用 M-29 表核对材料用量

取当月实际完成工作量对应的定额消耗量,与库房实际发出的材料量核对,把定额允许的损耗和真实超耗区分开,让每一项超耗都获得书面解释,再用累计数据结账。

7 个步骤14 分钟总承包商专业分包商

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Take the norm consumption for the work you are reporting

生产定额

For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.

原因: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.

输入Positions in the reportNorm consumption per unit成果Normative requirementSubstituted materials converted
2

Separate the losses the norm allows from real overrun

损耗系数

Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.

原因: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.

输入Materials in scopeDelivery and cutting form成果Allowed loss per materialPurchase quantity explained
3

Fix the volume of work the month actually completed

进度

Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.

原因: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.

输入Measurement on siteUnits the smeta uses成果Volume completed this monthSame figure as the acceptance act
4

Record what was really issued and consumed

现场库存

Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.

原因: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.

输入Deliveries booked inIssues to each position成果Actual consumptionClosing stock counted
5

Compare actual against norm position by position

结算后核算

Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.

原因: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.

输入Normative requirementActual consumption成果Variance per positionVariance in money
6

Get every overrun explained and signed for

审批路线

Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.

原因: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.

输入Overruns above thresholdWritten reason from the site成果Accepted explanationsRejected and referred on
7

Close the month with the cumulative position

报告

Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.

原因: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.

输入Variance with explanationsPosition from previous months成果Signed report for the monthCumulative position
模块

此方案使用的模块

190 个平台模块中的 7

The market this case is written for

俄罗斯

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 现场与作业 案例

现场与作业

收尾现场一天的工作

妥善收尾一天的工作:记录日志、登记人工和机械工时、上传照片并记录安全观察,让这一天以可依赖的证据形式留存下来。

4 个步骤9 分钟打开
现场与作业

答复一份RFI

将现场提出的问题转化为可跟踪的请求,推动到负责给出答复的一方,并将回复归档,使其成为项目记录的一部分。

3 个步骤9 分钟打开
现场与作业

记录计工计料与时间材料

把已下达指令的额外工作转化为能获得赔付的索赔:施工发生的同时记录人工、机械和材料,当天就取得签认,再依据合同提交。

3 个步骤9 分钟打开