現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する

初日から obshchiy zhurnal rabot を維持し、署名され次第、証書と資材文書を保管し、RD-11-02-2006 が定める構成で ispolnitelnaya dokumentatsiya をまとめ、引渡しに署名させ、state construction supervision の最終検査に合格し、都市計画法第55条に基づき供用許可を申請する。

7ステップ15 分総合建設会社デベロッパー / 発注者プロジェクト / 施工管理会社コストコンサルティング会社 / 積算事務所

仕組みをステップごとに

プラットフォーム全体で7ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Open the works journal on the day the permit is issued

施工管理

Start the obshchiy zhurnal rabot in the form the supervision rules prescribe, register it where the rules require, and record from the outset who may sign on behalf of the developer, the contractor, the designer's supervision and the construction control service, with the orders that appointed them. Keep the specialised journals for the works that need their own.

スクリーンショット、ステップ 1: Open the works journal on the day the permit is issued (施工管理, 現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する)
施工管理: Open the works journal on the day the permit is issued

理由: The journal is the primary record the supervision body reads at the final check, and it is read for continuity as much as for content, so a gap in it is a gap in the evidence that the work was controlled at all. An entry signed by a person whose appointment is not on file is worth no more than an unsigned one, and that is discovered at the end, when nobody can go back and be appointed retroactively.

入力Construction permitParties and their authorities出力Works journal openSignatories on record
2

File the acts and the material documents as they are signed

文書

As each piece of work closes, file its act of concealed works or of intermediate acceptance of a responsible structure together with what backs it: the passports and certificates for the materials built in, the laboratory protocols, the geodetic survey schemes and the drawings marked with what was actually built. Keep a running list of what is still missing, by structure rather than by supplier.

スクリーンショット、ステップ 2: File the acts and the material documents as they are signed (文書, 現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する)
文書: File the acts and the material documents as they are signed

理由: These documents are cheap to obtain in the week the work happens and close to impossible a year later, when the concrete supplier has changed its testing laboratory and the subcontractor has been paid in full. A list kept by structure also tells you which act is blocking the set, which a list kept by supplier never does.

入力Concealed work actsMaterial passports and protocols出力Acts filed by structureMissing documents named
3

Assemble the as-built set and check it against the list

検証

Assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 sets out, in the order the register lists it, and run the completeness check yourself before handing it to anybody: every act present, every act referencing documents that exist, every sheet signed by a person entitled to sign it, and the volumes numbered so a reader can find a structure without asking you.

スクリーンショット、ステップ 3: Assemble the as-built set and check it against the list (検証, 現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する)
検証: Assemble the as-built set and check it against the list

理由: The supervision body checks the set against the same published list, so running that check first costs a day and moves every finding from their report into your worklist. A set handed over incomplete does not simply come back, it starts a round of correspondence that puts weeks between the last brick and the permit, and those weeks are usually financed.

入力Acts filed by structureRequired composition list出力As-built set assembledCompleteness report
4

Sign the acceptance of the finished object

引き渡しとクローズアウト

Hand the object over to the customer on the acceptance act the contract names, with the outstanding items listed as remarks, each with an owner and a date, rather than as a sentence saying the works are complete. Reconcile the accepted scope against everything already accepted month by month so the total agrees with the sum of the acts.

スクリーンショット、ステップ 4: Sign the acceptance of the finished object (引き渡しとクローズアウト, 現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する)
引き渡しとクローズアウト: Sign the acceptance of the finished object

理由: The acceptance date starts the guarantee period and usually the release of the retained amounts, so it is a commercial event and not a ceremony. Remarks recorded without an owner and a date are the ones that reappear at the end of the guarantee period as defects, by which time the argument is about who caused them rather than about who agreed to fix them.

入力As-built set assembledContract scope出力Acceptance act signedRemarks list with dates
5

Pass the final check of the state construction supervision

検査

Close out every finding from the checks carried out during construction first, then call the final check, present the journal and the as-built set against the design documentation, and take the conclusion of conformity. Where the object is subject to environmental supervision, treat that conclusion as its own thread with its own dates.

スクリーンショット、ステップ 5: Pass the final check of the state construction supervision (検査, 現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する)
検査: Pass the final check of the state construction supervision

理由: The conclusion of conformity is the document without which the permit to commission cannot be applied for at all, and it is refused on unclosed findings from checks that happened a year earlier. Treating each interim finding as closed only when the supervision body says it is closed, rather than when the work was redone, is what keeps that list empty at the end.

入力As-built set assembledPrior inspection findings出力Conclusion of conformityFindings cleared
6

Apply for the permit to commission

当局への提出

Lodge the application with the body that issued the construction permit, attaching the documents article 55 of the Town Planning Code lists: the title and planning documents, the acceptance act, the conclusion of conformity, the documents on the utility connections, and the technical plan prepared by a cadastral engineer. Check the address and the technical parameters against the design before you send it.

理由: The grounds for refusing this permit are listed in the code and are almost all documentary, which means almost all of them are avoidable by reading the same list first. A parameter that disagrees with the design, an area that disagrees with the technical plan, is a refusal, and the object cannot be used or registered until it is resolved.

入力Conclusion of conformityTechnical plan出力Permit to commissionObject on the cadastre
7

Start the guarantee period from the right date

保証と瑕疵担保

Register the guarantee period from the acceptance date, with the equipment warranties that run on their own shorter clocks recorded separately, and put the end date in front of the person who will still be responsible for the building when it arrives. Keep the as-built set where that person can reach it rather than in the contractor's archive.

スクリーンショット、ステップ 7: Start the guarantee period from the right date (保証と瑕疵担保, 現場を締めくくり、使用開始許可 (vvod v ekspluatatsiyu) を取得する)
保証と瑕疵担保: Start the guarantee period from the right date

理由: The contract guarantee and the longer statutory period for claims about the quality of a building are two different clocks, and the shorter one is the one everybody remembers. Registering both from the acceptance date is what makes a defect found in year four a question about the guarantee rather than a question about whether anybody kept the paperwork.

入力Acceptance act signedGuarantee terms出力Guarantee registerEnd date under watch
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 7 個

The market this case is written for

ロシア

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

引き渡しとライフサイクルの他のケース

引き渡しとライフサイクル

引き渡しと竣工処理を行う

案件をきれいに終える。手直しリストをゼロにし、すべての検査が合格し未解決の不適合がないことを確認し、竣工図書一式をまとめ、署名済みの引き渡しを発行する。

5ステップ14 分開く
引き渡しとライフサイクル

竣工図と維持管理マニュアルの引渡し

竣工記録をまとめ、品質ファイルに漏れがないことを確認したうえで、運営者が実際に建物を管理・運用できる維持管理マニュアルを発行します。

3ステップ12 分開く
引き渡しとライフサイクル

引き渡し受入検査を実施する

施主と共に完成した工事を巡回し、受入基準に照らして合否を記録し、不具合リストをゼロまで解消し、清算された引き渡し受入を発行する。

3ステップ11 分開く