Kasus / Lapangan dan proyek
Lapangan dan proyek

Cocokkan material pada formulir M-29

Ambil konsumsi norma untuk pekerjaan yang benar-benar diselesaikan bulan itu, bandingkan dengan yang benar-benar dikeluarkan gudang, pisahkan kehilangan yang diizinkan dari kelebihan pemakaian sesungguhnya, minta setiap kelebihan pemakaian dijelaskan secara tertulis, dan tutup bulan dengan posisi kumulatif.

7 langkah14 mntKontraktor umumSubkontraktor spesialis

Cara kerjanya, langkah demi langkah

7 langkah di seluruh platform - apa yang Anda lakukan di setiap langkah dan mengapa itu penting.

1

Take the norm consumption for the work you are reporting

Norma Produksi

For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.

Mengapa: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.

MasukanPositions in the reportNorm consumption per unitHasilNormative requirementSubstituted materials converted
2

Separate the losses the norm allows from real overrun

Faktor Sisa Material

Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.

Tangkapan layar, langkah 2: Separate the losses the norm allows from real overrun (Faktor Sisa Material, Cocokkan material pada formulir M-29)
Faktor Sisa Material: Separate the losses the norm allows from real overrun

Mengapa: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.

MasukanMaterials in scopeDelivery and cutting formHasilAllowed loss per materialPurchase quantity explained
3

Fix the volume of work the month actually completed

Kemajuan

Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.

Tangkapan layar, langkah 3: Fix the volume of work the month actually completed (Kemajuan, Cocokkan material pada formulir M-29)
Kemajuan: Fix the volume of work the month actually completed

Mengapa: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.

MasukanMeasurement on siteUnits the smeta usesHasilVolume completed this monthSame figure as the acceptance act
4

Record what was really issued and consumed

Inventaris Lapangan

Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.

Tangkapan layar, langkah 4: Record what was really issued and consumed (Inventaris Lapangan, Cocokkan material pada formulir M-29)
Inventaris Lapangan: Record what was really issued and consumed

Mengapa: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.

MasukanDeliveries booked inIssues to each positionHasilActual consumptionClosing stock counted
5

Compare actual against norm position by position

Kalkulasi pascakerja

Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.

Tangkapan layar, langkah 5: Compare actual against norm position by position (Kalkulasi pascakerja, Cocokkan material pada formulir M-29)
Kalkulasi pascakerja: Compare actual against norm position by position

Mengapa: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.

MasukanNormative requirementActual consumptionHasilVariance per positionVariance in money
6

Get every overrun explained and signed for

Rute persetujuan

Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.

Tangkapan layar, langkah 6: Get every overrun explained and signed for (Rute persetujuan, Cocokkan material pada formulir M-29)
Rute persetujuan: Get every overrun explained and signed for

Mengapa: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.

MasukanOverruns above thresholdWritten reason from the siteHasilAccepted explanationsRejected and referred on
7

Close the month with the cumulative position

Laporan

Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.

Tangkapan layar, langkah 7: Close the month with the cumulative position (Laporan, Cocokkan material pada formulir M-29)
Laporan: Close the month with the cumulative position

Mengapa: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.

MasukanVariance with explanationsPosition from previous monthsHasilSigned report for the monthCumulative position
Modul

Modul dalam playbook ini

7 / 190 modul platform

The market this case is written for

Rusia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Lainnya di Lapangan dan proyek

Lapangan dan proyek

Jalankan hari kerja di lokasi

Tutup hari kerja dengan benar: catat diary, bukukan jam kerja tenaga kerja dan alat berat, u…

4 langkah9 mntBuka
Lapangan dan proyek

Menjawab RFI

Ubah pertanyaan dari lapangan menjadi permintaan terlacak, arahkan ke pihak yang berwenang m…

3 langkah9 mntBuka