BIMと数量拾い

Reconcile a drawing issue against the index

Diff an issued sheet set against the drawing index and see what is missing, what turned up unannounced and what is sitting at a revision the index does not expect, then chase the gaps with the numbers in hand.

4ステップ8 分総合建設会社BIM / デジタルコンサルティング会社プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で4ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Take in the issued sheet set

文書

Load the issued set into the project files and split it into individual sheets, so each drawing lands as its own record with a number and a revision picked up from the title block rather than sitting inside a two hundred page file.

理由: You cannot reconcile a bundle. Until the issue is broken into numbered sheets the only way to answer whether A-114 arrived is for somebody to scroll, and nobody scrolls the same set twice, which is how a missing sheet survives three weeks of everybody assuming it is in there.

入力Issued PDF setCovering transmittal出力Individual numbered sheetsRevision read off each one
2

Reconcile it against the index

図面室

Point the completeness check at the index, either the index PDF the designer issued or a sheet list pasted straight in, and run it. It reports what the index expects and you do not hold, what you hold and the index never mentioned, and what matched but at a different revision.

理由: Sheet numbers get written a dozen ways across a project, A-101, A 101, a.101, so ticking two lists off by eye reliably misses the ones that differ only by a hyphen. The check collapses those differences before it compares, which is why it finds gaps a careful person reading the same two lists will not.

入力Sheets you actually holdDrawing index or issue register出力Missing and extra listsRevision mismatches
3

Chase what never arrived

送付

Check the missing list against the transmittal record first, to be sure the sheets were genuinely never issued rather than mislaid on your side, then go back to the issuer with the exact numbers and the revision each one should be at.

理由: A designer answers we sent everything in one line, and answers a list of eleven sheet numbers in a day. Naming the gap precisely, against the transmittal that was meant to carry it, turns a fortnight of email into a short conversation, and leaves a dated trail if the missing sheet later costs somebody a week.

入力Missing sheet numbersTransmittal log出力Request naming each sheetDated chase trail
4

Account for what arrived unannounced

文書

Work the other two lists. Register the sheets that came in outside the index so they stop being invisible, and for every revision mismatch settle which side is behind, the index or the set, before anyone builds from either.

理由: An extra sheet is usually one somebody issued without updating the index, which makes it the drawing nobody is tracking. A revision mismatch is worse, because both parties are certain they hold the current sheet and one of them is pricing or pouring to geometry that has already moved.

入力Extra sheets and mismatchesDrawing register出力Everything registeredAgreed current revision
モジュール

このプレイブックのモジュール

プラットフォーム 184 モジュール中 3

BIMと数量拾いの他のケース

BIMと数量拾い

BIMモデルから6Dカーボンを算出する

変換済みのBIMモデルを組み込みCO2排出量に変換します。自動集計がジオメトリから数量を読み取り、各材料を排出係数と対応させ、削減目標を設定してレポートを発行します。5ステップです。

5ステップ12 分開く
BIMと数量拾い

BIMモデルから数量を取得する

変換済みモデルを読み込み、要素数量をジオメトリからそのまま取得し、価格付き明細書に反映させ、マッピング内容を検証する。

3ステップ12 分開く
BIMと数量拾い

DWGから数量を計測する

DWGを読み込み、既知の寸法に対して縮尺を固定し、必要な面積・長さ・数量を計測し、その数量をそのまま積算済みの内訳書に反映させる。

3ステップ10 分開く