Rakenda hinnamuutuse valemit avalikul ehituslepingul

Salvesta hinnaeskalatsiooni klausel koos selle komponentide, kaaludega ja baaskuupäevaga, lae selles nimetatud indeksiseeria, arvuta perioodi jooksul tehtud töö korrigeerimine, kanna see arvele, ja hoia arvutuskäik kohas, kus kontrollija saab selle üle korrata.

5 sammu20 minPeatöövõtjaKulunõustamine / QSArendaja / klientProjekti- / ehitusjuhtimisbüroo

Kuidas see töötab, samm-sammult

5 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

Write the clause down as parameters, not as prose

Lepingud

Record against the contract each component the clause names and its weightage, which index series applies to each, what the base date is, whether a minimum period must pass before anything is payable, and whether a ceiling applies.

Ekraanipilt, samm 1: Write the clause down as parameters, not as prose (Lepingud, Rakenda hinnamuutuse valemit avalikul ehituslepingul)
Lepingud: Write the clause down as parameters, not as prose

Miks: The clause is read once, at the start, by whoever is available, and then applied for years by other people. Turning it into stated parameters at that first reading is what stops the third claim being computed on a different understanding from the first.

SisendThe contract conditionsVäljundComponents and their weightagesBase date, threshold and ceiling
2

Load the index series and pin the base month

Hinnaindeks

Bring in the published series for each component, record the base month value the contract fixes, and add each period's value as it is published. Where a series is revised after publication, keep both the provisional and the final figure.

Ekraanipilt, samm 2: Load the index series and pin the base month (Hinnaindeks, Rakenda hinnamuutuse valemit avalikul ehituslepingul)
Hinnaindeks: Load the index series and pin the base month

Miks: Index series get revised, and a claim computed on a provisional figure has to be reworked when the final one lands. Holding both makes that a recomputation rather than a discovery, and it explains the difference to the checker before they ask.

SisendThe index series the clause namesVäljundBase and current index per component
3

Compute the adjustment on the period, component by component

Mahutabel

Take the value of work executed in the period from the bill, split it by the weightages, apply each component's index movement, and keep the working visible per component rather than as a single figure.

Ekraanipilt, samm 3: Compute the adjustment on the period, component by component (Mahutabel, Rakenda hinnamuutuse valemit avalikul ehituslepingul)
Mahutabel: Compute the adjustment on the period, component by component

Miks: Escalation is checked by re-doing it, not by reading it. Working that shows the split, the two index values and the resulting amount for each component can be verified in minutes; a single total invites the checker to compute their own and argue about the difference.

SisendValue of work done in the periodBase and current indicesVäljundThe adjustment for the periodWorking, component by component
4

Bill it as its own line, never inside the rates

Finants

Put the adjustment on the running account bill as a separate line naming the period and the clause, and let the tax and the deductions treat it the way the contract and the invoice rules require.

Ekraanipilt, samm 4: Bill it as its own line, never inside the rates (Finants, Rakenda hinnamuutuse valemit avalikul ehituslepingul)
Finants: Bill it as its own line, never inside the rates

Miks: Escalation folded into rates makes the rates untraceable to the contract and the escalation untraceable to a period, so both become unverifiable at once. Kept as a line, it can be certified, queried or withheld on its own without touching the measured work.

SisendThe computed adjustmentVäljundEscalation as its own bill line
5

Keep the evidence with the period it belongs to

Nõuete tõendid

File the published index pages used, the value of work certified for the period, and the working, all keyed to the period, so any single month can be produced on its own.

Miks: Escalation is settled at the end of the job as often as during it, by which time the person who computed period four has left. A file organised by period answers a query about period four; a file organised by year does not.

SisendThe working and the published figuresVäljundA file that supports every period
Moodulid

Selle tegevusjuhendi moodulid

5 / 190 platvormi moodulit

The market this case is written for

India

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Rohkem valdkonnas Äritegevus ja lepingud

Äritegevus ja lepingud

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 sammu11 minAva