केस / हैंडओवर और जीवनचक्र
हैंडओवर और जीवनचक्र

ऑब्जेक्ट बंद करें और vvod v ekspluatatsiyu लें

पहले दिन से obshchiy zhurnal rabot रखें, दस्तावेज़ और सामग्री के काग़ज़ हस्ताक्षर होते ही फ़ाइल करें, RD-11-02-2006 द्वारा सूचीबद्ध संरचना में ispolnitelnaya dokumentatsiya इकट्ठा करें, स्वीकृति पर हस्ताक्षर करवाएं, state construction supervision की अंतिम जांच पास करें, और टाउन प्लानिंग कोड की धारा 55 के तहत कमीशनिंग की अनुमति के लिए आवेदन करें।

7 चरण15 मिनटमुख्य ठेकेदारडेवलपर / क्लाइंटप्रोजेक्ट / निर्माण प्रबंधन फर्मलागत परामर्श / QS फर्म

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 7 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Open the works journal on the day the permit is issued

निर्माण नियंत्रण

Start the obshchiy zhurnal rabot in the form the supervision rules prescribe, register it where the rules require, and record from the outset who may sign on behalf of the developer, the contractor, the designer's supervision and the construction control service, with the orders that appointed them. Keep the specialised journals for the works that need their own.

क्यों: The journal is the primary record the supervision body reads at the final check, and it is read for continuity as much as for content, so a gap in it is a gap in the evidence that the work was controlled at all. An entry signed by a person whose appointment is not on file is worth no more than an unsigned one, and that is discovered at the end, when nobody can go back and be appointed retroactively.

इनपुटConstruction permitParties and their authoritiesपरिणामWorks journal openSignatories on record
2

File the acts and the material documents as they are signed

दस्तावेज़

As each piece of work closes, file its act of concealed works or of intermediate acceptance of a responsible structure together with what backs it: the passports and certificates for the materials built in, the laboratory protocols, the geodetic survey schemes and the drawings marked with what was actually built. Keep a running list of what is still missing, by structure rather than by supplier.

क्यों: These documents are cheap to obtain in the week the work happens and close to impossible a year later, when the concrete supplier has changed its testing laboratory and the subcontractor has been paid in full. A list kept by structure also tells you which act is blocking the set, which a list kept by supplier never does.

इनपुटConcealed work actsMaterial passports and protocolsपरिणामActs filed by structureMissing documents named
3

Assemble the as-built set and check it against the list

सत्यापन

Assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 sets out, in the order the register lists it, and run the completeness check yourself before handing it to anybody: every act present, every act referencing documents that exist, every sheet signed by a person entitled to sign it, and the volumes numbered so a reader can find a structure without asking you.

क्यों: The supervision body checks the set against the same published list, so running that check first costs a day and moves every finding from their report into your worklist. A set handed over incomplete does not simply come back, it starts a round of correspondence that puts weeks between the last brick and the permit, and those weeks are usually financed.

इनपुटActs filed by structureRequired composition listपरिणामAs-built set assembledCompleteness report
4

Sign the acceptance of the finished object

हैंडओवर और क्लोज़आउट

Hand the object over to the customer on the acceptance act the contract names, with the outstanding items listed as remarks, each with an owner and a date, rather than as a sentence saying the works are complete. Reconcile the accepted scope against everything already accepted month by month so the total agrees with the sum of the acts.

क्यों: The acceptance date starts the guarantee period and usually the release of the retained amounts, so it is a commercial event and not a ceremony. Remarks recorded without an owner and a date are the ones that reappear at the end of the guarantee period as defects, by which time the argument is about who caused them rather than about who agreed to fix them.

इनपुटAs-built set assembledContract scopeपरिणामAcceptance act signedRemarks list with dates
5

Pass the final check of the state construction supervision

निरीक्षण

Close out every finding from the checks carried out during construction first, then call the final check, present the journal and the as-built set against the design documentation, and take the conclusion of conformity. Where the object is subject to environmental supervision, treat that conclusion as its own thread with its own dates.

क्यों: The conclusion of conformity is the document without which the permit to commission cannot be applied for at all, and it is refused on unclosed findings from checks that happened a year earlier. Treating each interim finding as closed only when the supervision body says it is closed, rather than when the work was redone, is what keeps that list empty at the end.

इनपुटAs-built set assembledPrior inspection findingsपरिणामConclusion of conformityFindings cleared
6

Apply for the permit to commission

प्राधिकरण प्रस्तुतियाँ

Lodge the application with the body that issued the construction permit, attaching the documents article 55 of the Town Planning Code lists: the title and planning documents, the acceptance act, the conclusion of conformity, the documents on the utility connections, and the technical plan prepared by a cadastral engineer. Check the address and the technical parameters against the design before you send it.

क्यों: The grounds for refusing this permit are listed in the code and are almost all documentary, which means almost all of them are avoidable by reading the same list first. A parameter that disagrees with the design, an area that disagrees with the technical plan, is a refusal, and the object cannot be used or registered until it is resolved.

इनपुटConclusion of conformityTechnical planपरिणामPermit to commissionObject on the cadastre
7

Start the guarantee period from the right date

वारंटी और दोष दायित्व

Register the guarantee period from the acceptance date, with the equipment warranties that run on their own shorter clocks recorded separately, and put the end date in front of the person who will still be responsible for the building when it arrives. Keep the as-built set where that person can reach it rather than in the contractor's archive.

क्यों: The contract guarantee and the longer statutory period for claims about the quality of a building are two different clocks, and the shorter one is the one everybody remembers. Registering both from the acceptance date is what makes a defect found in year four a question about the guarantee rather than a question about whether anybody kept the paperwork.

इनपुटAcceptance act signedGuarantee termsपरिणामGuarantee registerEnd date under watch
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 7 मॉड्यूल

The market this case is written for

रूस

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

हैंडओवर और जीवनचक्र में और देखें

हैंडओवर और जीवनचक्र

एज-बिल्ट और O&M हैंडओवर

एज-बिल्ट रिकॉर्ड इकट्ठा करें, साबित करें कि क्वालिटी फाइल में कोई कमी नहीं है, फिर एक ऑपरेशन…

3 चरण12 मिनटखोलें
हैंडओवर और जीवनचक्र

हैंडओवर स्वीकृति निरीक्षण करें

क्लाइंट के साथ पूर्ण किए गए काम का निरीक्षण करें, स्वीकृति मानदंडों के अनुसार क्या पास हुआ औ…

3 चरण11 मिनटखोलें