Casos prácticos / Presupuestación y costos
Presupuestación y costos

Mantener el presupuesto dentro del monto autorizado

Lleva el trabajo de un presupuesto preliminar y su aprobación a un presupuesto detallado y su visto bueno técnico, mantén el contingente a la vista, sigue cada desviación contra el tope, y pide una revisión antes de que se acabe el dinero, no después.

5 pasos20 minDesarrollador / clienteGestora de proyectos / construcciónConsultoría de costos / QSContratista general

Cómo funciona, paso a paso

5 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Put up a preliminary estimate that says what it assumed

Estimación conceptual

Build the early estimate from area rates or from comparable completed work, and record with it the scope assumed, the price level used and what is excluded. Carry that figure as the amount put up for approval.

Por que: The approved amount is fixed from this estimate and governs the job for years, so its assumptions matter more than its precision. An estimate that states what it left out can be revised for a stated reason; one that states only a number is revised for what looks like a mistake.

EntradaThe scope as proposedPlinth area or comparable ratesResultadoA preliminary estimate with its basisThe amount put up for approval
2

Build the detailed estimate and compare it with the approval

Presupuesto

Measure and price the work in full on the governing schedule, then set the total beside the approved amount and account for the difference sub-head by sub-head rather than as one variance.

Por que: The gap between a preliminary and a detailed estimate is normal and is expected to be explained. Explaining it by sub-head shows whether the scope grew, the rates moved or the early estimate was thin, and only the first of those is a reason to revise the approval.

EntradaWorking drawings and specificationThe governing schedule of ratesResultadoA detailed estimate for technical sanctionWhere it sits against the approval
3

Keep the contingency visible and spend it deliberately

Provisiones y contingencia

Hold the contingency as its own provision inside the sanctioned amount, with a note of what it is for, and record each drawing on it against the event that caused it.

Por que: Contingency spread into rates is spent invisibly and is gone before anyone knows it was being used. Held apart, it answers the only question that matters halfway through a job, which is how much room is left before the ceiling and what has already consumed the rest.

EntradaWhat the job might still meetResultadoContingency as a stated provisionWho may draw on it and for what
4

Add the deviations up as they happen

Órdenes de cambio

Record every deviation with its value, whether it is an excess over a sanctioned quantity, a new item or a saving, and keep the cumulative effect against the sanctioned amount rather than against the last approved change.

Por que: Deviations are approved one at a time and consume the ceiling collectively, which is precisely the arithmetic nobody does in the moment. A running total is the only instrument that turns twelve reasonable individual decisions into a visible position.

EntradaDeviations as they ariseResultadoA running total against the ceilingHeadroom left, at any moment
5

Ask for the revision before the headroom is gone

Informes

Report the position against the sanctioned amount at each period, and when the trend shows the ceiling being reached, produce the revised estimate with the reasons separated into scope, quantity and rate, and put it up while there is still room to work under the existing sanction.

Por que: A revision sought early is a technical submission with an answer to every question. One sought after the ceiling is passed is the same submission with an explanation attached for why work continued, and that explanation is what turns an ordinary cost increase into a finding against the department.

EntradaThe position against the ceilingResultadoA revised estimate with its reasonsAsked for while there is still headroom
Módulos

Módulos de este playbook

5 / 190 módulos de la plataforma

The market this case is written for

India

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Más en Presupuestación y costos

Presupuestación y costos

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 pasos12 minAbrir
Presupuestación y costos

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 pasos11 minAbrir