilištu

Pravilno zatvorite dan: zabilježite dnevnik, unesite sate rada i mehanizacije, učitajte foto…

4 koraka9 minOtvori
Gradilište i teren

Odgovorite na RFI

Pretvorite pitanje s gradilišta u praćeni zahtjev, proslijedite ga strani koja treba dati od…

3 koraka9 minOtvori