Casos / Entrega e ciclo de vida
Entrega e ciclo de vida

Encerre a obra e obtenha o vvod v ekspluatatsiyu

Mantenha o obshchiy zhurnal rabot desde o primeiro dia, arquive os actos e os documentos de material à medida que são assinados, monte a ispolnitelnaya dokumentatsiya na composição que a RD-11-02-2006 lista, assine a aceitação, passe a verificação final da fiscalização estatal de obra e requeira a licença de utilização ao abrigo do artigo 55.º do Código de Urbanismo.

7 etapas15 minEmpreiteiro geralPromotor / clienteGabinete de gestão de projetos / obrasConsultoria de custos / QS

Como funciona, passo a passo

7 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Open the works journal on the day the permit is issued

Controlo de obra

Start the obshchiy zhurnal rabot in the form the supervision rules prescribe, register it where the rules require, and record from the outset who may sign on behalf of the developer, the contractor, the designer's supervision and the construction control service, with the orders that appointed them. Keep the specialised journals for the works that need their own.

Por quê: The journal is the primary record the supervision body reads at the final check, and it is read for continuity as much as for content, so a gap in it is a gap in the evidence that the work was controlled at all. An entry signed by a person whose appointment is not on file is worth no more than an unsigned one, and that is discovered at the end, when nobody can go back and be appointed retroactively.

EntradaConstruction permitParties and their authoritiesResultadoWorks journal openSignatories on record
2

File the acts and the material documents as they are signed

Documentos

As each piece of work closes, file its act of concealed works or of intermediate acceptance of a responsible structure together with what backs it: the passports and certificates for the materials built in, the laboratory protocols, the geodetic survey schemes and the drawings marked with what was actually built. Keep a running list of what is still missing, by structure rather than by supplier.

Por quê: These documents are cheap to obtain in the week the work happens and close to impossible a year later, when the concrete supplier has changed its testing laboratory and the subcontractor has been paid in full. A list kept by structure also tells you which act is blocking the set, which a list kept by supplier never does.

EntradaConcealed work actsMaterial passports and protocolsResultadoActs filed by structureMissing documents named
3

Assemble the as-built set and check it against the list

Validação

Assemble the ispolnitelnaya dokumentatsiya in the composition RD-11-02-2006 sets out, in the order the register lists it, and run the completeness check yourself before handing it to anybody: every act present, every act referencing documents that exist, every sheet signed by a person entitled to sign it, and the volumes numbered so a reader can find a structure without asking you.

Por quê: The supervision body checks the set against the same published list, so running that check first costs a day and moves every finding from their report into your worklist. A set handed over incomplete does not simply come back, it starts a round of correspondence that puts weeks between the last brick and the permit, and those weeks are usually financed.

EntradaActs filed by structureRequired composition listResultadoAs-built set assembledCompleteness report
4

Sign the acceptance of the finished object

Entrega e Encerramento

Hand the object over to the customer on the acceptance act the contract names, with the outstanding items listed as remarks, each with an owner and a date, rather than as a sentence saying the works are complete. Reconcile the accepted scope against everything already accepted month by month so the total agrees with the sum of the acts.

Por quê: The acceptance date starts the guarantee period and usually the release of the retained amounts, so it is a commercial event and not a ceremony. Remarks recorded without an owner and a date are the ones that reappear at the end of the guarantee period as defects, by which time the argument is about who caused them rather than about who agreed to fix them.

EntradaAs-built set assembledContract scopeResultadoAcceptance act signedRemarks list with dates
5

Pass the final check of the state construction supervision

Inspeções

Close out every finding from the checks carried out during construction first, then call the final check, present the journal and the as-built set against the design documentation, and take the conclusion of conformity. Where the object is subject to environmental supervision, treat that conclusion as its own thread with its own dates.

Por quê: The conclusion of conformity is the document without which the permit to commission cannot be applied for at all, and it is refused on unclosed findings from checks that happened a year earlier. Treating each interim finding as closed only when the supervision body says it is closed, rather than when the work was redone, is what keeps that list empty at the end.

EntradaAs-built set assembledPrior inspection findingsResultadoConclusion of conformityFindings cleared
6

Apply for the permit to commission

Submissões à Autoridade

Lodge the application with the body that issued the construction permit, attaching the documents article 55 of the Town Planning Code lists: the title and planning documents, the acceptance act, the conclusion of conformity, the documents on the utility connections, and the technical plan prepared by a cadastral engineer. Check the address and the technical parameters against the design before you send it.

Por quê: The grounds for refusing this permit are listed in the code and are almost all documentary, which means almost all of them are avoidable by reading the same list first. A parameter that disagrees with the design, an area that disagrees with the technical plan, is a refusal, and the object cannot be used or registered until it is resolved.

EntradaConclusion of conformityTechnical planResultadoPermit to commissionObject on the cadastre
7

Start the guarantee period from the right date

Garantias e responsabilidade por defeitos

Register the guarantee period from the acceptance date, with the equipment warranties that run on their own shorter clocks recorded separately, and put the end date in front of the person who will still be responsible for the building when it arrives. Keep the as-built set where that person can reach it rather than in the contractor's archive.

Por quê: The contract guarantee and the longer statutory period for claims about the quality of a building are two different clocks, and the shorter one is the one everybody remembers. Registering both from the acceptance date is what makes a defect found in year four a question about the guarantee rather than a question about whether anybody kept the paperwork.

EntradaAcceptance act signedGuarantee termsResultadoGuarantee registerEnd date under watch
Módulos

Módulos deste playbook

7 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Rússia

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • GESN/FER
  • KS-2 / KS-3

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Entrega e ciclo de vida

Entrega e ciclo de vida

Entregar e encerrar a obra

Termine a obra de forma limpa: leve a lista de pendências a zero, confirme que todas as insp…