Check SRO membership before anyone starts work

Write down what each work package legally requires, check the membership and the level of responsibility of every firm you intend to use, make it a condition of award, file the register extract and watch the dates that lapse.

6 steps11 minGeneral contractorDeveloper / clientProject / construction management firm

How it works, step by step

6 steps across the platform - what you do at each one, and why it matters.

1

Say what each discipline on the job actually requires

Credentials

For each discipline, record what the firm or the individual doing it must hold: SRO membership in construction, in design or in survey, and any separate authorisation the work itself carries, such as work on a cultural heritage object or on a hazardous production facility. Mark the requirement blocking where a gap has to stop the work, and set the grace period you are willing to allow.

Why: The requirement belongs to the work rather than to the supplier, and writing it down first is what makes every later check mechanical instead of a judgement call. Blocking is the decision that matters, because a requirement that is only a note stops nobody. It also surfaces the work that needs no membership at all, since the Town Planning Code exempts contracts below a stated value and certain categories of work, and demanding it there costs you bidders for nothing.

InDisciplines on the jobFirms or people who hold itOutBlocking requirement per disciplineWork that needs none
2

Prequalify every firm against its own register extract

Subcontractor Directory

For each firm, work through the prequalification questionnaire with the register extract in front of you: which SRO it belongs to, its membership number, when it joined, and which level of responsibility it holds against the value of the work you mean to give it. Attach the extract, and block the firm with the reason written down where the level does not cover that work. Read it from the extract, not from the scan on the firm's letterhead.

Subcontractor Directory screen in OpenConstructionERP: Prequalify every firm against its own register extract (Check SRO membership before anyone starts work)
Subcontractor Directory: Prequalify every firm against its own register extract

Why: Membership is a live status rather than a certificate: it can be suspended or terminated while the firm goes on sending the same scanned page. The level is the part most often wrong, because a firm that is genuinely a member is very often a member at a level below the contract it is about to sign.

InFirms under considerationRegister extractOutPrequalification decidedFirms blocked with a reason
3

Make it a condition of award, not a question afterwards

Procurement

Attach the requirement to the package in procurement so that an award cannot be made to a firm that does not meet it, and ask for the register extract as part of the offer rather than as something to be produced once the work is under way.

Procurement screen in OpenConstructionERP: Make it a condition of award, not a question afterwards (Check SRO membership before anyone starts work)
Procurement: Make it a condition of award, not a question afterwards

Why: Checked after award this only ever produces bad options: re-tender and lose the programme, or carry on with a contractor whose work you may not be able to hand over. Checked as a condition of award it costs one field on the offer form.

InRequirement per packageOffers receivedOutEligible biddersAward blocked without cover
4

Keep the register extract that proves it

Documents

File the register extract for each firm together with the date it was taken, alongside the insurance and any separate authorisation, and keep it attached to the work package rather than in a general supplier folder.

Documents screen in OpenConstructionERP: Keep the register extract that proves it (Check SRO membership before anyone starts work)
Documents: Keep the register extract that proves it

Why: When the client's technical supervision or an inspection asks who was entitled to do this work, the answer has to be a document dated before the work started. An extract pulled after the question is asked proves only that the firm is a member today, which is a much weaker statement and usually the wrong one.

InRegister extract with its dateInsurance and permitsOutEvidence on the packageProof dated before the work
5

Write the membership into the subcontract as a standing duty

Contracts

Put the requirement in the subcontract itself: membership held for the whole term and not only at signature, notice to you within a fixed number of days if it is suspended or terminated, and the right to suspend the work and withhold payment until it is restored.

Contracts screen in OpenConstructionERP: Write the membership into the subcontract as a standing duty (Check SRO membership before anyone starts work)
Contracts: Write the membership into the subcontract as a standing duty

Why: Membership lapses quietly and the SRO writes to its member, not to you. Checked once at award, it is a snapshot; written into the contract, it is a duty that runs for the whole term and gives you something to act on. A firm that was covered at award and is not covered in month eight goes on signing acts the client can later refuse, and that is normally found while the handover package is being checked.

InFirm cleared for awardSubcontract clause templateOutMembership as a standing obligationDuty to report a lapse
6

Read who may not work today, and what lapses next

Credentials

Read the compliance answer across the project: holders a blocking requirement stops outright, holders still inside their grace period, credentials expiring soon, and requirements that bind nobody at all because no holder on the register matches them. Clear that list before those firms reach the site.

Why: This is the rare compliance question that is arithmetic rather than judgement, so it belongs in a report read on a date and not in somebody's habit. Expiry is worked out from the dates each time it is read rather than from a status somebody typed once, which is the only version of this check that survives a firm renewing late. A requirement binding nobody is the other half of the finding: the work is being done by somebody the requirement never reached.

InEvery firm and person on siteRequirements that bind themOutWho may not work todayRequirements binding nobody
Modules

Modules in this playbook

5 / 190 platform modules

The market this case is written for

Russia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

More in Quality & safety

Quality & safety

Toolbox talk and safety check

Brief the crew on the hazards this shift actually carries, capture who was there, then prov…

2 steps8 minOpen