ケース / 引き渡しとライフサイクル
引き渡しとライフサイクル

jótállás と瑕疵担保責任を分けたうえで保留金を解放する

jótállás と szavatosság を二つの別のものとして契約に書き込み、残っている項目を列挙したうえで工事を引き取り、二つの期間を別々に数え、先に終わる方ではなく正しい方に対して保留金を解放する。

7ステップ12 分総合建設会社専門工事業者デベロッパー / 発注者コストコンサルティング会社 / 積算事務所

仕組みをステップごとに

プラットフォーム全体で7ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Write the two guarantees as two clauses

契約

Record in the contract, separately, the jotallas the contractor undertakes and its period, and the szavatossag that follows from the Ptk. whether anybody writes it down or not. Alongside them record how the obligation is secured: retention held from each payment, a bank guarantee, or both, and on what event each is released.

理由: Under jotallas the obligor escapes only by proving that the cause of the defect arose after performance; under szavatossag the party claiming carries the proof. A clause that says only garancia leaves that question to be argued at the worst possible moment, which is when a defect has appeared and neither side has a technical answer yet. Two clauses cost one paragraph and settle it in advance.

入力Contract draftScope and building type出力Two guarantees written separatelyRetention and security terms
2

Check whether a mandatory jotallas applies

検証

Before the terms are agreed, check whether the work falls under a jotallas imposed by law rather than chosen by the parties. Government Decree 181/2003 (XI. 5.) is the one that matters in housing, and where it applies the parties cannot contract below it.

理由: A negotiated guarantee shorter than the mandatory floor is not a negotiated guarantee, it is an unenforceable clause that both sides believed until the day it was tested. The contractor priced a risk it did not shed and the client relied on a period that was never in danger, and both find out at the same moment.

入力Building type and clientDrafted guarantee terms出力Mandatory floor identifiedCompliance report
3

Take the works over with the list attached

パンチリスト

Walk the works at the atadas-atvetel and record what is outstanding as a list of items with owners and dates, separating what is genuinely incomplete from what is defective. Fix the takeover date on the record, because both guarantee periods are measured from performance.

理由: Everything after this is dated from here, so a takeover that happened in stages and was never written down leaves two parties with two different opinions about when the clocks started. The distinction between incomplete and defective matters as much: incomplete work is finishing under the contract, and defective work is the guarantee, and only one of them should be holding up the payment.

入力Completed worksTakeover inspection出力List of outstanding itemsTakeover date fixed
4

Put the retention on a schedule, not in a memory

財務

Total what has been retained across the payments, split it into the portion released at takeover and the portion released at the end of the guarantee, and record each release as a dated event with the condition that triggers it.

理由: Retention is the most commonly forgotten money in construction, in both directions. A contractor who does not track it asks for it late, sometimes years late and sometimes never. A client who does not track it releases it early against a defect it had every right to hold, and cannot get it back.

入力Retention held to dateRelease terms出力Release scheduleBalance still held
5

Run the two clocks as two clocks

期限

Open a deadline for each period from the takeover date: the jotallas as the contract or the decree sets it, and the kellekszavatossagi igeny separately. Where the thing supplied is real property, that second one lapses five years from performance under the Ptk. rather than in the one year that applies generally.

理由: Both parties tend to file the job when the shorter clock stops, and that is the error the five-year rule punishes. A client who lets the szavatossagi period run out on a real defect loses a claim it had; a contractor who thinks the file closed with the jotallas has stopped keeping the record that would answer the claim. Two dated deadlines cost nothing and prevent both.

入力Takeover dateBoth guarantee periods出力Jotallas end dateSzavatossag end date
6

Classify each defect before you argue about it

保証と瑕疵担保

When a defect is notified, record which period it falls in, what the site record says about that work, and which guarantee is being relied on. Then track the remedy to closure with the date it was fixed, because a repaired part restarts the limitation on that part.

理由: Which guarantee applies decides who has to prove what, and that decides the outcome far more often than the technical merits do. Making the classification an explicit step, with the site record next to it, is what turns a defect notice into a question with an answer rather than into an exchange of letters that runs until somebody gives up.

入力Defect notified after handoverSite record for that work出力Defect classified under one guaranteeRemedy tracked to closure
7

Close the guarantee without closing the file

完了

At the end of the jotallas period, walk the outstanding items, release the final retention against a clean list, and keep the project record open until the longer szavatossagi period has run rather than archiving it with the money.

理由: The record is the asset that outlives the retention. A claim arriving in year four is answered from the naplo, the inspections and the takeover list, and a firm that filed all of it when the money was released is answering from memory instead. Releasing the retention and keeping the file are two decisions, and only one of them should be made at this point.

入力Expired jotallas periodOpen defect items出力Final retention releasedRecord kept for the longer period
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 7

The market this case is written for

ハンガリー

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Kbt.
  • TSZSZ

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

引き渡しとライフサイクルの他のケース

引き渡しとライフサイクル

引き渡しと竣工処理を行う

案件をきれいに終える。手直しリストをゼロにし、すべての検査が合格し未解決の不適合がないことを確認し、竣工図書一式をまとめ、署名済みの引き渡しを発行する。

5ステップ14 分開く
引き渡しとライフサイクル

竣工図と維持管理マニュアルの引渡し

竣工記録をまとめ、品質ファイルに漏れがないことを確認したうえで、運営者が実際に建物を管理・運用できる維持管理マニュアルを発行します。

3ステップ12 分開く
引き渡しとライフサイクル

引き渡し受入検査を実施する

施主と共に完成した工事を巡回し、受入基準に照らして合否を記録し、不具合リストをゼロまで解消し、清算された引き渡し受入を発行する。

3ステップ11 分開く