案例 / 估算与成本
估算与成本

编制自有composição de custo unitário própria

把insumos的价格定一次,设定可以自圆其说的coeficientes,在下面搭建composições auxiliares,由它们组成serviço,让单价被计算出来而不是直接键入,并记录每个系数的来源。

7 个步骤20 分钟造价咨询 / 工料测量顾问总承包商专业分包商

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Price the insumos once

资源目录

Put the mao de obra, the materiais and the equipamentos into the catalog as priced insumos, each in the unit it is bought or paid in and each typed as labour, material or plant. An hour of pedreiro, a tonne of cimento, a productive hour of retroescavadeira.

原因: Every composicao you write will lean on the same few dozen insumos. Priced once, a change in the steel price moves every composicao that contains steel in a single edit. Priced inside each composicao, the same change is a search through four hundred lines and some of them will be missed.

输入Supplier quotes and labour costsUnits of measure成果Priced insumo ratesLabour, material and plant separated
2

Set the coeficientes you can defend

生产定额

Decide how much of each insumo one unit of the servico consumes, and take the figure from a measured period on a real job wherever you have one. Where you do not, take it from a published productivity study and say which. Keep the loss and reuse factors separate from the productivity itself.

原因: The coefficient is what the disagreement is actually about, and it is the only part of the composicao that a reader can test against their own experience. Written down with its source it becomes a conversation about how the work is done. Left implicit inside a unit cost, the same disagreement arrives as an accusation that the price is inflated, and there is nothing to point at.

输入Site records of work donePublished productivity rates成果Coeficientes per unit of workSource recorded per coefficient
3

Build the composicoes auxiliares first

组合单价

Anything produced on site before it goes into the work is an auxiliar: the argamassa, the concreto feito em obra, the forma you assemble and use several times. Build each as its own assembly, in its own unit, from the insumos you have just priced.

原因: The argamassa turns up in the alvenaria, the reboco and the piso, and it is one mix. Modelled once as an auxiliar it stays one number in three composicoes. Retyped into each of them it becomes three numbers that drift apart the first time the sand price moves, and nobody can tell which of the three is the stale one.

输入Priced insumo ratesMix quantities per unit成果Composicao auxiliar with a calculated rateOne rate shared by every user
4

Compose the servico at the stated coeficientes

组合单价

Build the servico as an assembly in the unit the bill measures it in, and give every component the quantity one unit of work consumes. Keep the equipment split between productive and idle hours where the machine waits on the crew, because the two are paid differently and averaging them hides both.

原因: A unit cost that is the total of its components can be checked line by line by somebody who disagrees with only one of them. A unit cost typed in as a single figure has to be accepted or rejected whole, and in public work that means rejected, because there is nothing in it an analyst is able to approve.

输入Composicoes auxiliares pricedCoeficientes per unit of work成果Composicao with a built-up rateReadable priced breakdown
5

Put the calculated cost on the bill

工程量清单

Apply the composicao to its position so the unit cost on the bill is the total of the breakdown rather than a number somebody keyed in. Do the same for the positions that share the recipe and differ only in thickness, diameter or class.

原因: A typed cost and its composicao stop agreeing the moment either one changes, and the bill is the copy everybody reads. Linked, the orcamento you submit and the calculation you defend are the same arithmetic, which is the entire reason for writing the composicao in the first place.

输入Composicao and its calculated rateBill positions to price成果Priced bill positionsRate linked to its breakdown
6

Write down why this composicao exists at all

估算依据

For each composicao propria record two things on the basis of estimate: that the reference systems carry no equivalent item, and where each coefficient and each insumo price came from. Name the job or the study, not the person.

原因: Decreto 7.983 of 2013 permits a composicao propria where the reference systems fall short, and the permission is only as strong as the evidence that they do. Without that sentence the composicao reads as a way around the median rather than as an answer to a real gap, and it is the reading, not the arithmetic, that decides the finding.

输入Source recorded per coefficientReason the base carries no item成果Justification report per composicaoTrail an auditor can follow
7

Keep it as your own banco de composicoes

造价数据库

Move the composicoes you are happy with into the cost database under codes you can search, with the reference month they were priced in. The next orcamento starts from these instead of from a published base you correct in the same three places every time.

原因: A published base is a good place to start and a poor place to finish: its coeficientes are regional averages and its prices belong to a month that has passed. The version your own jobs have corrected is worth more than either, and it only accumulates if somebody puts it somewhere other than the last project folder.

输入Finished composicoes成果Your own cost databaseRates ready for the next orcamento
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

巴西

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Lei 14.133
  • SINAPI
  • ABNT NBR 12721

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 估算与成本 案例

估算与成本

发出估算前进行核查

让已计价的清单通过核查规则,清除所有警告和错误,再导出一份可以直接交给客户的干净报告。

3 个步骤8 分钟打开
估算与成本

根据成本数据库进行估算

从真实的成本数据库中提取已计价项目,据此构建清单,把常用的组合做法打包成组合定额,提交投标数字前先做校核。

4 个步骤12 分钟打开
估算与成本

根据成本风险设定应急费

把单点估算转化为区间估算,对真正存在不确定性的项目运行蒙特卡洛模拟,读取P50到P90的分布区间,设定一个可以逐项说清楚的应急费。

3 个步骤11 分钟打开