Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu)

Tieni l'obshchiy zhurnal rabot fin dal primo giorno, archivia gli atti e i documenti sui materiali man mano che vengono firmati, assembla l'ispolnitelnaya dokumentatsiya nella composizione che RD-11-02-2006 elenca, fai firmare l'accettazione, supera il controllo finale della state construction supervision e presenta domanda per il permesso di messa in esercizio ai sensi dell'articolo 55 del Codice urbanistico.

7 passaggi15 minImpresa generaleSviluppatore / committenteStudio di gestione progetti / cantieriConsulenza costi / QS

Come funziona, passo dopo passo

7 passi attraverso la piattaforma - cosa fare a ciascuno e perché conta.

1

Open the works journal on the day the permit is issued

Controllo del cantiere

Start the obshchiy zhurnal rabot in the form the supervision rules prescribe, register it where the rules require, and record from the outset who may sign on behalf of the developer, the contractor, the designer's supervision and the construction control service, with the orders that appointed them. Keep the specialised journals for the works that need their own.

Schermata, passaggio 1: Open the works journal on the day the permit is issued (Controllo del cantiere, Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu))
Controllo del cantiere: Open the works journal on the day the permit is issued

Perché: The journal is the primary record the supervision body reads at the final check, and it is read for continuity as much as for content, so a gap in it is a gap in the evidence that the work was controlled at all. An entry signed by a person whose appointment is not on file is worth no more than an unsigned one, and that is discovered at the end, when nobody can go back and be appointed retroactively.

In entrataConstruction permitParties and their authoritiesIn uscitaWorks journal openSignatories on record
2

File the acts and the material documents as they are signed

Documenti

As each piece of work closes, file its act of concealed works or of intermediate acceptance of a responsible structure together with what backs it: the passports and certificates for the materials built in, the laboratory protocols, the geodetic survey schemes and the drawings marked with what was actually built. Keep a running list of what is still missing, by structure rather than by supplier.

Schermata, passaggio 2: File the acts and the material documents as they are signed (Documenti, Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu))
Documenti: File the acts and the material documents as they are signed

Perché: These documents are cheap to obtain in the week the work happens and close to impossible a year later, when the concrete supplier has changed its testing laboratory and the subcontractor has been paid in full. A list kept by structure also tells you which act is blocking the set, which a list kept by supplier never does.

In entrataConcealed work actsMaterial passports and protocolsIn uscitaActs filed by structureMissing documents named
3

Assemble the as-built set and check it against the list

Validazione

Assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 sets out, in the order the register lists it, and run the completeness check yourself before handing it to anybody: every act present, every act referencing documents that exist, every sheet signed by a person entitled to sign it, and the volumes numbered so a reader can find a structure without asking you.

Schermata, passaggio 3: Assemble the as-built set and check it against the list (Validazione, Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu))
Validazione: Assemble the as-built set and check it against the list

Perché: The supervision body checks the set against the same published list, so running that check first costs a day and moves every finding from their report into your worklist. A set handed over incomplete does not simply come back, it starts a round of correspondence that puts weeks between the last brick and the permit, and those weeks are usually financed.

In entrataActs filed by structureRequired composition listIn uscitaAs-built set assembledCompleteness report
4

Sign the acceptance of the finished object

Consegna e chiusura

Hand the object over to the customer on the acceptance act the contract names, with the outstanding items listed as remarks, each with an owner and a date, rather than as a sentence saying the works are complete. Reconcile the accepted scope against everything already accepted month by month so the total agrees with the sum of the acts.

Schermata, passaggio 4: Sign the acceptance of the finished object (Consegna e chiusura, Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu))
Consegna e chiusura: Sign the acceptance of the finished object

Perché: The acceptance date starts the guarantee period and usually the release of the retained amounts, so it is a commercial event and not a ceremony. Remarks recorded without an owner and a date are the ones that reappear at the end of the guarantee period as defects, by which time the argument is about who caused them rather than about who agreed to fix them.

In entrataAs-built set assembledContract scopeIn uscitaAcceptance act signedRemarks list with dates
5

Pass the final check of the state construction supervision

Ispezioni

Close out every finding from the checks carried out during construction first, then call the final check, present the journal and the as-built set against the design documentation, and take the conclusion of conformity. Where the object is subject to environmental supervision, treat that conclusion as its own thread with its own dates.

Schermata, passaggio 5: Pass the final check of the state construction supervision (Ispezioni, Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu))
Ispezioni: Pass the final check of the state construction supervision

Perché: The conclusion of conformity is the document without which the permit to commission cannot be applied for at all, and it is refused on unclosed findings from checks that happened a year earlier. Treating each interim finding as closed only when the supervision body says it is closed, rather than when the work was redone, is what keeps that list empty at the end.

In entrataAs-built set assembledPrior inspection findingsIn uscitaConclusion of conformityFindings cleared
6

Apply for the permit to commission

Sottomissioni all'autorità

Lodge the application with the body that issued the construction permit, attaching the documents article 55 of the Town Planning Code lists: the title and planning documents, the acceptance act, the conclusion of conformity, the documents on the utility connections, and the technical plan prepared by a cadastral engineer. Check the address and the technical parameters against the design before you send it.

Perché: The grounds for refusing this permit are listed in the code and are almost all documentary, which means almost all of them are avoidable by reading the same list first. A parameter that disagrees with the design, an area that disagrees with the technical plan, is a refusal, and the object cannot be used or registered until it is resolved.

In entrataConclusion of conformityTechnical planIn uscitaPermit to commissionObject on the cadastre
7

Start the guarantee period from the right date

Garanzie e responsabilità per difetti

Register the guarantee period from the acceptance date, with the equipment warranties that run on their own shorter clocks recorded separately, and put the end date in front of the person who will still be responsible for the building when it arrives. Keep the as-built set where that person can reach it rather than in the contractor's archive.

Schermata, passaggio 7: Start the guarantee period from the right date (Garanzie e responsabilità per difetti, Chiudere l’opera e ottenere l’autorizzazione all’esercizio (vvod v ekspluatatsiyu))
Garanzie e responsabilità per difetti: Start the guarantee period from the right date

Perché: The contract guarantee and the longer statutory period for claims about the quality of a building are two different clocks, and the shorter one is the one everybody remembers. Registering both from the acceptance date is what makes a defect found in year four a question about the guarantee rather than a question about whether anybody kept the paperwork.

In entrataAcceptance act signedGuarantee termsIn uscitaGuarantee registerEnd date under watch
Moduli

Moduli di questo playbook

7 / 190 moduli della piattaforma

The market this case is written for

Russia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Altro in Consegna e ciclo di vita

Consegna e ciclo di vita

Consegnare e chiudere il progetto

Concludi il progetto in modo pulito: porta la punch list a zero, verifica che ogni ispezione…

5 passaggi14 minApri
Consegna e ciclo di vita

Consegna as-built e O&M

Metti insieme il fascicolo as-built, dimostra che il fascicolo qualità non ha lacune, poi em…

3 passaggi12 minApri