Build a parametric assembly

Give an assembly named parameters and drive its component quantities from formulas over them: enter the wall area when you apply it and let the reinforcement, the concrete and the composite rate follow.

4단계12 분원가 컨설팅 / 적산 업체종합건설사전문건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 4단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Name the parameters

일위대가

Give the assembly the few named parameters it really turns on. Each is one of three kinds: an input the estimator enters when they apply it, with a sensible default; a constant that does not move, such as a rebar ratio; or a calculated value derived from the others, such as area from length times height.

이유: The parameters are the questions the assembly asks whoever uses it, so keep them to the ones that genuinely change between jobs. Every extra input is another figure somebody has to be right about at half past five on the day the tender goes in.

입력Build-up you price repeatedlyWhat actually varies job to job결과Named parametersResolved default values
2

Drive the quantities from a formula

일위대가

Set a component's quantity from a formula over the parameters instead of a fixed number, the reinforcement as wall area times the rebar ratio, the formwork as area times a double-sided factor. Any line whose quantity is computed carries an fx marker on it.

이유: A fixed recipe makes you re-derive the steel by hand every time the wall moves. Written as a formula the relationship is stated once, so the ratio you agreed with the engineer is the ratio in every priced line, and the fx marker stops anyone reading a derived quantity as one that was measured.

입력Named parametersComponent lines결과Quantity formulasComputed lines marked fx
3

Prove it before anyone uses it

일위대가

The editor checks the parameter graph as you work and flags problems inline against the parameter or component they belong to: a name referenced but never defined, two parameters sharing a name, a formula that will not parse, a cycle where two calculated values depend on each other. Then run the expansion preview at real values and read the quantity each line moves from and to, plus the rolled-up rate the server will write.

이유: A cycle or a stale reference does not announce itself in a spreadsheet, it just returns a number that looks plausible. Previewing at values you actually expect is what catches a formula that is right in principle and out by a factor of ten, and because the preview runs on the same decimal arithmetic as the live expansion, the rate you read here is the rate that lands, exact to the cent.

입력Draft parametric assemblyValues you expect on the job결과Named errors, if anyBefore and after per line
4

Apply it to the bill

내역서

Place the assembly on a bill position and enter the one figure it asks for, the wall area for that element. The components expand at those values and the composite rate follows, with nobody retyping a quantity.

이유: This is where the parametric version earns its keep over a fixed recipe. When the wall grows at the next design issue you change one input rather than eleven component quantities, and the two or three that would quietly have been forgotten move with the rest.

입력Proven assemblyWall area for this element결과Priced bill positionComponents at computed quantities
모듈

이 플레이북의 모듈

플랫폼 184개 모듈 중 2

적산 및 원가 카테고리의 더 보기

적산 및 원가

발송 전 견적 점검

산출된 내역서를 검증 규칙에 통과시켜 모든 경고와 오류를 해결한 뒤, 발주자에게 바로 전달할 수 있는 깨끗한 보고서를 내보냅니다.

3단계8 분열기
적산 및 원가

원가 데이터베이스로 견적 산정하기

실제 원가 데이터베이스에서 가격 항목을 가져와 내역서를 작성하고, 반복되는 조합을 어셈블리로 묶은 뒤, 입찰 금액을 확정하기 전에 검토를 실행합니다.

4단계12 분열기
적산 및 원가

비용 리스크로 예비비 산정하기

단일 값 견적을 범위로 바꾸고, 실제로 불확실한 항목에 대해 몬테카를로 시뮬레이션을 실행하여 P50~P90 분포를 읽고, 항목별로 근거를 설명할 수 있는 예비비를 설…

3단계11 분열기