Reconcile materials on form M-29

Take the norm consumption for the work the month actually completed, set it against what the store really issued, separate allowed losses from real overrun, get each overrun explained in writing and close the month with the cumulative position.

7 steps14 minGeneral contractorSpecialist subcontractor

How it works, step by step

7 steps across the platform - what you do at each one, and why it matters.

1

Take the norm consumption for the work you are reporting

Production Norms

For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.

Why: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.

InPositions in the reportNorm consumption per unitOutNormative requirementSubstituted materials converted
2

Separate the losses the norm allows from real overrun

Waste Factors

Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.

Waste Factors screen in OpenConstructionERP: Separate the losses the norm allows from real overrun (Reconcile materials on form M-29)
Waste Factors: Separate the losses the norm allows from real overrun

Why: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.

InMaterials in scopeDelivery and cutting formOutAllowed loss per materialPurchase quantity explained
3

Fix the volume of work the month actually completed

Progress

Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.

Progress screen in OpenConstructionERP: Fix the volume of work the month actually completed (Reconcile materials on form M-29)
Progress: Fix the volume of work the month actually completed

Why: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.

InMeasurement on siteUnits the smeta usesOutVolume completed this monthSame figure as the acceptance act
4

Record what was really issued and consumed

Site Inventory

Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.

Site Inventory screen in OpenConstructionERP: Record what was really issued and consumed (Reconcile materials on form M-29)
Site Inventory: Record what was really issued and consumed

Why: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.

InDeliveries booked inIssues to each positionOutActual consumptionClosing stock counted
5

Compare actual against norm position by position

Post-calculation

Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.

Post-calculation screen in OpenConstructionERP: Compare actual against norm position by position (Reconcile materials on form M-29)
Post-calculation: Compare actual against norm position by position

Why: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.

InNormative requirementActual consumptionOutVariance per positionVariance in money
6

Get every overrun explained and signed for

Approval routes

Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.

Approval routes screen in OpenConstructionERP: Get every overrun explained and signed for (Reconcile materials on form M-29)
Approval routes: Get every overrun explained and signed for

Why: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.

InOverruns above thresholdWritten reason from the siteOutAccepted explanationsRejected and referred on
7

Close the month with the cumulative position

Reports

Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.

Reports screen in OpenConstructionERP: Close the month with the cumulative position (Reconcile materials on form M-29)
Reports: Close the month with the cumulative position

Why: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.

InVariance with explanationsPosition from previous monthsOutSigned report for the monthCumulative position
Modules

Modules in this playbook

7 / 190 platform modules

The market this case is written for

Russia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

More in Site & field

Site & field

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 steps9 minOpen
Site & field

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 steps9 minOpen