Reconcile a drawing issue against the index

Diff an issued sheet set against the drawing index and see what is missing, what turned up unannounced and what is sitting at a revision the index does not expect, then chase the gaps with the numbers in hand.

4 стъпки8 минГлавен изпълнителBIM / дигитален консултингФирма за проектен / строителен мениджмънт

Как работи, стъпка по стъпка

4 стъпки през платформата - какво правите на всяка и защо е важно.

1

Take in the issued sheet set

Документи

Load the issued set into the project files and split it into individual sheets, so each drawing lands as its own record with a number and a revision picked up from the title block rather than sitting inside a two hundred page file.

Защо: You cannot reconcile a bundle. Until the issue is broken into numbered sheets the only way to answer whether A-114 arrived is for somebody to scroll, and nobody scrolls the same set twice, which is how a missing sheet survives three weeks of everybody assuming it is in there.

ВходIssued PDF setCovering transmittalРезултатIndividual numbered sheetsRevision read off each one
2

Reconcile it against the index

Зала за чертежи

Point the completeness check at the index, either the index PDF the designer issued or a sheet list pasted straight in, and run it. It reports what the index expects and you do not hold, what you hold and the index never mentioned, and what matched but at a different revision.

Защо: Sheet numbers get written a dozen ways across a project, A-101, A 101, a.101, so ticking two lists off by eye reliably misses the ones that differ only by a hyphen. The check collapses those differences before it compares, which is why it finds gaps a careful person reading the same two lists will not.

ВходSheets you actually holdDrawing index or issue registerРезултатMissing and extra listsRevision mismatches
3

Chase what never arrived

Предавания

Check the missing list against the transmittal record first, to be sure the sheets were genuinely never issued rather than mislaid on your side, then go back to the issuer with the exact numbers and the revision each one should be at.

Защо: A designer answers we sent everything in one line, and answers a list of eleven sheet numbers in a day. Naming the gap precisely, against the transmittal that was meant to carry it, turns a fortnight of email into a short conversation, and leaves a dated trail if the missing sheet later costs somebody a week.

ВходMissing sheet numbersTransmittal logРезултатRequest naming each sheetDated chase trail
4

Account for what arrived unannounced

Документи

Work the other two lists. Register the sheets that came in outside the index so they stop being invisible, and for every revision mismatch settle which side is behind, the index or the set, before anyone builds from either.

Защо: An extra sheet is usually one somebody issued without updating the index, which makes it the drawing nobody is tracking. A revision mismatch is worse, because both parties are certain they hold the current sheet and one of them is pricing or pouring to geometry that has already moved.

ВходExtra sheets and mismatchesDrawing registerРезултатEverything registeredAgreed current revision
Модули

Модули в този наръчник

3 / 184 модула на платформата

Още в BIM и количествено пресмятане

BIM и количествено пресмятане

Получете 6D въглерод от BIM модел

Превърнете конвертиран BIM модел в отпечатък от вложен въглерод. Автоматичното обогатяване ч…

5 стъпки12 минОтвори
BIM и количествено пресмятане

Извличане на количества от BIM модел

Заредете конвертиран модел, извлечете количествата на елементите директно от геометрията, пр…

3 стъпки12 минОтвори
BIM и количествено пресмятане

Измерете количества от DWG

Заредете DWG, фиксирайте мащаба спрямо известен размер, измерете нужните площи, дължини и бр…

3 стъпки10 минОтвори