Bir götürü bedeli serbest bırakın ve koordinasyon ücretini tahsil edin

İşverenin götürü bedellerini bir kayıt defterinde tutun, koordinasyon ücretinin üzerinden tahsil edilecek bir dayanağı olsun diye uzmanlık paketlerini metrajda taşıyın, paketi ihaleye çıkarın, ihale edildikçe düşün ve kalanı raporlayın.

5 adım20 dkAna yükleniciMaliyet danışmanlığı / QSGeliştirici / işverenProje / inşaat yönetim bürosu

Nasıl çalışır, adım adım

Platform genelinde 5 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Put every sum on the register with what it is for

Ödenekler ve Beklenmedik Giderler

Enter each sum the bill carries: the provisional sums the owner holds for undefined scope, the prime cost sums standing in for packages to be tendered, and the contingency. Give each one the scope it covers, not just a figure.

Neden: A sum with no stated scope gets drawn against for whatever is convenient, and by the time somebody asks what it was for the answer is a list of unrelated instructions. Writing the scope down at the start is what makes the drawdowns arguable later.

GirdiSums named in the billWhat each sum is forÇıktıSums on the registerTotal held, visible
2

Give the fee something to be charged on

Keşif Özeti

Carry the packages and the sums in the bill as positions under a section of their own, then add the coordination fee as a markup scoped to that section rather than to the bill. A scoped markup applies to the position it names and everything under it, and can stand in for a bill-wide one where the two would otherwise both apply.

Neden: The main contractor's fee for coordinating specialists the owner appoints directly, and for handling what the owner supplies, is a percentage on a defined part of the works and not on the job. If those packages live only in a register, the fee has no base and ends up as a number somebody agreed verbally. Build the section first and the fee is configuration; charge the fee first and it has nothing to compute on.

GirdiDirectly appointed packagesThe fee percentageÇıktıIts own section in the billFee scoped to that section
3

Tender the package the sum was holding money for

Tedarik

Once the scope firms up, tender the package properly and let it. The price it is let at is what actually gets drawn against the sum, not the sum itself.

Neden: A provisional sum is an estimate of something nobody had designed, and the gap between the sum and the let price is money that belongs to somebody. Tendering it rather than converting it at book value is how that gap becomes visible while there is still a decision to make about it.

GirdiThe sum being releasedScope now definedÇıktıQuotations on one scopePackage let, at a real price
4

Draw down against the sum as the work is released

Ödenekler ve Beklenmedik Giderler

Record a drawdown for the amount released and note which package it went to. The remaining balance is worked out from the drawdowns rather than stored, and drawing more than was held is recorded and flagged rather than refused.

Neden: A stored balance goes stale the first time somebody edits a drawdown; a derived one cannot. And the moment a sum goes over is exactly the moment the project needs to see it rather than be stopped by it, because the work is usually already instructed by then and the conversation that matters is with the owner, not with the software.

GirdiLet price and instructionÇıktıDrawdown recordedRemaining balance, derived
5

Report the position while it can still be acted on

Raporlar

Report what is held, what has been drawn, what remains against each sum, and the coordination fee the packages have earned. Take the unspent balances to the owner as part of the settlement conversation.

Neden: An unspent provisional sum belongs back to the owner at final account, and it goes back because somebody put it on a schedule and asked. Reporting the balances monthly means that schedule already exists when the settlement starts, instead of being assembled from instructions at the point where every figure is contested.

GirdiRegister with its drawdownsÇıktıHeld, drawn and remainingFee earned on the packages
Modüller

Bu senaryodaki modüller

4 / 190 platform modülü

The market this case is written for

Çin

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Ticari ve sözleşmeler kategorisinde daha fazlası

Ticari ve sözleşmeler

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 adım11 dk