Casos prácticos / Presupuestación y costes
Presupuestación y costes

Construir una composição de custo unitário própria

Fije el precio de los insumos una sola vez, establezca coeficientes que pueda defender, construya las composições auxiliares debajo, componga el serviço a partir de ellas, y deje que el costo unitario se calcule en vez de teclearse, con el origen de cada coeficiente en el registro.

7 pasos20 minConsultoría de costes / QSContratista generalSubcontratista especialista

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Price the insumos once

Catálogo de recursos

Put the mao de obra, the materiais and the equipamentos into the catalog as priced insumos, each in the unit it is bought or paid in and each typed as labour, material or plant. An hour of pedreiro, a tonne of cimento, a productive hour of retroescavadeira.

Por que: Every composicao you write will lean on the same few dozen insumos. Priced once, a change in the steel price moves every composicao that contains steel in a single edit. Priced inside each composicao, the same change is a search through four hundred lines and some of them will be missed.

EntradaSupplier quotes and labour costsUnits of measureResultadoPriced insumo ratesLabour, material and plant separated
2

Set the coeficientes you can defend

Normas de producción

Decide how much of each insumo one unit of the servico consumes, and take the figure from a measured period on a real job wherever you have one. Where you do not, take it from a published productivity study and say which. Keep the loss and reuse factors separate from the productivity itself.

Por que: The coefficient is what the disagreement is actually about, and it is the only part of the composicao that a reader can test against their own experience. Written down with its source it becomes a conversation about how the work is done. Left implicit inside a unit cost, the same disagreement arrives as an accusation that the price is inflated, and there is nothing to point at.

EntradaSite records of work donePublished productivity ratesResultadoCoeficientes per unit of workSource recorded per coefficient
3

Build the composicoes auxiliares first

Partidas compuestas

Anything produced on site before it goes into the work is an auxiliar: the argamassa, the concreto feito em obra, the forma you assemble and use several times. Build each as its own assembly, in its own unit, from the insumos you have just priced.

Por que: The argamassa turns up in the alvenaria, the reboco and the piso, and it is one mix. Modelled once as an auxiliar it stays one number in three composicoes. Retyped into each of them it becomes three numbers that drift apart the first time the sand price moves, and nobody can tell which of the three is the stale one.

EntradaPriced insumo ratesMix quantities per unitResultadoComposicao auxiliar with a calculated rateOne rate shared by every user
4

Compose the servico at the stated coeficientes

Partidas compuestas

Build the servico as an assembly in the unit the bill measures it in, and give every component the quantity one unit of work consumes. Keep the equipment split between productive and idle hours where the machine waits on the crew, because the two are paid differently and averaging them hides both.

Por que: A unit cost that is the total of its components can be checked line by line by somebody who disagrees with only one of them. A unit cost typed in as a single figure has to be accepted or rejected whole, and in public work that means rejected, because there is nothing in it an analyst is able to approve.

EntradaComposicoes auxiliares pricedCoeficientes per unit of workResultadoComposicao with a built-up rateReadable priced breakdown
5

Put the calculated cost on the bill

Presupuesto

Apply the composicao to its position so the unit cost on the bill is the total of the breakdown rather than a number somebody keyed in. Do the same for the positions that share the recipe and differ only in thickness, diameter or class.

Por que: A typed cost and its composicao stop agreeing the moment either one changes, and the bill is the copy everybody reads. Linked, the orcamento you submit and the calculation you defend are the same arithmetic, which is the entire reason for writing the composicao in the first place.

EntradaComposicao and its calculated rateBill positions to priceResultadoPriced bill positionsRate linked to its breakdown
6

Write down why this composicao exists at all

Bases de la estimación

For each composicao propria record two things on the basis of estimate: that the reference systems carry no equivalent item, and where each coefficient and each insumo price came from. Name the job or the study, not the person.

Por que: Decreto 7.983 of 2013 permits a composicao propria where the reference systems fall short, and the permission is only as strong as the evidence that they do. Without that sentence the composicao reads as a way around the median rather than as an answer to a real gap, and it is the reading, not the arithmetic, that decides the finding.

EntradaSource recorded per coefficientReason the base carries no itemResultadoJustification report per composicaoTrail an auditor can follow
7

Keep it as your own banco de composicoes

Base de datos de costes

Move the composicoes you are happy with into the cost database under codes you can search, with the reference month they were priced in. The next orcamento starts from these instead of from a published base you correct in the same three places every time.

Por que: A published base is a good place to start and a poor place to finish: its coeficientes are regional averages and its prices belong to a month that has passed. The version your own jobs have corrected is worth more than either, and it only accumulates if somebody puts it somewhere other than the last project folder.

EntradaFinished composicoesResultadoYour own cost databaseRates ready for the next orcamento
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Brasil

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Presupuestación y costes