公共工事に物価変動調整式を適用する

エスカレーション条項をその構成要素、ウェイトおよび基準日とともに記録し、条項が指定する指数系列を読み込み、期間中に実施した工事に対する調整額を計算し、それを請求し、検査者が再計算できる形で計算過程を残す。

5ステップ20 分総合建設会社コストコンサルティング会社 / 積算事務所デベロッパー / 発注者プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で5ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Write the clause down as parameters, not as prose

契約

Record against the contract each component the clause names and its weightage, which index series applies to each, what the base date is, whether a minimum period must pass before anything is payable, and whether a ceiling applies.

理由: The clause is read once, at the start, by whoever is available, and then applied for years by other people. Turning it into stated parameters at that first reading is what stops the third claim being computed on a different understanding from the first.

入力The contract conditions出力Components and their weightagesBase date, threshold and ceiling
2

Load the index series and pin the base month

物価指数

Bring in the published series for each component, record the base month value the contract fixes, and add each period's value as it is published. Where a series is revised after publication, keep both the provisional and the final figure.

理由: Index series get revised, and a claim computed on a provisional figure has to be reworked when the final one lands. Holding both makes that a recomputation rather than a discovery, and it explains the difference to the checker before they ask.

入力The index series the clause names出力Base and current index per component
3

Compute the adjustment on the period, component by component

内訳書

Take the value of work executed in the period from the bill, split it by the weightages, apply each component's index movement, and keep the working visible per component rather than as a single figure.

理由: Escalation is checked by re-doing it, not by reading it. Working that shows the split, the two index values and the resulting amount for each component can be verified in minutes; a single total invites the checker to compute their own and argue about the difference.

入力Value of work done in the periodBase and current indices出力The adjustment for the periodWorking, component by component
4

Bill it as its own line, never inside the rates

財務

Put the adjustment on the running account bill as a separate line naming the period and the clause, and let the tax and the deductions treat it the way the contract and the invoice rules require.

理由: Escalation folded into rates makes the rates untraceable to the contract and the escalation untraceable to a period, so both become unverifiable at once. Kept as a line, it can be certified, queried or withheld on its own without touching the measured work.

入力The computed adjustment出力Escalation as its own bill line
5

Keep the evidence with the period it belongs to

クレーム証拠

File the published index pages used, the value of work certified for the period, and the working, all keyed to the period, so any single month can be produced on its own.

理由: Escalation is settled at the end of the job as often as during it, by which time the person who computed period four has left. A file organised by period answers a query about period four; a file organised by year does not.

入力The working and the published figures出力A file that supports every period
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 5

The market this case is written for

インド

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

コマーシャルと契約の他のケース

コマーシャルと契約

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3ステップ11 分開く
コマーシャルと契約

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3ステップ11 分開く
コマーシャルと契約

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3ステップ12 分開く