Close the object and get the commissioning permit (vvod v ekspluatatsiyu)

Keep the obshchiy zhurnal rabot from the first day, file the acts and the material documents as they are signed, assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 lists, sign the acceptance, pass the final check of the state construction supervision and apply for the permit to commission under article 55 of the Town Planning Code.

7 алхам15 минЕрөнхий гүйцэтгэгчХөгжүүлэгч / захиалагчТөслийн / барилгын менежментийн компаниӨртгийн зөвлөгөө / QS

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 7 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Open the works journal on the day the permit is issued

Барилгын хяналт

Start the obshchiy zhurnal rabot in the form the supervision rules prescribe, register it where the rules require, and record from the outset who may sign on behalf of the developer, the contractor, the designer's supervision and the construction control service, with the orders that appointed them. Keep the specialised journals for the works that need their own.

Дэлгэцийн зураг, 1-р алхам: Open the works journal on the day the permit is issued (Барилгын хяналт, Close the object and get the commissioning permit (vvod v ekspluatatsiyu))
Барилгын хяналт: Open the works journal on the day the permit is issued

Яагаад: The journal is the primary record the supervision body reads at the final check, and it is read for continuity as much as for content, so a gap in it is a gap in the evidence that the work was controlled at all. An entry signed by a person whose appointment is not on file is worth no more than an unsigned one, and that is discovered at the end, when nobody can go back and be appointed retroactively.

ОролтConstruction permitParties and their authoritiesҮр дүнWorks journal openSignatories on record
2

File the acts and the material documents as they are signed

Баримт бичиг

As each piece of work closes, file its act of concealed works or of intermediate acceptance of a responsible structure together with what backs it: the passports and certificates for the materials built in, the laboratory protocols, the geodetic survey schemes and the drawings marked with what was actually built. Keep a running list of what is still missing, by structure rather than by supplier.

Дэлгэцийн зураг, 2-р алхам: File the acts and the material documents as they are signed (Баримт бичиг, Close the object and get the commissioning permit (vvod v ekspluatatsiyu))
Баримт бичиг: File the acts and the material documents as they are signed

Яагаад: These documents are cheap to obtain in the week the work happens and close to impossible a year later, when the concrete supplier has changed its testing laboratory and the subcontractor has been paid in full. A list kept by structure also tells you which act is blocking the set, which a list kept by supplier never does.

ОролтConcealed work actsMaterial passports and protocolsҮр дүнActs filed by structureMissing documents named
3

Assemble the as-built set and check it against the list

Шалгалт

Assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 sets out, in the order the register lists it, and run the completeness check yourself before handing it to anybody: every act present, every act referencing documents that exist, every sheet signed by a person entitled to sign it, and the volumes numbered so a reader can find a structure without asking you.

Дэлгэцийн зураг, 3-р алхам: Assemble the as-built set and check it against the list (Шалгалт, Close the object and get the commissioning permit (vvod v ekspluatatsiyu))
Шалгалт: Assemble the as-built set and check it against the list

Яагаад: The supervision body checks the set against the same published list, so running that check first costs a day and moves every finding from their report into your worklist. A set handed over incomplete does not simply come back, it starts a round of correspondence that puts weeks between the last brick and the permit, and those weeks are usually financed.

ОролтActs filed by structureRequired composition listҮр дүнAs-built set assembledCompleteness report
4

Sign the acceptance of the finished object

Хүлээлгэн өгөх ба хаалт

Hand the object over to the customer on the acceptance act the contract names, with the outstanding items listed as remarks, each with an owner and a date, rather than as a sentence saying the works are complete. Reconcile the accepted scope against everything already accepted month by month so the total agrees with the sum of the acts.

Дэлгэцийн зураг, 4-р алхам: Sign the acceptance of the finished object (Хүлээлгэн өгөх ба хаалт, Close the object and get the commissioning permit (vvod v ekspluatatsiyu))
Хүлээлгэн өгөх ба хаалт: Sign the acceptance of the finished object

Яагаад: The acceptance date starts the guarantee period and usually the release of the retained amounts, so it is a commercial event and not a ceremony. Remarks recorded without an owner and a date are the ones that reappear at the end of the guarantee period as defects, by which time the argument is about who caused them rather than about who agreed to fix them.

ОролтAs-built set assembledContract scopeҮр дүнAcceptance act signedRemarks list with dates
5

Pass the final check of the state construction supervision

Шалгалт

Close out every finding from the checks carried out during construction first, then call the final check, present the journal and the as-built set against the design documentation, and take the conclusion of conformity. Where the object is subject to environmental supervision, treat that conclusion as its own thread with its own dates.

Дэлгэцийн зураг, 5-р алхам: Pass the final check of the state construction supervision (Шалгалт, Close the object and get the commissioning permit (vvod v ekspluatatsiyu))
Шалгалт: Pass the final check of the state construction supervision

Яагаад: The conclusion of conformity is the document without which the permit to commission cannot be applied for at all, and it is refused on unclosed findings from checks that happened a year earlier. Treating each interim finding as closed only when the supervision body says it is closed, rather than when the work was redone, is what keeps that list empty at the end.

ОролтAs-built set assembledPrior inspection findingsҮр дүнConclusion of conformityFindings cleared
6

Apply for the permit to commission

Зөвшөөрөл авахаар өгсөн баримт бичиг

Lodge the application with the body that issued the construction permit, attaching the documents article 55 of the Town Planning Code lists: the title and planning documents, the acceptance act, the conclusion of conformity, the documents on the utility connections, and the technical plan prepared by a cadastral engineer. Check the address and the technical parameters against the design before you send it.

Яагаад: The grounds for refusing this permit are listed in the code and are almost all documentary, which means almost all of them are avoidable by reading the same list first. A parameter that disagrees with the design, an area that disagrees with the technical plan, is a refusal, and the object cannot be used or registered until it is resolved.

ОролтConclusion of conformityTechnical planҮр дүнPermit to commissionObject on the cadastre
7

Start the guarantee period from the right date

Баталгаа ба согог арилгах хариуцлага

Register the guarantee period from the acceptance date, with the equipment warranties that run on their own shorter clocks recorded separately, and put the end date in front of the person who will still be responsible for the building when it arrives. Keep the as-built set where that person can reach it rather than in the contractor's archive.

Дэлгэцийн зураг, 7-р алхам: Start the guarantee period from the right date (Баталгаа ба согог арилгах хариуцлага, Close the object and get the commissioning permit (vvod v ekspluatatsiyu))
Баталгаа ба согог арилгах хариуцлага: Start the guarantee period from the right date

Яагаад: The contract guarantee and the longer statutory period for claims about the quality of a building are two different clocks, and the shorter one is the one everybody remembers. Registering both from the acceptance date is what makes a defect found in year four a question about the guarantee rather than a question about whether anybody kept the paperwork.

ОролтAcceptance act signedGuarantee termsҮр дүнGuarantee registerEnd date under watch
Модулиуд

Энэ тоглолтын модулиуд

Платформын 190 модулиас 7

The market this case is written for

Орос

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Хүлээлцэх ба амьдралын мөчлөг дахь бусад

Хүлээлцэх ба амьдралын мөчлөг

Хүлээлгэн өгч, ажлыг хаах

Ажлыг цэвэрхэн дуусгах: гэмтлийн жагсаалтыг тэгд хүргэ, бүх шалгалт тэнцсэн, нийцлийн зөрчил…

5 алхам14 минНээх