以 KS-2 验收单和 KS-3 结算单结束本月

按 smeta 计量本期完成量,把 GESN 定额展开为它所包含的资源,由业主技术监理签署 KS-2 验收单,并据此开具 KS-3 结算单,让累计数与已确认数永不出现差额。

7 个步骤12 分钟总承包商专业分包商开发商/业主

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Measure the period smeta position by smeta position

进度

Record what was executed against each smeta position for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

屏幕截图,步骤 1:Measure the period smeta position by smeta position (进度, 以 KS-2 验收单和 KS-3 结算单结束本月)
进度: Measure the period smeta position by smeta position

原因: A KS-2 act built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one smeta position rather than about the whole month, and the rest of the money moves while that one is settled.

输入Approved smetaWork executed this period成果Percent complete per smeta positionExecuted volumes for the period
2

Value it at the contract rates

工程量清单

Read the valuation back against the bill and check the rates it used are the contract rates. Where a smeta position has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line. A norm-based rate carries the labour, machinery and materials behind it, so the act can be read back to the resources it claims rather than to a single figure. That is what makes a disagreement about one position a conversation about one norm.

屏幕截图,步骤 2:Value it at the contract rates (工程量清单, 以 KS-2 验收单和 KS-3 结算单结束本月)
工程量清单: Value it at the contract rates

原因: An additional works agreement certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

输入Executed volumes for the periodGESN norms and smeta rates成果KS-2 act for the periodAdditional works flagged
3

Get it approved by the people who have to approve it

审批路线

Route the KS-2 act to the client's technical supervisor, and to whoever the contract adds after them. Keep the approval date, because the KS-3 certificate follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it. On a state contract under 44-FZ the act is signed as the acceptance document in the EIS, the customer has the period the contract sets and at most twenty working days to sign it or refuse it with reasons, and payment then falls due within seven working days of that signature.

屏幕截图,步骤 3:Get it approved by the people who have to approve it (审批路线, 以 KS-2 验收单和 KS-3 结算单结束本月)
审批路线: Get it approved by the people who have to approve it

原因: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

输入KS-2 act for the periodTechnical supervisor named for acceptance成果Signed KS-2 actAcceptance date on record
4

Apply guarantee retention and previous payments

财务

Take the cumulative valuation, subtract what has already been certified, and apply guarantee retention at the contract percentage. The figure that leaves this step is the one the KS-3 certificate is raised for, and the backup behind it is the measure that produced it.

屏幕截图,步骤 4:Apply guarantee retention and previous payments (财务, 以 KS-2 验收单和 KS-3 结算单结束本月)
财务: Apply guarantee retention and previous payments

原因: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

输入Signed KS-2 acts to datePrevious payments and guarantee retention成果Cumulative value of worksNet due for the period
5

Issue the KS-3 certificate against the approved figure

财务

Raise the KS-3 certificate against the approved KS-2 act, carrying guarantee retention and any deduction the contract provides for, and reference the KS-2 act on it. The KS-3 carries the VAT line, at twenty-two percent since January 2026, and the VAT invoice (schet-faktura), or the universal transfer document that replaces the act and the invoice together, follows within five calendar days of the KS-2 signature, because that signature is the tax point for the works.

屏幕截图,步骤 5:Issue the KS-3 certificate against the approved figure (财务, 以 KS-2 验收单和 KS-3 结算单结束本月)
财务: Issue the KS-3 certificate against the approved figure

原因: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the KS-2 act also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

输入Cumulative value of worksGuarantee retention and deductions成果KS-3 certificate issuedAmount carried into the accounts
6

Open the payment clock on the right day

付款时钟

Open a clock over the KS-3 certificate starting from the day the KS-2 act is signed, under 44-FZ. Payment falls due 7 working days later, and the clock records that date rather than leaving it to be worked out when somebody asks. That is the state-contract clock, and the module carries it as the Russian public procurement regime. On a private contract the Civil Code leaves the period to the parties, so open the clock on the contract's own days instead.

原因: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the day the KS-2 act is signed once makes the whole chain checkable.

输入KS-3 certificate and its dateContract payment terms成果Open payment clockFinal date for payment
7

Reconcile what was certified against what was asked

事件对账

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

原因: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight. The two forms are reconciled at contract close whether or not anybody reconciled them monthly, and a year of small differences is not a month of arithmetic. Doing it every period is the same work spread over the time when it is still cheap to correct.

输入Amount certified on the KS-3Amount accepted on the KS-2 acts成果Difference carried forwardOutstanding by age
模块

此方案使用的模块

190 个平台模块中的 6 个

The market this case is written for

俄罗斯

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 商务与合同 案例

商务与合同

把变更转化为已付款的变更单

在范围变更还新鲜时就记录下来,依据你已约定的单价将其作为合同变更报价,并在下一期进度付款申请中计入,使额外工作能够获得补偿,而不是被悄悄吸收。

3 个步骤11 分钟打开
商务与合同

管理分包工程

将某工种分包给分包商,以带付款计划表和保留金条款的分包合同确定下来,再按实际完成的工作逐期支付款项。

3 个步骤11 分钟打开
商务与合同

付款申请与对账

按合同对本期已完成工作进行估值,附上依据提出申请,并将已核证的金额与账户实际到账的金额进行对账。

3 个步骤12 分钟打开