Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu)

Lleve el obshchiy zhurnal rabot desde el primer día, archive las actas y los documentos de material a medida que se firman, ensamble la ispolnitelnaya dokumentatsiya en la composición que enumera RD-11-02-2006, firme la recepción, pase la verificación final de la supervisión estatal de la construcción, y solicite el permiso de puesta en servicio bajo el artículo 55 del Código de Planeamiento Urbano.

7 pasos15 minContratista generalPromotor / clienteGestora de proyectos / construcciónConsultoría de costes / QS

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Open the works journal on the day the permit is issued

Control de obra

Start the obshchiy zhurnal rabot in the form the supervision rules prescribe, register it where the rules require, and record from the outset who may sign on behalf of the developer, the contractor, the designer's supervision and the construction control service, with the orders that appointed them. Keep the specialised journals for the works that need their own.

Captura de pantalla, paso 1: Open the works journal on the day the permit is issued (Control de obra, Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu))
Control de obra: Open the works journal on the day the permit is issued

Por que: The journal is the primary record the supervision body reads at the final check, and it is read for continuity as much as for content, so a gap in it is a gap in the evidence that the work was controlled at all. An entry signed by a person whose appointment is not on file is worth no more than an unsigned one, and that is discovered at the end, when nobody can go back and be appointed retroactively.

EntradaConstruction permitParties and their authoritiesResultadoWorks journal openSignatories on record
2

File the acts and the material documents as they are signed

Documentos

As each piece of work closes, file its act of concealed works or of intermediate acceptance of a responsible structure together with what backs it: the passports and certificates for the materials built in, the laboratory protocols, the geodetic survey schemes and the drawings marked with what was actually built. Keep a running list of what is still missing, by structure rather than by supplier.

Captura de pantalla, paso 2: File the acts and the material documents as they are signed (Documentos, Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu))
Documentos: File the acts and the material documents as they are signed

Por que: These documents are cheap to obtain in the week the work happens and close to impossible a year later, when the concrete supplier has changed its testing laboratory and the subcontractor has been paid in full. A list kept by structure also tells you which act is blocking the set, which a list kept by supplier never does.

EntradaConcealed work actsMaterial passports and protocolsResultadoActs filed by structureMissing documents named
3

Assemble the as-built set and check it against the list

Validación

Assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 sets out, in the order the register lists it, and run the completeness check yourself before handing it to anybody: every act present, every act referencing documents that exist, every sheet signed by a person entitled to sign it, and the volumes numbered so a reader can find a structure without asking you.

Captura de pantalla, paso 3: Assemble the as-built set and check it against the list (Validación, Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu))
Validación: Assemble the as-built set and check it against the list

Por que: The supervision body checks the set against the same published list, so running that check first costs a day and moves every finding from their report into your worklist. A set handed over incomplete does not simply come back, it starts a round of correspondence that puts weeks between the last brick and the permit, and those weeks are usually financed.

EntradaActs filed by structureRequired composition listResultadoAs-built set assembledCompleteness report
4

Sign the acceptance of the finished object

Entrega y cierre

Hand the object over to the customer on the acceptance act the contract names, with the outstanding items listed as remarks, each with an owner and a date, rather than as a sentence saying the works are complete. Reconcile the accepted scope against everything already accepted month by month so the total agrees with the sum of the acts.

Captura de pantalla, paso 4: Sign the acceptance of the finished object (Entrega y cierre, Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu))
Entrega y cierre: Sign the acceptance of the finished object

Por que: The acceptance date starts the guarantee period and usually the release of the retained amounts, so it is a commercial event and not a ceremony. Remarks recorded without an owner and a date are the ones that reappear at the end of the guarantee period as defects, by which time the argument is about who caused them rather than about who agreed to fix them.

EntradaAs-built set assembledContract scopeResultadoAcceptance act signedRemarks list with dates
5

Pass the final check of the state construction supervision

Inspecciones

Close out every finding from the checks carried out during construction first, then call the final check, present the journal and the as-built set against the design documentation, and take the conclusion of conformity. Where the object is subject to environmental supervision, treat that conclusion as its own thread with its own dates.

Captura de pantalla, paso 5: Pass the final check of the state construction supervision (Inspecciones, Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu))
Inspecciones: Pass the final check of the state construction supervision

Por que: The conclusion of conformity is the document without which the permit to commission cannot be applied for at all, and it is refused on unclosed findings from checks that happened a year earlier. Treating each interim finding as closed only when the supervision body says it is closed, rather than when the work was redone, is what keeps that list empty at the end.

EntradaAs-built set assembledPrior inspection findingsResultadoConclusion of conformityFindings cleared
6

Apply for the permit to commission

Presentaciones a Autoridad

Lodge the application with the body that issued the construction permit, attaching the documents article 55 of the Town Planning Code lists: the title and planning documents, the acceptance act, the conclusion of conformity, the documents on the utility connections, and the technical plan prepared by a cadastral engineer. Check the address and the technical parameters against the design before you send it.

Por que: The grounds for refusing this permit are listed in the code and are almost all documentary, which means almost all of them are avoidable by reading the same list first. A parameter that disagrees with the design, an area that disagrees with the technical plan, is a refusal, and the object cannot be used or registered until it is resolved.

EntradaConclusion of conformityTechnical planResultadoPermit to commissionObject on the cadastre
7

Start the guarantee period from the right date

Garantías y responsabilidad por defectos

Register the guarantee period from the acceptance date, with the equipment warranties that run on their own shorter clocks recorded separately, and put the end date in front of the person who will still be responsible for the building when it arrives. Keep the as-built set where that person can reach it rather than in the contractor's archive.

Captura de pantalla, paso 7: Start the guarantee period from the right date (Garantías y responsabilidad por defectos, Cierra la obra y obtén el permiso de puesta en servicio (vvod v ekspluatatsiyu))
Garantías y responsabilidad por defectos: Start the guarantee period from the right date

Por que: The contract guarantee and the longer statutory period for claims about the quality of a building are two different clocks, and the shorter one is the one everybody remembers. Registering both from the acceptance date is what makes a defect found in year four a question about the guarantee rather than a question about whether anybody kept the paperwork.

EntradaAcceptance act signedGuarantee termsResultadoGuarantee registerEnd date under watch
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Rusia

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • GESN/FER
  • KS-2 / KS-3

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.

Más en Entrega y ciclo de vida

Entrega y ciclo de vida

Entregar y cerrar la obra

Termine el proyecto sin cabos sueltos: lleve la lista de repasos a cero, confirme que todas…

5 pasos14 minAbrir
Entrega y ciclo de vida

Entrega as-built y O&M

Reúne el registro as-built, demuestra que el expediente de calidad no tiene lagunas y entreg…

3 pasos12 minAbrir