Wafi에 따라 off plan으로 판매하고 escrow account에서 인출하기

한 유닛이라도 판매되기 전에 프로젝트를 인가받고, 인출의 기준이 될 cost plan을 기록으로 남기고, 모든 구매자 대금을 escrow account로 흘려보내고, 필요가 아니라 인증된 진척도에 따라 인출하고, 규제기관에 그 일정대로 보고하고, 유닛이 인도된 뒤에야 계좌를 닫는다.

7단계15 분시행사 / 발주처원가 컨설팅 / 적산 업체PM/CM 업체종합건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Licence the project before you market a single unit

부동산 개발

Register the development and apply for the off-plan licence with everything the programme asks for: clear title to the land, the approved design and the building permit, an appointed contractor and engineering consultant who both hold current classification, the technical and financial study, and the escrow arrangement with an accredited bank. Record the licence number and its validity against the project.

이유: Marketing or taking a deposit before the licence is issued is unlicensed selling, not an early start, and it is the one irregularity a buyer can point at years later to unwind their contract. The licence conditions also fix who certifies progress for the rest of the project, so the appointments made here decide who signs the drawdown every month.

입력Land titleApproved design and permit결과Off-plan licenceLicensed parties on record
2

Put the cost plan the drawdown is measured against on record

내역서

Build the project cost plan the escrow will be drawn against: construction by element, consultancy, authority and utility charges, marketing and the finance cost, each with the month it is expected to fall in. Keep the construction section reconciled to the contract sum so a certified percentage of work maps onto a figure without a second calculation.

이유: The escrow releases against progress on a budget it already holds, so a cost plan that does not match the contract turns every drawdown into a reconciliation exercise with the bank. The expenditure curve is also the thing that tells you, months in advance, whether sales are running ahead of construction or behind it, which is the question the whole regime exists to answer.

입력Approved designConstruction contract결과Cost plan by elementExpenditure curve
3

Route every buyer payment into the escrow account

재무

Sell only against the licensed unit schedule, and take every instalment into the project escrow account rather than into a company account, including the reservation amount. Keep the ledger by unit and by buyer so the balance held can be read against the units sold at any moment, and keep the developer's own contribution as its own line.

이유: The account is dedicated to this project by law, which is what protects a buyer from the developer's other troubles, and money that passed through a company account first has left that protection whatever happens next. A ledger kept by unit is also the only way to answer a cancellation quickly, because a refund is calculated on what that buyer actually paid in.

입력Signed unit contractsEscrow account결과Escrow ledgerBuyer payments received
4

Measure the period and have the consultant certify it

진척

Measure what was actually built in the period against the cost plan, element by element, and have the appointed engineering consultant certify the completion percentage in a progress report with photographs and the measured backup behind it. Show the period movement and the cumulative figure separately.

이유: The percentage in that report is the only number that moves money out of the account, so a report written from a site walk rather than from measurement is a cash flow forecast built on an opinion. Showing the movement apart from the cumulative figure is what lets the bank check the month in minutes instead of recalculating the whole project.

입력Work done on siteCost plan by element결과Certified completion percentageConsultant progress report
5

Draw against certified progress, never against need

지불

Lodge the release request with the certified percentage, the contractor's invoice for the same period and the supporting measurement, and take out only what that certification supports. Record what was released, what remains held and the portion the regime keeps back until the units are handed over.

이유: The escrow agent is checking the request against the certificate, not against the developer's payment run, so a request that runs ahead of the certified work is refused and delays the money that was actually earned along with it. Reading the held balance every month is also the earliest warning that sales money is being consumed faster than the building is rising.

입력Consultant progress reportContractor invoices결과Released amountBalance still held
6

Report to the regulator on the schedule the licence sets

권한 제출

File the periodic report the licence requires: physical progress against the programme, units sold, amounts received and released, and any change to the appointed contractor or consultant. Keep each filing with the period it covers and put the next date under a reminder.

이유: The licence is a continuing permission rather than a one-off approval, and the reporting is how it stays alive. A development that stops reporting is a development the regulator will look at, and the sanction that hurts is a suspension of further sales, which stops the inflow while the construction obligations carry on unchanged.

입력Certified completion percentageEscrow ledger결과Report filedLicence kept in good standing
7

Hand the units over, then close the account

인계 및 준공 정산

Take the completion and occupancy documents, clear the snag list per unit, hand over against a signed record for each buyer and register the title in their name. Only then release the retained balance and ask the escrow agent to close the account, with the final statement kept in the project file.

이유: The held-back portion is the buyers' last piece of leverage and the developer's last incentive to finish properly, so releasing it before the handovers are documented removes both at once. A closing statement that reconciles every riyal received against every riyal released is also what answers a complaint about this project three years from now, when nobody involved is still at the company.

입력Completion certificateBalance still held결과Units handed overEscrow account closed
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6

The market this case is written for

사우디아라비아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기