List every permit and planning condition, book the final statutory inspections, collect the completion certificates and confirm every condition is discharged so the building can be legally occupied.

4 steps10 minGeneral contractorProject / construction management firmDeveloper / client

How it works, step by step

4 steps across the platform - what you do at each one, and why it matters.

1

List every approval

Handover

List every permit, statutory approval and planning condition the project carries, with what each one needs to be discharged and who is responsible for it.

Handover screen in OpenConstructionERP: List every approval (Close out permits and statutory approvals)
Handover: List every approval

Why: A condition forgotten until handover week can stall occupation. Listing them all early is what turns a scramble for certificates into a schedule that closes out in good time.

InConsents and conditionsOutApprovals schedule
2

Book the final inspections

Inspections

Book the final statutory inspections - building control, fire, utilities and any specialist body - and record each sign-off against the approval it satisfies.

Inspections screen in OpenConstructionERP: Book the final inspections (Close out permits and statutory approvals)
Inspections: Book the final inspections

Why: Statutory inspectors work to their own diaries, not yours. Booking them early and tracking each sign-off is what keeps a missing inspection from becoming the thing that delays completion.

InApprovals scheduleOutStatutory sign-offs
3

Collect the certificates

Documents

Collect the completion certificates and approval letters into the handover file, so the proof that the building is signed off lives in one place the client can rely on.

Documents screen in OpenConstructionERP: Collect the certificates (Close out permits and statutory approvals)
Documents: Collect the certificates

Why: A certificate that cannot be found is a certificate that does not exist as far as a lawyer or a future buyer is concerned. Filing them properly protects the client for the life of the building.

InStatutory sign-offsOutCompletion certificates
4

Confirm every condition discharged

Handover

Confirm every condition is formally discharged and nothing is left outstanding, so the building is legally clear for the client to occupy and operate.

Handover screen in OpenConstructionERP: Confirm every condition discharged (Close out permits and statutory approvals)
Handover: Confirm every condition discharged

Why: One undischarged condition can make an occupied building non-compliant. Confirming the full set is closed is the final gate that lets everyone hand over and move on with confidence.

InCertificates collectedOutCleared for occupation
Modules

Modules in this playbook

3 / 190 platform modules

More in Handover & lifecycle

Handover & lifecycle

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 steps14 minOpen
Handover & lifecycle

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 steps12 minOpen