Vakalar / Ticari ve sözleşmeler
Ticari ve sözleşmeler

Wafi kapsamında off plan sat ve escrow account'tan çek

Herhangi bir birim pazarlanmadan önce projeyi lisanslayın, çekimin ölçüleceği cost plan'ı kaydedin, her alıcı ödemesini escrow account'a yönlendirin, ihtiyaca göre değil onaylanmış ilerlemeye göre çekin, düzenleyiciye kendi takvimine göre rapor verin ve hesabı yalnızca birimler teslim edildiğinde kapatın.

7 adım15 dkGeliştirici / işverenMaliyet danışmanlığı / QSProje / inşaat yönetim bürosuAna yüklenici

Nasıl çalışır, adım adım

Platform genelinde 7 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Licence the project before you market a single unit

Gayrimenkul Geliştirme

Register the development and apply for the off-plan licence with everything the programme asks for: clear title to the land, the approved design and the building permit, an appointed contractor and engineering consultant who both hold current classification, the technical and financial study, and the escrow arrangement with an accredited bank. Record the licence number and its validity against the project.

Neden: Marketing or taking a deposit before the licence is issued is unlicensed selling, not an early start, and it is the one irregularity a buyer can point at years later to unwind their contract. The licence conditions also fix who certifies progress for the rest of the project, so the appointments made here decide who signs the drawdown every month.

GirdiLand titleApproved design and permitÇıktıOff-plan licenceLicensed parties on record
2

Put the cost plan the drawdown is measured against on record

Keşif Özeti

Build the project cost plan the escrow will be drawn against: construction by element, consultancy, authority and utility charges, marketing and the finance cost, each with the month it is expected to fall in. Keep the construction section reconciled to the contract sum so a certified percentage of work maps onto a figure without a second calculation.

Neden: The escrow releases against progress on a budget it already holds, so a cost plan that does not match the contract turns every drawdown into a reconciliation exercise with the bank. The expenditure curve is also the thing that tells you, months in advance, whether sales are running ahead of construction or behind it, which is the question the whole regime exists to answer.

GirdiApproved designConstruction contractÇıktıCost plan by elementExpenditure curve
3

Route every buyer payment into the escrow account

Finans

Sell only against the licensed unit schedule, and take every instalment into the project escrow account rather than into a company account, including the reservation amount. Keep the ledger by unit and by buyer so the balance held can be read against the units sold at any moment, and keep the developer's own contribution as its own line.

Neden: The account is dedicated to this project by law, which is what protects a buyer from the developer's other troubles, and money that passed through a company account first has left that protection whatever happens next. A ledger kept by unit is also the only way to answer a cancellation quickly, because a refund is calculated on what that buyer actually paid in.

GirdiSigned unit contractsEscrow accountÇıktıEscrow ledgerBuyer payments received
4

Measure the period and have the consultant certify it

İlerleme

Measure what was actually built in the period against the cost plan, element by element, and have the appointed engineering consultant certify the completion percentage in a progress report with photographs and the measured backup behind it. Show the period movement and the cumulative figure separately.

Neden: The percentage in that report is the only number that moves money out of the account, so a report written from a site walk rather than from measurement is a cash flow forecast built on an opinion. Showing the movement apart from the cumulative figure is what lets the bank check the month in minutes instead of recalculating the whole project.

GirdiWork done on siteCost plan by elementÇıktıCertified completion percentageConsultant progress report
5

Draw against certified progress, never against need

Ödemeler

Lodge the release request with the certified percentage, the contractor's invoice for the same period and the supporting measurement, and take out only what that certification supports. Record what was released, what remains held and the portion the regime keeps back until the units are handed over.

Neden: The escrow agent is checking the request against the certificate, not against the developer's payment run, so a request that runs ahead of the certified work is refused and delays the money that was actually earned along with it. Reading the held balance every month is also the earliest warning that sales money is being consumed faster than the building is rising.

GirdiConsultant progress reportContractor invoicesÇıktıReleased amountBalance still held
6

Report to the regulator on the schedule the licence sets

Resmi Makam Başvuruları

File the periodic report the licence requires: physical progress against the programme, units sold, amounts received and released, and any change to the appointed contractor or consultant. Keep each filing with the period it covers and put the next date under a reminder.

Neden: The licence is a continuing permission rather than a one-off approval, and the reporting is how it stays alive. A development that stops reporting is a development the regulator will look at, and the sanction that hurts is a suspension of further sales, which stops the inflow while the construction obligations carry on unchanged.

GirdiCertified completion percentageEscrow ledgerÇıktıReport filedLicence kept in good standing
7

Hand the units over, then close the account

Teslim ve Kapanış

Take the completion and occupancy documents, clear the snag list per unit, hand over against a signed record for each buyer and register the title in their name. Only then release the retained balance and ask the escrow agent to close the account, with the final statement kept in the project file.

Neden: The held-back portion is the buyers' last piece of leverage and the developer's last incentive to finish properly, so releasing it before the handovers are documented removes both at once. A closing statement that reconciles every riyal received against every riyal released is also what answers a complaint about this project three years from now, when nobody involved is still at the company.

GirdiCompletion certificateBalance still heldÇıktıUnits handed overEscrow account closed
Modüller

Bu senaryodaki modüller

6 / 190 platform modülü

The market this case is written for

Suudi Arabistan

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Ticari ve sözleşmeler kategorisinde daha fazlası

Ticari ve sözleşmeler

Bir taşeron paketini yürütün

Bir imalat paketini bir taşerona verin, ödeme tablosu ve hakediş kesintisiyle birlikte sözle…

3 adım11 dk
Ticari ve sözleşmeler

Hakediş talebi ve mutabakat

Bu dönem yerinde yapılan işi sözleşmeye göre değerlendirin, kanıtlarını arkasına koyarak hak…

3 adım12 dk