سناریوها / برآورد و هزینه‌یابی
برآورد و هزینه‌یابی

پایبندی برآورد به مبلغ مصوب

کار را از یک برآورد اولیه و تأییدش تا برآورد تفصیلی و تصویب فنی آن ببرید، اقلام پیش‌بینی‌نشده را جایی قابل مشاهده نگه دارید، هر انحراف را در برابر سقف پیگیری کنید، و پیش از آنکه پول تمام شود، نه بعد از آن، درخواست بازنگری بدهید.

5 مرحله20 دقیقهسازنده / کارفرمادفتر مدیریت پروژه / ساختمشاوره هزینه / QSپیمانکار عمومی

چگونه کار می‌کند، گام به گام

5 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Put up a preliminary estimate that says what it assumed

برآورد مفهومی

Build the early estimate from area rates or from comparable completed work, and record with it the scope assumed, the price level used and what is excluded. Carry that figure as the amount put up for approval.

چرا: The approved amount is fixed from this estimate and governs the job for years, so its assumptions matter more than its precision. An estimate that states what it left out can be revised for a stated reason; one that states only a number is revised for what looks like a mistake.

ورودیThe scope as proposedPlinth area or comparable ratesخروجیA preliminary estimate with its basisThe amount put up for approval
2

Build the detailed estimate and compare it with the approval

صورت مقادیر (BOQ)

Measure and price the work in full on the governing schedule, then set the total beside the approved amount and account for the difference sub-head by sub-head rather than as one variance.

چرا: The gap between a preliminary and a detailed estimate is normal and is expected to be explained. Explaining it by sub-head shows whether the scope grew, the rates moved or the early estimate was thin, and only the first of those is a reason to revise the approval.

ورودیWorking drawings and specificationThe governing schedule of ratesخروجیA detailed estimate for technical sanctionWhere it sits against the approval
3

Keep the contingency visible and spend it deliberately

تخصیص‌ها و ذخیره اضطراری

Hold the contingency as its own provision inside the sanctioned amount, with a note of what it is for, and record each drawing on it against the event that caused it.

چرا: Contingency spread into rates is spent invisibly and is gone before anyone knows it was being used. Held apart, it answers the only question that matters halfway through a job, which is how much room is left before the ceiling and what has already consumed the rest.

ورودیWhat the job might still meetخروجیContingency as a stated provisionWho may draw on it and for what
4

Add the deviations up as they happen

سفارش‌های تغییر

Record every deviation with its value, whether it is an excess over a sanctioned quantity, a new item or a saving, and keep the cumulative effect against the sanctioned amount rather than against the last approved change.

چرا: Deviations are approved one at a time and consume the ceiling collectively, which is precisely the arithmetic nobody does in the moment. A running total is the only instrument that turns twelve reasonable individual decisions into a visible position.

ورودیDeviations as they ariseخروجیA running total against the ceilingHeadroom left, at any moment
5

Ask for the revision before the headroom is gone

گزارش‌ها

Report the position against the sanctioned amount at each period, and when the trend shows the ceiling being reached, produce the revised estimate with the reasons separated into scope, quantity and rate, and put it up while there is still room to work under the existing sanction.

چرا: A revision sought early is a technical submission with an answer to every question. One sought after the ceiling is passed is the same submission with an explanation attached for why work continued, and that explanation is what turns an ordinary cost increase into a finding against the department.

ورودیThe position against the ceilingخروجیA revised estimate with its reasonsAsked for while there is still headroom
ماژول‌ها

ماژول‌های این سناریو

5 / 190 ماژول پلتفرم

The market this case is written for

هند

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در برآورد و هزینه‌یابی

برآورد و هزینه‌یابی

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 مرحله8 دقیقهباز کردن
برآورد و هزینه‌یابی

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 مرحله12 دقیقهباز کردن
برآورد و هزینه‌یابی

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 مرحله11 دقیقهباز کردن