Open the tender and write down the designation it asks for, both halves of it: the class of work, and the grade. Then read the scope against the class, because a building contract with a substantial electrical or mechanical element can call for more than one class.

چرا: The designation is the first thing an evaluation committee checks and the cheapest thing to fail on. A bid from a firm whose class of work does not cover the contract is not scored and then rejected, it is set aside before scoring, and the tender fee and three weeks of estimating go with it.
Put your own designation next to your estimate of the tender value and make the bid or no bid decision on it. Each grade carries a tender value ceiling, rising through the nine grades, and only grade 9 has no upper limit.
چرا: A grade is a ceiling, not a guideline: a public sector client cannot award above it whatever the merits of the price. Making the call before the estimating starts is the difference between a considered no bid and an expensive one, and recording why you passed is what lets you argue for an upgrade with evidence next year.
Record the expiry date of the registration as a deadline with a reminder far enough ahead to renew, and put the same date against every bid in the pipeline that closes after it.

چرا: Registration is checked as at the closing date of the tender, not as at the day the work starts. A firm that has been on the register for eleven years and let it lapse for eleven days is, on that day, a firm a public sector client may not award to, and no amount of history changes that.
For each package you intend to sublet, record the subcontractor, the class of work its designation carries and the value of the package, and flag any package whose value or class the subcontractor cannot cover.

چرا: The electrical and mechanical classes exist precisely because that work is graded separately from general building. A team assembled on price alone can be perfectly capable and still put a package with a firm whose designation does not reach it, and the tender document usually asks you to name them.
Hold the registration certificate, the tax clearance, the letter of good standing under the Compensation for Occupational Injuries and Diseases Act 130 of 1993 and the B-BBEE certificate or sworn affidavit in one place, each with the date it stops being current.

چرا: Every one of these documents is asked for by almost every tender and every one of them expires. Hunting for the current version on the afternoon a bid closes is how a compliant firm submits an expired certificate, and an expired certificate is treated as no certificate.
Supply the client with what the register of projects needs and keep the record of the submission. A public sector client registers construction works above R200 000; for state owned entities and for private sector work the threshold is R10 million.

چرا: The register of projects is the client's duty under the construction industry development regulations, but the data comes from the contractor and the delay lands on the contractor. It also matters to you later: the performance record built on registered projects is what a grading upgrade application is assessed on, so a project nobody registered is a project that never counted towards your next grade.
6 / 190 ماژول پلتفرم
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.
یک صورتوضعیت قیمتگذاریشده را به بازار ببرید: آن را بستهبندی کنید، پیمانکاران جزء را دعوت…
مقادیری که قبلاً قیمتگذاری کردهاید را بخرید: یک درخواست خرید از روی صورتوضعیت مطرح کنید،…
پوشهای از مناقصههای بازگشتی که هرگز کاملاً با هم مطابقت ندارند را بردارید، آنها را به هما…