Casos / Orçamentação e custos
Orçamentação e custos

Produza um elemental cost plan pelo Australian Cost Management Manual

Fixe a área bruta de piso e a functional unit, construa o plano elemento a elemento na lista de elementos da AIQS, taxe cada elemento a partir de obras analisadas, escale para o meio da construção, mantenha as contingências de projecto e de construção separadas e emita um plano contra o qual o próximo possa ser comparado.

6 etapas18 minConsultoria de custos / QSPromotor / clienteGabinete de gestão de projetos / obras

Como funciona, passo a passo

6 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Fix the area, the functional unit and the exclusions

Base da estimativa

Record the gross floor area the plan is built on, measured the way the manual measures it, the functional unit the client thinks in, beds, car spaces, classrooms or seats, and the list of what the plan excludes: land, authority charges, loose furniture, client contingency and the escalation beyond the horizon you have priced to.

Por quê: Two cost plans for the same building differ by a fifth when they measure area differently, and neither is wrong. Everything downstream is a rate per square metre, so an area defined loosely puts the same looseness on every element at once, and no later check finds it because every element is internally consistent.

EntradaProject brief and area scheduleDesign stage reachedResultadoGross floor area agreedInclusions and exclusions stated
2

Build the plan element by element

Estimativa conceptual

Work down the element list rather than around the drawing: substructure, columns, upper floors, staircases, roof, external walls, windows and external doors, internal walls and doors, the three finishes, fittings, services and external works. Each element carries its own quantity, its element unit quantity and its cost, so the number can be argued about one element at a time.

Por quê: An element list worked through in order is also a completeness check, because an element with nothing against it is visible and a missing trade in a lump sum is not. It is how a plan produced in a day still has a roof in it.

EntradaGross floor area agreedConcept drawingsResultadoCost plan by elementElement quantities
3

Rate each element against projects already analysed

Explorador de custos

Compare each element unit rate with the same element on completed projects of the same type, and write down the reason for every element that sits outside the range. A facade rate double the library is either a design decision worth naming or an error, and the difference between those two is a sentence.

Por quê: Elemental analysis exists so that a plan can be challenged before it is approved rather than after it is exceeded. An element that nobody could explain at the design review is the same element that becomes the overrun, and it was visible months earlier.

EntradaCost plan by elementAnalysed projectsResultadoElements benchmarkedOutlying elements explained
4

Escalate to the middle of construction, not to today

Índice de preços

Record the base date the rates are current at, then escalate them to the midpoint of the construction period the programme implies. State both dates on the plan, and state the index you escalated with.

Por quê: A cost plan priced at today's rates for a building that starts in eighteen months is wrong on the day it is issued, and it is wrong in the direction nobody wants to discover later. Naming the base date is what lets a board read the number as an estimate of a future cost rather than as a price.

EntradaElements benchmarkedIndicative programmeResultadoEscalated to a stated dateBase date on the record
5

Keep the two contingencies apart

Provisões e contingências

Carry a design contingency for the drawings that are not finished yet and a separate construction contingency for what the site will find, each as its own entry with what it is for. Reduce the design one as the design is resolved rather than letting it drift into the construction one.

Por quê: One combined contingency answers no question. It cannot be released as the design firms up, because nobody can say which part was for the design, and it cannot be defended when the site finds rock, because it has already been spent on documentation gaps.

EntradaEscalated to a stated dateKnown design gapsResultadoDesign contingencyConstruction contingency
6

Issue it against the plan it replaces

Relatórios

Issue the plan with the element table, the rate per square metre, the rate per functional unit and a reconciliation against the previous plan that says which elements moved and why. Keep it as the version the next design review is measured from.

Por quê: A cost plan issued without a reconciliation is a new number rather than a report on the old one, and the conversation it produces is about whether to believe it. With the movement written out element by element, the same meeting is about four decisions that were already made.

EntradaComplete cost planPrevious cost planResultadoCost plan issuedMovement since the last plan
Módulos

Módulos deste playbook

6 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Austrália

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • AS 4000
  • Security of Payment Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.