Cases / Oplevering & levenscyclus
Oplevering & levenscyclus

Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven

Schrijf de twee garanties als twee afzonderlijke dingen in het contract, neem het werk over met de openstaande punten op een lijst, laat beide termijnen apart lopen, en geef de inhouding vrij tegen de juiste van de twee in plaats van tegen degene die het eerst afloopt.

7 stappen12 minHoofdaannemerGespecialiseerde onderaannemerOntwikkelaar / opdrachtgeverKostenadvies- / QS-bureau

Zo werkt het, stap voor stap

7 stappen door het platform - wat je bij elke stap doet en waarom het ertoe doet.

1

Write the two guarantees as two clauses

Contracten

Record in the contract, separately, the jotallas the contractor undertakes and its period, and the szavatossag that follows from the Ptk. whether anybody writes it down or not. Alongside them record how the obligation is secured: retention held from each payment, a bank guarantee, or both, and on what event each is released.

Schermafbeelding, stap 1: Write the two guarantees as two clauses (Contracten, Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven)
Contracten: Write the two guarantees as two clauses

Waarom: Under jotallas the obligor escapes only by proving that the cause of the defect arose after performance; under szavatossag the party claiming carries the proof. A clause that says only garancia leaves that question to be argued at the worst possible moment, which is when a defect has appeared and neither side has a technical answer yet. Two clauses cost one paragraph and settle it in advance.

InvoerContract draftScope and building typeResultaatTwo guarantees written separatelyRetention and security terms
2

Check whether a mandatory jotallas applies

Validatie

Before the terms are agreed, check whether the work falls under a jotallas imposed by law rather than chosen by the parties. Government Decree 181/2003 (XI. 5.) is the one that matters in housing, and where it applies the parties cannot contract below it.

Schermafbeelding, stap 2: Check whether a mandatory jotallas applies (Validatie, Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven)
Validatie: Check whether a mandatory jotallas applies

Waarom: A negotiated guarantee shorter than the mandatory floor is not a negotiated guarantee, it is an unenforceable clause that both sides believed until the day it was tested. The contractor priced a risk it did not shed and the client relied on a period that was never in danger, and both find out at the same moment.

InvoerBuilding type and clientDrafted guarantee termsResultaatMandatory floor identifiedCompliance report
3

Take the works over with the list attached

Opnamelijst

Walk the works at the atadas-atvetel and record what is outstanding as a list of items with owners and dates, separating what is genuinely incomplete from what is defective. Fix the takeover date on the record, because both guarantee periods are measured from performance.

Schermafbeelding, stap 3: Take the works over with the list attached (Opnamelijst, Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven)
Opnamelijst: Take the works over with the list attached

Waarom: Everything after this is dated from here, so a takeover that happened in stages and was never written down leaves two parties with two different opinions about when the clocks started. The distinction between incomplete and defective matters as much: incomplete work is finishing under the contract, and defective work is the guarantee, and only one of them should be holding up the payment.

InvoerCompleted worksTakeover inspectionResultaatList of outstanding itemsTakeover date fixed
4

Put the retention on a schedule, not in a memory

Financiën

Total what has been retained across the payments, split it into the portion released at takeover and the portion released at the end of the guarantee, and record each release as a dated event with the condition that triggers it.

Schermafbeelding, stap 4: Put the retention on a schedule, not in a memory (Financiën, Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven)
Financiën: Put the retention on a schedule, not in a memory

Waarom: Retention is the most commonly forgotten money in construction, in both directions. A contractor who does not track it asks for it late, sometimes years late and sometimes never. A client who does not track it releases it early against a defect it had every right to hold, and cannot get it back.

InvoerRetention held to dateRelease termsResultaatRelease scheduleBalance still held
5

Run the two clocks as two clocks

Deadlines

Open a deadline for each period from the takeover date: the jotallas as the contract or the decree sets it, and the kellekszavatossagi igeny separately. Where the thing supplied is real property, that second one lapses five years from performance under the Ptk. rather than in the one year that applies generally.

Waarom: Both parties tend to file the job when the shorter clock stops, and that is the error the five-year rule punishes. A client who lets the szavatossagi period run out on a real defect loses a claim it had; a contractor who thinks the file closed with the jotallas has stopped keeping the record that would answer the claim. Two dated deadlines cost nothing and prevent both.

InvoerTakeover dateBoth guarantee periodsResultaatJotallas end dateSzavatossag end date
6

Classify each defect before you argue about it

Garanties & onderhoudstermijn

When a defect is notified, record which period it falls in, what the site record says about that work, and which guarantee is being relied on. Then track the remedy to closure with the date it was fixed, because a repaired part restarts the limitation on that part.

Schermafbeelding, stap 6: Classify each defect before you argue about it (Garanties & onderhoudstermijn, Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven)
Garanties & onderhoudstermijn: Classify each defect before you argue about it

Waarom: Which guarantee applies decides who has to prove what, and that decides the outcome far more often than the technical merits do. Making the classification an explicit step, with the site record next to it, is what turns a defect notice into a question with an answer rather than into an exchange of letters that runs until somebody gives up.

InvoerDefect notified after handoverSite record for that workResultaatDefect classified under one guaranteeRemedy tracked to closure
7

Close the guarantee without closing the file

Afsluiting

At the end of the jotallas period, walk the outstanding items, release the final retention against a clean list, and keep the project record open until the longer szavatossagi period has run rather than archiving it with the money.

Schermafbeelding, stap 7: Close the guarantee without closing the file (Afsluiting, Jótállás en szavatosság uit elkaar houden en de inhouding vrijgeven)
Afsluiting: Close the guarantee without closing the file

Waarom: The record is the asset that outlives the retention. A claim arriving in year four is answered from the naplo, the inspections and the takeover list, and a firm that filed all of it when the money was released is answering from memory instead. Releasing the retention and keeping the file are two decisions, and only one of them should be made at this point.

InvoerExpired jotallas periodOpen defect itemsResultaatFinal retention releasedRecord kept for the longer period
Modules

Modules in dit playbook

7 / 190 platformmodules

The market this case is written for

Hongarije

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Kbt.
  • TSZSZ

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Meer in Oplevering & levenscyclus

Oplevering & levenscyclus

Opleveren en afsluiten

Rond het project netjes af: werk de opleverlijst naar nul, bevestig dat elke inspectie is ge…

5 stappen14 minOpenen
Oplevering & levenscyclus

Revisie en onderhoudsoplevering

Stel het revisiedossier samen, toon aan dat het kwaliteitsdossier geen hiaten heeft, en leve…

3 stappen12 minOpenen
Oplevering & levenscyclus

Voer een opleveringsinspectie uit

Loop het afgeronde werk na met de klant, leg vast wat wel en wat niet voldoet aan de oplever…

3 stappen11 minOpenen