Fixez la gross floor area et l'unité fonctionnelle, construisez le plan élément par élément sur la liste d'éléments de l'AIQS, chiffrez chaque élément à partir de projets analysés, réévaluez au milieu de la construction, gardez séparées les contingencies de conception et de construction, et publiez un plan sur lequel le suivant pourra être comparé.
6 étapes à travers la plateforme - ce que vous faites à chacune et pourquoi c’est important.
Record the gross floor area the plan is built on, measured the way the manual measures it, the functional unit the client thinks in, beds, car spaces, classrooms or seats, and the list of what the plan excludes: land, authority charges, loose furniture, client contingency and the escalation beyond the horizon you have priced to.
Pourquoi: Two cost plans for the same building differ by a fifth when they measure area differently, and neither is wrong. Everything downstream is a rate per square metre, so an area defined loosely puts the same looseness on every element at once, and no later check finds it because every element is internally consistent.
Work down the element list rather than around the drawing: substructure, columns, upper floors, staircases, roof, external walls, windows and external doors, internal walls and doors, the three finishes, fittings, services and external works. Each element carries its own quantity, its element unit quantity and its cost, so the number can be argued about one element at a time.
Pourquoi: An element list worked through in order is also a completeness check, because an element with nothing against it is visible and a missing trade in a lump sum is not. It is how a plan produced in a day still has a roof in it.
Compare each element unit rate with the same element on completed projects of the same type, and write down the reason for every element that sits outside the range. A facade rate double the library is either a design decision worth naming or an error, and the difference between those two is a sentence.
Pourquoi: Elemental analysis exists so that a plan can be challenged before it is approved rather than after it is exceeded. An element that nobody could explain at the design review is the same element that becomes the overrun, and it was visible months earlier.
Record the base date the rates are current at, then escalate them to the midpoint of the construction period the programme implies. State both dates on the plan, and state the index you escalated with.
Pourquoi: A cost plan priced at today's rates for a building that starts in eighteen months is wrong on the day it is issued, and it is wrong in the direction nobody wants to discover later. Naming the base date is what lets a board read the number as an estimate of a future cost rather than as a price.
Carry a design contingency for the drawings that are not finished yet and a separate construction contingency for what the site will find, each as its own entry with what it is for. Reduce the design one as the design is resolved rather than letting it drift into the construction one.
Pourquoi: One combined contingency answers no question. It cannot be released as the design firms up, because nobody can say which part was for the design, and it cannot be defended when the site finds rock, because it has already been spent on documentation gaps.
Issue the plan with the element table, the rate per square metre, the rate per functional unit and a reconciliation against the previous plan that says which elements moved and why. Keep it as the version the next design review is measured from.
Pourquoi: A cost plan issued without a reconciliation is a new number rather than a report on the old one, and the conversation it produces is about whether to believe it. With the movement written out element by element, the same meeting is about four decisions that were already made.
6 / 190 modules de la plateforme
Tout dans ce cas suit la façon dont les travaux sont métrés, chiffrés et payés sur ce marché. Les formulaires, la décomposition des coûts et les règles de paiement sont ceux qui y sont utilisés, pas une version générique.
Normes qu’il suit
Vous n’avez rien de tout cela à paramétrer à la main. Au premier démarrage, la plateforme demande sur quel marché vous travaillez. Choisissez celui-ci et elle règle la langue de l’interface, charge la base de coûts correspondante, enregistre la classification des coûts et ajoute un projet d’exemple que vous pouvez ouvrir tout de suite.
Les contrôles propres à ce marché sont eux aussi fournis avec la plateforme. Une fois activés, un devis auquel il manque quelque chose que le marché attend est signalé pendant que vous y travaillez, et non après l’envoi de l’offre.
Passez un bordereau chiffré dans les règles de validation, corrigez chaque avertissement et…
Extraire des postes chiffrés d'une base de coûts réelle, construire le devis à partir d'eux,…
Transformer une estimation ponctuelle en fourchette, exécuter une simulation Monte Carlo sur…