Предаване и приключване
Завършете обекта чисто: доведете списъка с недостатъци до нула, потвърдете, че всяка инспекц…
Впишете двете гаранции в договора като две различни неща, приемете работите с описани оставащи забележки, водете двата срока поотделно и освободете задържаните суми срещу правилния от тях, а не срещу онзи, който изтича пръв.
7 стъпки през платформата - какво правите на всяка и защо е важно.
Record in the contract, separately, the jotallas the contractor undertakes and its period, and the szavatossag that follows from the Ptk. whether anybody writes it down or not. Alongside them record how the obligation is secured: retention held from each payment, a bank guarantee, or both, and on what event each is released.

Защо: Under jotallas the obligor escapes only by proving that the cause of the defect arose after performance; under szavatossag the party claiming carries the proof. A clause that says only garancia leaves that question to be argued at the worst possible moment, which is when a defect has appeared and neither side has a technical answer yet. Two clauses cost one paragraph and settle it in advance.
Before the terms are agreed, check whether the work falls under a jotallas imposed by law rather than chosen by the parties. Government Decree 181/2003 (XI. 5.) is the one that matters in housing, and where it applies the parties cannot contract below it.

Защо: A negotiated guarantee shorter than the mandatory floor is not a negotiated guarantee, it is an unenforceable clause that both sides believed until the day it was tested. The contractor priced a risk it did not shed and the client relied on a period that was never in danger, and both find out at the same moment.
Walk the works at the atadas-atvetel and record what is outstanding as a list of items with owners and dates, separating what is genuinely incomplete from what is defective. Fix the takeover date on the record, because both guarantee periods are measured from performance.

Защо: Everything after this is dated from here, so a takeover that happened in stages and was never written down leaves two parties with two different opinions about when the clocks started. The distinction between incomplete and defective matters as much: incomplete work is finishing under the contract, and defective work is the guarantee, and only one of them should be holding up the payment.
Total what has been retained across the payments, split it into the portion released at takeover and the portion released at the end of the guarantee, and record each release as a dated event with the condition that triggers it.

Защо: Retention is the most commonly forgotten money in construction, in both directions. A contractor who does not track it asks for it late, sometimes years late and sometimes never. A client who does not track it releases it early against a defect it had every right to hold, and cannot get it back.
Open a deadline for each period from the takeover date: the jotallas as the contract or the decree sets it, and the kellekszavatossagi igeny separately. Where the thing supplied is real property, that second one lapses five years from performance under the Ptk. rather than in the one year that applies generally.
Защо: Both parties tend to file the job when the shorter clock stops, and that is the error the five-year rule punishes. A client who lets the szavatossagi period run out on a real defect loses a claim it had; a contractor who thinks the file closed with the jotallas has stopped keeping the record that would answer the claim. Two dated deadlines cost nothing and prevent both.
When a defect is notified, record which period it falls in, what the site record says about that work, and which guarantee is being relied on. Then track the remedy to closure with the date it was fixed, because a repaired part restarts the limitation on that part.

Защо: Which guarantee applies decides who has to prove what, and that decides the outcome far more often than the technical merits do. Making the classification an explicit step, with the site record next to it, is what turns a defect notice into a question with an answer rather than into an exchange of letters that runs until somebody gives up.
At the end of the jotallas period, walk the outstanding items, release the final retention against a clean list, and keep the project record open until the longer szavatossagi period has run rather than archiving it with the money.

Защо: The record is the asset that outlives the retention. A claim arriving in year four is answered from the naplo, the inspections and the takeover list, and a firm that filed all of it when the money was released is answering from memory instead. Releasing the retention and keeping the file are two decisions, and only one of them should be made at this point.
7 / 190 модула на платформата
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.
Завършете обекта чисто: доведете списъка с недостатъци до нула, потвърдете, че всяка инспекц…
Съберете екзекутивната документация, докажете, че досието по качеството няма пропуски, после…
Обходете завършените работи с клиента, отбележете какво отговаря и какво не спрямо критериит…