Casos prácticos / Entrega y ciclo de vida
Entrega y ciclo de vida

Separar la jótállás de la szavatosság y liberar la retención

Escriba las dos garantías en el contrato como dos cosas distintas, reciba la obra con la lista de pendientes anotada, corra los dos plazos por separado, y libere la retención contra la que corresponde y no contra la que termina primero.

7 pasos12 minContratista generalSubcontratista especialistaPromotor / clienteConsultoría de costes / QS

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Write the two guarantees as two clauses

Contratos

Record in the contract, separately, the jotallas the contractor undertakes and its period, and the szavatossag that follows from the Ptk. whether anybody writes it down or not. Alongside them record how the obligation is secured: retention held from each payment, a bank guarantee, or both, and on what event each is released.

Por que: Under jotallas the obligor escapes only by proving that the cause of the defect arose after performance; under szavatossag the party claiming carries the proof. A clause that says only garancia leaves that question to be argued at the worst possible moment, which is when a defect has appeared and neither side has a technical answer yet. Two clauses cost one paragraph and settle it in advance.

EntradaContract draftScope and building typeResultadoTwo guarantees written separatelyRetention and security terms
2

Check whether a mandatory jotallas applies

Validación

Before the terms are agreed, check whether the work falls under a jotallas imposed by law rather than chosen by the parties. Government Decree 181/2003 (XI. 5.) is the one that matters in housing, and where it applies the parties cannot contract below it.

Por que: A negotiated guarantee shorter than the mandatory floor is not a negotiated guarantee, it is an unenforceable clause that both sides believed until the day it was tested. The contractor priced a risk it did not shed and the client relied on a period that was never in danger, and both find out at the same moment.

EntradaBuilding type and clientDrafted guarantee termsResultadoMandatory floor identifiedCompliance report
3

Take the works over with the list attached

Lista de pendientes

Walk the works at the atadas-atvetel and record what is outstanding as a list of items with owners and dates, separating what is genuinely incomplete from what is defective. Fix the takeover date on the record, because both guarantee periods are measured from performance.

Por que: Everything after this is dated from here, so a takeover that happened in stages and was never written down leaves two parties with two different opinions about when the clocks started. The distinction between incomplete and defective matters as much: incomplete work is finishing under the contract, and defective work is the guarantee, and only one of them should be holding up the payment.

EntradaCompleted worksTakeover inspectionResultadoList of outstanding itemsTakeover date fixed
4

Put the retention on a schedule, not in a memory

Finanzas

Total what has been retained across the payments, split it into the portion released at takeover and the portion released at the end of the guarantee, and record each release as a dated event with the condition that triggers it.

Por que: Retention is the most commonly forgotten money in construction, in both directions. A contractor who does not track it asks for it late, sometimes years late and sometimes never. A client who does not track it releases it early against a defect it had every right to hold, and cannot get it back.

EntradaRetention held to dateRelease termsResultadoRelease scheduleBalance still held
5

Run the two clocks as two clocks

Plazos

Open a deadline for each period from the takeover date: the jotallas as the contract or the decree sets it, and the kellekszavatossagi igeny separately. Where the thing supplied is real property, that second one lapses five years from performance under the Ptk. rather than in the one year that applies generally.

Por que: Both parties tend to file the job when the shorter clock stops, and that is the error the five-year rule punishes. A client who lets the szavatossagi period run out on a real defect loses a claim it had; a contractor who thinks the file closed with the jotallas has stopped keeping the record that would answer the claim. Two dated deadlines cost nothing and prevent both.

EntradaTakeover dateBoth guarantee periodsResultadoJotallas end dateSzavatossag end date
6

Classify each defect before you argue about it

Garantías y responsabilidad por defectos

When a defect is notified, record which period it falls in, what the site record says about that work, and which guarantee is being relied on. Then track the remedy to closure with the date it was fixed, because a repaired part restarts the limitation on that part.

Por que: Which guarantee applies decides who has to prove what, and that decides the outcome far more often than the technical merits do. Making the classification an explicit step, with the site record next to it, is what turns a defect notice into a question with an answer rather than into an exchange of letters that runs until somebody gives up.

EntradaDefect notified after handoverSite record for that workResultadoDefect classified under one guaranteeRemedy tracked to closure
7

Close the guarantee without closing the file

Cierre

At the end of the jotallas period, walk the outstanding items, release the final retention against a clean list, and keep the project record open until the longer szavatossagi period has run rather than archiving it with the money.

Por que: The record is the asset that outlives the retention. A claim arriving in year four is answered from the naplo, the inspections and the takeover list, and a firm that filed all of it when the money was released is answering from memory instead. Releasing the retention and keeping the file are two decisions, and only one of them should be made at this point.

EntradaExpired jotallas periodOpen defect itemsResultadoFinal retention releasedRecord kept for the longer period
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Hungría

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • Kbt.
  • TSZSZ

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Entrega y ciclo de vida

Entrega y ciclo de vida

Entregar y cerrar la obra

Termine el proyecto sin cabos sueltos: lleve la lista de repasos a cero, confirme que todas…

5 pasos14 minAbrir
Entrega y ciclo de vida

Entrega as-built y O&M

Reúne el registro as-built, demuestra que el expediente de calidad no tiene lagunas y entreg…

3 pasos12 minAbrir