Casos / Entrega e ciclo de vida
Entrega e ciclo de vida

Separar a jótállás da szavatosság e libertar a retenção

Escreva as duas garantias no contrato como duas coisas distintas, receba os trabalhos com a lista de pendências registada, corra os dois prazos em separado, e liberte a retenção contra a garantia certa em vez de contra a que terminar primeiro.

7 etapas12 minEmpreiteiro geralSubempreiteiro especializadoPromotor / clienteConsultoria de custos / QS

Como funciona, passo a passo

7 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Write the two guarantees as two clauses

Contratos

Record in the contract, separately, the jotallas the contractor undertakes and its period, and the szavatossag that follows from the Ptk. whether anybody writes it down or not. Alongside them record how the obligation is secured: retention held from each payment, a bank guarantee, or both, and on what event each is released.

Por quê: Under jotallas the obligor escapes only by proving that the cause of the defect arose after performance; under szavatossag the party claiming carries the proof. A clause that says only garancia leaves that question to be argued at the worst possible moment, which is when a defect has appeared and neither side has a technical answer yet. Two clauses cost one paragraph and settle it in advance.

EntradaContract draftScope and building typeResultadoTwo guarantees written separatelyRetention and security terms
2

Check whether a mandatory jotallas applies

Validação

Before the terms are agreed, check whether the work falls under a jotallas imposed by law rather than chosen by the parties. Government Decree 181/2003 (XI. 5.) is the one that matters in housing, and where it applies the parties cannot contract below it.

Por quê: A negotiated guarantee shorter than the mandatory floor is not a negotiated guarantee, it is an unenforceable clause that both sides believed until the day it was tested. The contractor priced a risk it did not shed and the client relied on a period that was never in danger, and both find out at the same moment.

EntradaBuilding type and clientDrafted guarantee termsResultadoMandatory floor identifiedCompliance report
3

Take the works over with the list attached

Lista de Pendências

Walk the works at the atadas-atvetel and record what is outstanding as a list of items with owners and dates, separating what is genuinely incomplete from what is defective. Fix the takeover date on the record, because both guarantee periods are measured from performance.

Por quê: Everything after this is dated from here, so a takeover that happened in stages and was never written down leaves two parties with two different opinions about when the clocks started. The distinction between incomplete and defective matters as much: incomplete work is finishing under the contract, and defective work is the guarantee, and only one of them should be holding up the payment.

EntradaCompleted worksTakeover inspectionResultadoList of outstanding itemsTakeover date fixed
4

Put the retention on a schedule, not in a memory

Finanças

Total what has been retained across the payments, split it into the portion released at takeover and the portion released at the end of the guarantee, and record each release as a dated event with the condition that triggers it.

Por quê: Retention is the most commonly forgotten money in construction, in both directions. A contractor who does not track it asks for it late, sometimes years late and sometimes never. A client who does not track it releases it early against a defect it had every right to hold, and cannot get it back.

EntradaRetention held to dateRelease termsResultadoRelease scheduleBalance still held
5

Run the two clocks as two clocks

Prazos

Open a deadline for each period from the takeover date: the jotallas as the contract or the decree sets it, and the kellekszavatossagi igeny separately. Where the thing supplied is real property, that second one lapses five years from performance under the Ptk. rather than in the one year that applies generally.

Por quê: Both parties tend to file the job when the shorter clock stops, and that is the error the five-year rule punishes. A client who lets the szavatossagi period run out on a real defect loses a claim it had; a contractor who thinks the file closed with the jotallas has stopped keeping the record that would answer the claim. Two dated deadlines cost nothing and prevent both.

EntradaTakeover dateBoth guarantee periodsResultadoJotallas end dateSzavatossag end date
6

Classify each defect before you argue about it

Garantias e responsabilidade por defeitos

When a defect is notified, record which period it falls in, what the site record says about that work, and which guarantee is being relied on. Then track the remedy to closure with the date it was fixed, because a repaired part restarts the limitation on that part.

Por quê: Which guarantee applies decides who has to prove what, and that decides the outcome far more often than the technical merits do. Making the classification an explicit step, with the site record next to it, is what turns a defect notice into a question with an answer rather than into an exchange of letters that runs until somebody gives up.

EntradaDefect notified after handoverSite record for that workResultadoDefect classified under one guaranteeRemedy tracked to closure
7

Close the guarantee without closing the file

Encerramento

At the end of the jotallas period, walk the outstanding items, release the final retention against a clean list, and keep the project record open until the longer szavatossagi period has run rather than archiving it with the money.

Por quê: The record is the asset that outlives the retention. A claim arriving in year four is answered from the naplo, the inspections and the takeover list, and a firm that filed all of it when the money was released is answering from memory instead. Releasing the retention and keeping the file are two decisions, and only one of them should be made at this point.

EntradaExpired jotallas periodOpen defect itemsResultadoFinal retention releasedRecord kept for the longer period
Módulos

Módulos deste playbook

7 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Hungria

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • Kbt.
  • TSZSZ

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Entrega e ciclo de vida

Entrega e ciclo de vida

Entregar e encerrar a obra

Termine a obra de forma limpa: leve a lista de pendências a zero, confirme que todas as insp…

5 etapas14 minAbrir
Entrega e ciclo de vida

Entrega as-built e de O&M

Reúna o registo as-built, comprove que o dossier de qualidade não tem lacunas, e emita um pa…

3 etapas12 minAbrir