케이스 / 상업 및 계약
상업 및 계약

KS-2 act와 KS-3 증명서로 월 마감하기

smeta에 대조해 기간을 실측하고, GESN 표준품셈을 그것이 담고 있는 자원으로 전개하고, 발주처 기술감독관이 KS-2 act에 서명하게 하고, 그에 대해 KS-3 증명서를 발행함으로써, 누계 금액과 승인 금액이 서로 어긋나지 않게 한다.

7단계12 분종합건설사전문건설사시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Measure the period smeta position by smeta position

진척

Record what was executed against each smeta position for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

이유: A KS-2 act built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one smeta position rather than about the whole month, and the rest of the money moves while that one is settled.

입력Approved smetaWork executed this period결과Percent complete per smeta positionExecuted volumes for the period
2

Value it at the contract rates

내역서

Read the valuation back against the bill and check the rates it used are the contract rates. Where a smeta position has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line. A norm-based rate carries the labour, machinery and materials behind it, so the act can be read back to the resources it claims rather than to a single figure. That is what makes a disagreement about one position a conversation about one norm.

이유: An additional works agreement certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

입력Executed volumes for the periodGESN norms and smeta rates결과KS-2 act for the periodAdditional works flagged
3

Get it approved by the people who have to approve it

승인 경로

Route the KS-2 act to the client's technical supervisor, and to whoever the contract adds after them. Keep the approval date, because the KS-3 certificate follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it. On a state contract under 44-FZ the act is signed as the acceptance document in the EIS, the customer has the period the contract sets and at most twenty working days to sign it or refuse it with reasons, and payment then falls due within seven working days of that signature.

이유: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

입력KS-2 act for the periodTechnical supervisor named for acceptance결과Signed KS-2 actAcceptance date on record
4

Apply guarantee retention and previous payments

재무

Take the cumulative valuation, subtract what has already been certified, and apply guarantee retention at the contract percentage. The figure that leaves this step is the one the KS-3 certificate is raised for, and the backup behind it is the measure that produced it.

이유: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

입력Signed KS-2 acts to datePrevious payments and guarantee retention결과Cumulative value of worksNet due for the period
5

Issue the KS-3 certificate against the approved figure

재무

Raise the KS-3 certificate against the approved KS-2 act, carrying guarantee retention and any deduction the contract provides for, and reference the KS-2 act on it. The KS-3 carries the VAT line, at twenty-two percent since January 2026, and the VAT invoice (schet-faktura), or the universal transfer document that replaces the act and the invoice together, follows within five calendar days of the KS-2 signature, because that signature is the tax point for the works.

이유: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the KS-2 act also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

입력Cumulative value of worksGuarantee retention and deductions결과KS-3 certificate issuedAmount carried into the accounts
6

Open the payment clock on the right day

지급 시계

Open a clock over the KS-3 certificate starting from the day the KS-2 act is signed, under 44-FZ. Payment falls due 7 working days later, and the clock records that date rather than leaving it to be worked out when somebody asks. That is the state-contract clock, and the module carries it as the Russian public procurement regime. On a private contract the Civil Code leaves the period to the parties, so open the clock on the contract's own days instead.

이유: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the KS-2 act is signed once makes the whole chain checkable.

입력KS-3 certificate and its dateContract payment terms결과Open payment clockFinal date for payment
7

Reconcile what was certified against what was asked

사건 대사

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

이유: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight. The two forms are reconciled at contract close whether or not anybody reconciled them monthly, and a year of small differences is not a month of arithmetic. Doing it every period is the same work spread over the time when it is still cheap to correct.

입력Amount certified on the KS-3Amount accepted on the KS-2 acts결과Difference carried forwardOutstanding by age
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6

The market this case is written for

러시아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기