按Australian Cost Management Manual编制elemental cost plan

确定总建筑面积和functional unit,按AIQS构件清单逐个构件构建计划,用已分析的项目为每个构件定价,升级到施工中期,把设计和施工的预备费分开保留,并发布一份能让下一份与之比较的计划。

6 个步骤18 分钟造价咨询 / 工料测量顾问开发商/业主项目/施工管理公司

运作方式,逐步说明

贯穿平台的 6 个步骤 - 每一步做什么,以及为什么重要。

1

Fix the area, the functional unit and the exclusions

估算依据

Record the gross floor area the plan is built on, measured the way the manual measures it, the functional unit the client thinks in, beds, car spaces, classrooms or seats, and the list of what the plan excludes: land, authority charges, loose furniture, client contingency and the escalation beyond the horizon you have priced to.

原因: Two cost plans for the same building differ by a fifth when they measure area differently, and neither is wrong. Everything downstream is a rate per square metre, so an area defined loosely puts the same looseness on every element at once, and no later check finds it because every element is internally consistent.

输入Project brief and area scheduleDesign stage reached成果Gross floor area agreedInclusions and exclusions stated
2

Build the plan element by element

概念估算

Work down the element list rather than around the drawing: substructure, columns, upper floors, staircases, roof, external walls, windows and external doors, internal walls and doors, the three finishes, fittings, services and external works. Each element carries its own quantity, its element unit quantity and its cost, so the number can be argued about one element at a time.

原因: An element list worked through in order is also a completeness check, because an element with nothing against it is visible and a missing trade in a lump sum is not. It is how a plan produced in a day still has a roof in it.

输入Gross floor area agreedConcept drawings成果Cost plan by elementElement quantities
3

Rate each element against projects already analysed

Cost Explorer

Compare each element unit rate with the same element on completed projects of the same type, and write down the reason for every element that sits outside the range. A facade rate double the library is either a design decision worth naming or an error, and the difference between those two is a sentence.

原因: Elemental analysis exists so that a plan can be challenged before it is approved rather than after it is exceeded. An element that nobody could explain at the design review is the same element that becomes the overrun, and it was visible months earlier.

输入Cost plan by elementAnalysed projects成果Elements benchmarkedOutlying elements explained
4

Escalate to the middle of construction, not to today

价格指数

Record the base date the rates are current at, then escalate them to the midpoint of the construction period the programme implies. State both dates on the plan, and state the index you escalated with.

原因: A cost plan priced at today's rates for a building that starts in eighteen months is wrong on the day it is issued, and it is wrong in the direction nobody wants to discover later. Naming the base date is what lets a board read the number as an estimate of a future cost rather than as a price.

输入Elements benchmarkedIndicative programme成果Escalated to a stated dateBase date on the record
5

Keep the two contingencies apart

暂列金额与应急费

Carry a design contingency for the drawings that are not finished yet and a separate construction contingency for what the site will find, each as its own entry with what it is for. Reduce the design one as the design is resolved rather than letting it drift into the construction one.

原因: One combined contingency answers no question. It cannot be released as the design firms up, because nobody can say which part was for the design, and it cannot be defended when the site finds rock, because it has already been spent on documentation gaps.

输入Escalated to a stated dateKnown design gaps成果Design contingencyConstruction contingency
6

Issue it against the plan it replaces

报告

Issue the plan with the element table, the rate per square metre, the rate per functional unit and a reconciliation against the previous plan that says which elements moved and why. Keep it as the version the next design review is measured from.

原因: A cost plan issued without a reconciliation is a new number rather than a report on the old one, and the conversation it produces is about whether to believe it. With the movement written out element by element, the same meeting is about four decisions that were already made.

输入Complete cost planPrevious cost plan成果Cost plan issuedMovement since the last plan
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

澳大利亚

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 估算与成本 案例

估算与成本

发出估算前进行核查

让已计价的清单通过核查规则,清除所有警告和错误,再导出一份可以直接交给客户的干净报告。

3 个步骤8 分钟打开
估算与成本

根据成本数据库进行估算

从真实的成本数据库中提取已计价项目,据此构建清单,把常用的组合做法打包成组合定额,提交投标数字前先做校核。

4 个步骤12 分钟打开
估算与成本

根据成本风险设定应急费

把单点估算转化为区间估算,对真正存在不确定性的项目运行蒙特卡洛模拟,读取P50到P90的分布区间,设定一个可以逐项说清楚的应急费。

3 个步骤11 分钟打开