运作方式,逐步说明
贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。
Take the norm consumption for the work you are reporting
生产定额For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.
原因: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.
Separate the losses the norm allows from real overrun
损耗系数Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.
原因: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.
Fix the volume of work the month actually completed
进度Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.
原因: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.
Record what was really issued and consumed
现场库存Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.
原因: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.
Compare actual against norm position by position
结算后核算Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.
原因: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.
Get every overrun explained and signed for
审批路线Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.
原因: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.
Close the month with the cumulative position
报告Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.
原因: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.
此方案使用的模块
190 个平台模块中的 7 个

