공공 계약에 물가변동 조정식 적용하기

에스컬레이션 조항을 구성 요소, 가중치, 기준일과 함께 기록하고, 조항이 지정한 지수 시리즈를 불러오고, 해당 기간에 시행된 공사에 대한 조정액을 계산하고, 이를 청구하며, 검사자가 다시 계산할 수 있게 산출 근거를 남깁니다.

5단계20 분종합건설사원가 컨설팅 / 적산 업체시행사 / 발주처PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 5단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Write the clause down as parameters, not as prose

계약

Record against the contract each component the clause names and its weightage, which index series applies to each, what the base date is, whether a minimum period must pass before anything is payable, and whether a ceiling applies.

스크린샷, 1단계: Write the clause down as parameters, not as prose (계약, 공공 계약에 물가변동 조정식 적용하기)
계약: Write the clause down as parameters, not as prose

이유: The clause is read once, at the start, by whoever is available, and then applied for years by other people. Turning it into stated parameters at that first reading is what stops the third claim being computed on a different understanding from the first.

입력The contract conditions결과Components and their weightagesBase date, threshold and ceiling
2

Load the index series and pin the base month

물가 지수

Bring in the published series for each component, record the base month value the contract fixes, and add each period's value as it is published. Where a series is revised after publication, keep both the provisional and the final figure.

스크린샷, 2단계: Load the index series and pin the base month (물가 지수, 공공 계약에 물가변동 조정식 적용하기)
물가 지수: Load the index series and pin the base month

이유: Index series get revised, and a claim computed on a provisional figure has to be reworked when the final one lands. Holding both makes that a recomputation rather than a discovery, and it explains the difference to the checker before they ask.

입력The index series the clause names결과Base and current index per component
3

Compute the adjustment on the period, component by component

내역서

Take the value of work executed in the period from the bill, split it by the weightages, apply each component's index movement, and keep the working visible per component rather than as a single figure.

스크린샷, 3단계: Compute the adjustment on the period, component by component (내역서, 공공 계약에 물가변동 조정식 적용하기)
내역서: Compute the adjustment on the period, component by component

이유: Escalation is checked by re-doing it, not by reading it. Working that shows the split, the two index values and the resulting amount for each component can be verified in minutes; a single total invites the checker to compute their own and argue about the difference.

입력Value of work done in the periodBase and current indices결과The adjustment for the periodWorking, component by component
4

Bill it as its own line, never inside the rates

재무

Put the adjustment on the running account bill as a separate line naming the period and the clause, and let the tax and the deductions treat it the way the contract and the invoice rules require.

스크린샷, 4단계: Bill it as its own line, never inside the rates (재무, 공공 계약에 물가변동 조정식 적용하기)
재무: Bill it as its own line, never inside the rates

이유: Escalation folded into rates makes the rates untraceable to the contract and the escalation untraceable to a period, so both become unverifiable at once. Kept as a line, it can be certified, queried or withheld on its own without touching the measured work.

입력The computed adjustment결과Escalation as its own bill line
5

Keep the evidence with the period it belongs to

클레임 증거

File the published index pages used, the value of work certified for the period, and the working, all keyed to the period, so any single month can be produced on its own.

이유: Escalation is settled at the end of the job as often as during it, by which time the person who computed period four has left. A file organised by period answers a query about period four; a file organised by year does not.

입력The working and the published figures결과A file that supports every period
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 5개

The market this case is written for

인도

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.