케이스 / 상업 및 계약
상업 및 계약

Building Industry Fairness Act에 따라 project trust account 개설하기

퀸즐랜드 계약이 project trust를 요구하는 계약인지 판단하고, 계좌를 개설하고 통지를 하고, 모든 하도급업체에 beneficiary임을 알리고, cash retention을 retention trust account에 넣고, Act가 정한 순서로 trust에서 지급하고, account review가 요구할 기록을 보관한다.

6단계16 분종합건설사시행사 / 발주처전문건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Settle whether this contract needs a trust

계약

Record against the contract whether it is an eligible contract for a project trust under the Queensland Act: what kind of work it is, what it is worth, who the contracting party is and whether the contract engages subcontractors at all. Record who the trustee is, which on a project trust is the contracted party, normally the head contractor.

이유: The eligibility test has been widened in stages, so a company that correctly decided last year that a job was out of scope can be wrong about the same kind of job this year. The decision belongs on the contract record with the reasons, because the question comes back at the first audit and nobody remembers what was assumed.

입력The contract as signedWho the parties are결과Whether a trust is requiredWho the trustee is
2

Open the accounts and give the notices

재무

Open the project trust account with a financial institution that offers them, name it so it reads as a trust account, and give the notices the Act requires within the periods it sets: to the commission, to the contracting party and to each beneficiary. Record the date each notice went and to whom.

이유: The notices are where this regime is most often breached, because opening an account feels like the task and telling people about it feels like paperwork. The Act treats them as the substance: a trust nobody was told about protects nobody, and the penalty attaches to the notice rather than to the money.

입력Whether a trust is requiredBank that offers trust accounts결과Trust accounts openedNotices given on time
3

Keep the beneficiary register current

협력업체 디렉터리

Treat the subcontractor directory as the beneficiary register: every subcontractor engaged under the contract is a beneficiary of the project trust, and each new one has to be told after they are engaged rather than at the next convenient moment.

이유: A beneficiary can ask to see the trust records, and the obligation to tell them is triggered by the engagement, not by the first payment. A register that is a month behind the site is a register that has already missed a notice, and the subcontractors added late in a job are exactly the ones added under pressure.

입력Subcontracts letSubcontractors added later결과Beneficiary registerEach one told they are one
4

Put the cash retention where the Act puts it

유보금

Deposit cash retention withheld from a subcontractor into the retention trust account rather than into working capital, and hold the balance per subcontractor with the date each part of it falls due for release. One retention trust account serves the trustee across its contracts, so the per subcontractor balance has to be readable inside it.

이유: Retention used as working capital is the practice the whole trust framework was built to end, and it is also the practice that collapses a chain of subcontractors when a builder fails. Held in trust with a release date per subcontractor, the money is theirs and the release is something the calendar produces rather than something a subcontractor has to ask for twice.

입력Cash retention withheldRelease terms per subcontract결과Retention in the retention trustRelease dates per subcontractor
5

Pay from the trust, and pay yourself out of it last

지불

Run every payment to a beneficiary out of the project trust account, and withdraw the trustee's own entitlement from the same account only after the beneficiaries for that payment have been dealt with. Keep the payment record so each withdrawal can be traced to the amount it discharged.

이유: A trustee paying itself ahead of its beneficiaries is the failure the Act is aimed at, and it looks completely ordinary from inside a busy accounts department. The order matters more than the amount, which is why the sequence has to be built into how payments are run rather than checked afterwards.

입력Project payment receivedSubcontractor amounts due결과Beneficiaries paid from the trustTrustee's own money taken last
6

Review the account every month and keep the records

보고서

Reconcile the trust account against the bank statement each month, keep the trust ledger, the notices given and the records of every deposit and withdrawal, and hold them for the period the Act requires so they can be produced to the commission or to a beneficiary who asks.

이유: The account review is not an audit of whether the business is solvent, it is a check that the trust was operated as a trust, and it is answered entirely out of records that either exist or do not. A month reconciled at the time takes twenty minutes; the same month reconstructed under a request takes days and still looks reconstructed.

입력Trust account movementsBank statements결과Monthly account reviewTrust records ready to produce
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 4

The market this case is written for

오스트레일리아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • AS 4000
  • Security of Payment Act

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기